Notice of the ordinary meeting of the

Infrastructure Committee

Kōmiti Hanganga

Date:		Wednesday 26 August 2020
Time:		9.00a.m. 
Location:		Council Chamber, Civic House
			110 Trafalgar Street
			Nelson

Agenda

Rārangi take

Chair                Cr Brian McGurk

Deputy Chair   Cr Rohan O’Neill-Stevens

Members         Her Worship the Mayor Rachel Reese

                         Cr Yvonne Bowater

                         Cr Trudie Brand

                         Cr Mel Courtney

                         Cr Kate Fulton

                         Cr Judene Edgar

Cr Matt Lawrey

Cr Gaile Noonan

                         Cr Pete Rainey

                         Cr Rachel Sanson

                         Cr Tim Skinner

Pat Dougherty

Chief Executive

Quorum: 2

Nelson City Council Disclaimer

Please note that the contents of these Council and Committee Agendas have yet to be considered by Council and officer recommendations may be altered or changed by the Council in the process of making the formal Council decision.


Infrastructure Committee

Areas of Responsibility:

·    Bylaws, within the areas of responsibility

·    Transport network, including, roading network and associated structures, walkways, cycleways and shared pathways, footpaths and road reserve, street lighting, traffic management control and parking.

·    Water

·    Wastewater, including Bell Island Wastewater Treatment Plant

·    Stormwater and Flood Protection

·    Solid Waste management, including transfer stations and waste minimisation

·    Regional Landfill

·    Recycling

Delegations:

The committee has all of the responsibilities, powers, functions and duties of Council in relation to governance matters within its areas of responsibility, except where they have been retained by Council, or have been referred to other committees, subcommittees or subordinate decision-making bodies. 

The exercise of Council’s responsibilities, powers, functions and duties in relation to governance matters includes (but is not limited to):

·         Monitoring Council’s performance for the committee’s areas of responsibility, including legislative responsibilities and compliance requirements

·         Developing, approving, monitoring and reviewing policies and plans, including activity management plans and the Infrastructure Strategy

·         Reviewing and determining whether a bylaw or amendment, revocation or replacement of a bylaw is appropriate

·         Undertaking community engagement, including all steps relating to Special Consultative Procedures or other formal consultation processes

·         Approving submissions to external bodies or organisations, and on legislation and regulatory proposals

·         Hear, consider and decide all applications for road stopping

Powers to Recommend to Council:

In the following situations the committee may consider matters within the areas of responsibility but make recommendations to Council only (in accordance with sections 5.1.3 - 5.1.5 of the Delegations Register):

·         Matters that, under the Local Government Act 2002, the operation of law or other legislation, Council is unable to delegate

·         The purchase or disposal of land or property relating to the areas of responsibility, other than in accordance with the Long Term Plan or Annual Plan

·         Unbudgeted expenditure relating to the areas of responsibility, not included in the Long Term Plan or Annual Plan

·         Decisions regarding significant assets

 


Infrastructure Committee

26 August 2020

 

 

Page No.

 

1.       Apologies

1.1      An apology has been received from Councillor Fulton

2.       Confirmation of Order of Business

3.       Interests

3.1      Updates to the Interests Register

3.2      Identify any conflicts of interest in the agenda

4.       Public Forum

4.1      Nelsust - Presenting a signed letter by members of the community in support of lighting on the railway reserve

5.       Confirmation of Minutes

5.1      2 July 2020                                                                                  6 - 16

Document number M11986

Recommendation

That the Infrastructure Committee

1.    Confirms the minutes of the meeting of the Infrastructure Committee, held on 2 July 2020, as a true and correct record.

 

6.       Chairperson's Report  

 


 

7.       Draft 2021-31 Transport Activity Management Plan    17 - 28

Document number R14834

Recommendation

That the Infrastructure Committee

1.    Receives the report Draft 2021-31 Transport Activity Management Plan (R14834)  and its Attachment (A2435268); and

2.    Approves the Draft Transport Activity Management Plan 2021-31 (A2443789) as the version to inform the Long Term Plan 2021-31; and

3.    Notes that the Draft Transport Activity Management Plan 2021-31 will be updated following Council workshops in December 2020 and January 2021.

8.       Infrastructure Quarterly Report                                 29 - 97

Document number R19220

Recommendation

That the Infrastructure Committee

1.    Receives the report Infrastructure Quarterly Report (R19220) and its attachments (A2432783, A2428866 and A2430042).

 

Recommendation to Council

That the Council

1.    Approves additional unbudgeted funding of $382,210 to cover the impact of delays from COVID-19 on the following capital projects:

a.     $31,957 - Annesbrook Water Upgrade;

b.    $83,373 – St Vincent Street sewer renewal;

c.     $92,945 – Tahunanui Cycleway;

d.    $97,617 – Saxton Creek Stage 3;

e.     $14,318 -  Poormans Stream Culvert;

f.     $62,000 – Railway Reserve underpass; and

2.    Approves additional unbudgeted funding of $425,000 to fund the Hardy/Vanguard watermain renewal work to be undertaken in the 2020/21 financial year; and 

3.    Approves funding of $480,000 be brought forward from the 2021/22 financial year into the 2020/21 financial year, and $273,000 from the 2022/23 financial year into the 2020/21 financial year to allow the Tosswill Road Stormwater Upgrade to be completed ahead of schedule; and

4.    Approves funding of $1Million be brought forward from 2021/22 into the 2020/21 financial year to allow the Whakatu Drive (Storage World) Flood Protection upgrade to be completed in the 2020/21 financial year. 

 

  


Infrastructure Committee Minutes - 2 July 2020

 

 

Minutes of a meeting of the Infrastructure Committee

Held in the Council Chamber, Civic House, 110 Trafalgar Street, Nelson

On Thursday 2 July 2020, commencing at 11.31a.m.

 

Present:              Councillor B McGurk (Chairperson), Her Worship the Mayor R Reese, Councillors Y Bowater, T Brand, M Courtney, J Edgar, K Fulton, M Lawrey, R O'Neill-Stevens (Deputy Chair), G Noonan, P Rainey, R Sanson and T Skinner

In Attendance:    Group Manager Infrastructure (A Louverdis), Governance Adviser (E-J Ruthven), and Governance Support (K McLean)

Apologies :          Her Worship the Mayor (for lateness)

 

 

Karakia Timatanga


Committee members gave a karakia timatanga.

 

1.       Apologies

Resolved IC/2020/032

 

That the Infrastructure Committee

1.    Receives and accepts the apologies from Her Worship the Mayor for lateness.

McGurk/Sanson                                                                            Carried

Attendance:  Councillor Brand joined the meeting at 11.32a.m.

2.       Confirmation of Order of Business

There was no change to the order of business.

3.       Interests

There were no updates to the Interests Register, and no interests with items on the agenda were declared.

4.       Public Forum 

There was no public forum.

5.       Confirmation of Minutes

5.1      2 June 2020

Document number M10903, agenda pages 6 - 10 refer.

Resolved IC/2020/033

 

That the Infrastructure Committee

1.    Confirms the minutes of the meeting of the Infrastructure Committee, held on 2 June 2020, as a true and correct record.

Courtney/Sanson                                                                          Carried

 

6.       Chairperson's Report

Document number R18097, agenda pages 11 - 13 refer.

Attendance:  Her Worship the Mayor joined the meeting at 11.34a.m.

Councillor McGurk presented the report. 

Attendance:  Councillors Fulton and Lawrey joined the meeting at 11.39a.m.

Manager Transport and Solid Waste, Marg Parfitt, answered questions regarding the change to pay-by-plate parking meters, proposed temporary safety measures for the Franklyn Street/Waimea Road intersection, the changes to plastics recycling from 1 July 2020, and public transport patronage levels.

Resolved IC/2020/034

 

That the Infrastructure Committee

1.    Receives the report Chairperson's Report (R18097).

McGurk/O'Neill-Stevens                                                                 Carried

  

7.       Covid-19 Implications for Infrastructure

Document number R18058, agenda pages 14 - 16 refer.

Manager Capital Projects, Lois Plum, Manager Utilities, David Light, and Manager Transport and Solid Waste, Marg Parfitt, presented the report. 

Ms Plum provided updates regarding the Maitai Pathway Improvement project, the York Valley Road Resurfacing project, and the Bullivant Road Cycleway projects, noting that an alternative pathway to the Bullivant Road Cycleway would now be constructed.

Resolved IC/2020/035

 

That the Infrastructure Committee

1.    Receives the report Covid-19 Implications for Infrastructure (R18058).

Edgar/Bowater                                                                              Carried

 

8.       City Centre and Home Zone Speed Limits - Statement of Proposal for changes to the Speed Limit Bylaw

Document number R13686, agenda pages 17 - 56 refer.

Manager Transport and Solid Waste, Marg Parfitt, presented the report.  She noted the following corrections to the report, the Statement of Proposal and its attachments:

·    Iwa Road – maps to be updated to show the current speed limit of 30km/h;

·    Fifeshire Crescent – sections to be moved from 40km/h to 30km/h and included in list of ‘Home Zone’ streets; and

·      Hearings likely to take place in early September, rather than in August.

Ms Parfitt answered questions regarding:

·    Feedback received during the 30km/h speed limit imposed in the Central Business District during Covid-19 Alert levels 3 and 2, noting this was largely positive;

·    The reasons for excluding the Ring Roads, including Selwyn Place, from the Statement of Proposal, noting that the Ring Roads were more complex and should be considered as a whole as part of the Speed Management Plan next year;

·    The requirements of the Speed Limit Setting Rules, including establishing the Average Operating Speed in order to propose a new speed limit within 10km/h of the Average Operating Speed;

·    Whether the proposed National Speed Register could be included within the Statement of Proposal, to start to understand community views for additional areas where speed limits could be dropped;

·    The potential timeframes for implementing the outcomes of the consultation process;

·    Pedestrian-safety initiatives undertaken on Selwyn Place to increase awareness of pedestrian desire lines;

·    Whether it was feasible to include Selwyn Place within the Statement of Proposal at a lower speed limit of 40km/h or whether considering the Selwyn Place speed limit should be left for a later date;

·    Whether it was possible to consider a speed limit lower than 30km/h in the Central Business District through the proposed consultation process;

·    The rationale for including ‘Home Zone’ streets in the Statement of Proposal as being streets without a formed footpath;

·    The list of stakeholders to be directly contacted for feedback through the consultation process; and

·    Additional areas near to the Central Business District where high pedestrian numbers supported the potential for lower speed limits;

The meeting was adjourned from 12.59p.m to 1.47p.m, during which time Councillors Bowater and Noonan left the meeting.

Ms Parfitt, along with Senior Legal Adviser, Fiona McLeod, provided further advice that:

·    The ‘Scope’ section of the Statement of Proposal could be amended to note that, along with the options currently listed, Council may adopt a speed limit even lower than 30km/h, but that any speed limits adopted must still meet the Speed Limit Setting Rules; and

·    Council held insufficient data relating to Selwyn Place to be able to establish the Average Operating Speed, including not collecting data since Upper Trafalgar Street was closed, and that data should be collected and analysed before considering a change in speed limit for Selwyn Place.

Attendance:  Councillor Bowater and Noonan returned to the meeting at 1.54p.m.

Ms Parfitt, Ms McLeod, and Group Manager Infrastructure, Alec Louverdis, answered further questions regarding:

·    Whether it was possible to include Selwyn Place in the Statement of Proposal and collect data during the consultation process;

·    Whether the lower speed limits proposed for the Central business District and the ‘Home Zones’ could be put at risk if Selwyn Place were included in the Statement of Proposal, noting the insufficiency of data in relation to Selwyn Place;

·    What the implications for the rest of the Bylaw changes would be if the entire process was paused to enable data collection relating to Selwyn Place; and

·    Whether driver behaviour and average speed limits on Selwyn Place may have changed following the closure of Upper Trafalgar Street; and

·    Whether sectors of the community would be likely to oppose a speed limit reduction for Selwyn Place based on safety concerns.

Officers reiterated that to add Selwyn Place into the Statement of Proposal, and potentially decide to lower the speed limit when Council currently did not hold adequate data for Selwyn Place, could pose a legal risk to the rest of the proposed Bylaw changes.

Councillor Skinner, seconded by Councillor Brand, moved

That the Infrastructure Committee

1.     Receives the report City Centre and Home Zone Speed Limits - Statement of Proposal for changes to the Speed Limit Bylaw (R13686) and its attachments (A2398604,  A2403583, A239860, A2372939 and A2379502); and

2.     Agrees a Bylaw to set a permanent speed limit is the most appropriate way of addressing safety and access in the city centre (excluding the ring roads) and home zones; and

3.     Agrees the proposed amendments to the Speed Limits Bylaw 2011 (210) are the most appropriate form of bylaw and do not give rise to any implications under the New Zealand Bill of Rights Act 1990; and

4.     Agrees a summary of Statement of Proposal Amendment to the Speed Limits Bylaw 2011 (210) is not required; and

5.     Adopts the Statement of Proposal (A2372939 of Report 13686) relating to lowering of the speed limit from existing limit to 30km/h in the city centre (excluding the ring roads) and home zones; and

6.     Approves commencement of the Special Consultative Procedure, with the consultation period to run from 13 July 2020 to 14 August 2020; and

7.     Approves the Consultation Plan (A2379502 of Report 13686); and

8.     Notes that the Consultation Plan (A2379502 of Report 13686) will include sufficient steps to ensure the Statement of Proposal will be reasonably accessible to the public and will be publicised in a manner appropriate to its purpose and significance; and

9.     Notes that the Consultation Plan (A2379502 of Report 13686) will result in the Statement of Proposal being as widely publicised as is reasonably practicable as a basis for consultation.

The meeting was adjourned from 2.23p.m. to 3.01p.m, during which time Councillors Bowater and Noonan left the meeting.

Councillor Edgar, seconded by Her Worship the Mayor, moved an amendment:

That the Infrastructure Committee

1.     Receives the report City Centre and Home Zone Speed Limits - Statement of Proposal for changes to the Speed Limit Bylaw (R13686) and its attachments (A2398604,  A2403583, A239860, A2372939 and A2379502); and

2.     Agrees a Bylaw to set a permanent speed limit is the most appropriate way of addressing safety and access in the city centre including Selwyn Place (but excluding the rest of the ring roads) and home zones; and

3.     Agrees the proposed amendments to the Speed Limits Bylaw 2011 (210) are the most appropriate form of bylaw and do not give rise to any implications under the New Zealand Bill of Rights Act 1990; and

4.     Agrees a summary of Statement of Proposal Amendment to the Speed Limits Bylaw 2011 (210) is not required; and

5.     Adopts the Statement of Proposal (A2372939 of Report 13686) relating to lowering of the speed limit from existing limit to 30km/h in the city centre and home zones subject to the following amendments:

·        Adding Selwyn Place (but excluding the rest of the ring roads); and

·        Adding “adopting an even lower speed limit than 30km/h” to the list of bullet points under the heading “Scope of Council decisions following Consultation”; and

6.     Delegates to the Chair of the Infrastructure Committee to make the appropriate changes to the Statement of Proposal (A2372939 of Report R13686) to give effect to the amendments contained in clause 5, specifically:

·        Adding Selwyn Place (but excluding the rest of the ring roads); and

·        Adding “adopting an even lower speed limit than 30km/h” to the list of bullet points under the heading “Scope of Council decisions following Consultation”; and

7.     Directs officers to undertake further investigation relevant to the addition of Selwyn Place; and

8.     Approves commencement of the Special Consultative Procedure, with the consultation period to run from 13 July 2020 to 14 August 2020; and

9.     Approves the Consultation Plan (A2379502 of Report 13686); and

10.   Notes that the Consultation Plan (A2379502 of Report 13686) will include sufficient steps to ensure the Statement of Proposal will be reasonably accessible to the public and will be publicised in a manner appropriate to its purpose and significance; and

11.   Notes that the Consultation Plan (A2379502 of Report 13686) will result in the Statement of Proposal being as widely publicised as is reasonably practicable as a basis for consultation.

Committee members debated the amendment and views for and against were expressed.  The amendment was put.

Resolved IC/2020/036

That the Infrastructure Committee

1.    Receives the report City Centre and Home Zone Speed Limits - Statement of Proposal for changes to the Speed Limit Bylaw (R13686) and its attachments (A2398604,  A2403583, A239860, A2372939 and A2379502); and

2.    Agrees a Bylaw to set a permanent speed limit is the most appropriate way of addressing safety and access in the city centre including Selwyn Place (but excluding the rest of the ring roads) and home zones; and

3.    Agrees the proposed amendments to the Speed Limits Bylaw 2011 (210) are the most appropriate form of bylaw and do not give rise to any implications under the New Zealand Bill of Rights Act 1990; and

4.    Agrees a summary of Statement of Proposal Amendment to the Speed Limits Bylaw 2011 (210) is not required; and

5.    Adopts the Statement of Proposal (A2372939 of Report 13686) relating to lowering of the speed limit from existing limit to 30km/h in the city centre and home zones subject to the following amendments:

·        Adding Selwyn Place (but excluding the rest of the ring roads); and

·        Adding “adopting an even lower speed limit than 30km/h” to the list of bullet points under the heading “Scope of Council decisions following Consultation”; and

6.    Delegates to the Chair of the Infrastructure Committee to make the appropriate changes to the Statement of Proposal (A2372939 of Report R13686) to give effect to the amendments contained in clause 5, specifically:

·        Adding Selwyn Place (but excluding the rest of the ring roads); and

·        Adding “adopting an even lower speed limit than 30km/h” to the list of bullet points under the heading “Scope of Council decisions following Consultation”; and

7.    Directs officers to undertake further investigation relevant to the addition of Selwyn Place; and

8.    Approves commencement of the Special Consultative Procedure, with the consultation period to run from 13 July 2020 to 14 August 2020; and

9.    Approves the Consultation Plan (A2379502 of Report 13686); and

10.  Notes that the Consultation Plan (A2379502 of Report 13686) will include sufficient steps to ensure the Statement of Proposal will be reasonably accessible to the public and will be publicised in a manner appropriate to its purpose and significance; and

11.  Notes that the Consultation Plan (A2379502 of Report 13686) will result in the Statement of Proposal being as widely publicised as is reasonably practicable as a basis for consultation.

Edgar/Her Worship the Mayor                                                        Carried

The amendment was carried and became the substantive motion.

Resolved IC/2020/037

 

That the Infrastructure Committee

1.    Receives the report City Centre and Home Zone Speed Limits - Statement of Proposal for changes to the Speed Limit Bylaw (R13686) and its attachments (A2398604;  A2403583; A239860; A2372939  and A2379502); and

2.    Agrees a Bylaw to set a permanent speed limit is the most appropriate way of addressing safety and access in the city centre including Selwyn Place (but excluding the rest of the ring roads) and home zones; and

3.    Agrees the proposed amendments to the Speed Limits Bylaw 2011 (210) are the most appropriate form of bylaw and do not give rise to any implications under the New Zealand Bill of Rights Act 1990; and

4.    Agrees a summary of Statement of Proposal Amendment to the Speed Limits Bylaw 2011 (210) is not required; and

5.    Adopts the Statement of Proposal (A2372939 of Report 13686) relating to lowering of the speed limit from existing limit to 30km/h in the city centre and home zones subject to the following amendments:

·          Adding Selwyn Place (but excluding the rest of the ring roads); and

·          Adding “adopting an even lower speed limit than 30km/h” to the list of bullet points under the heading “Scope of Council decisions following Consultation”; and

6.    Delegates to the Chair of the Infrastructure Committee to make the appropriate changes to the Statement of Proposal (A2372939 of Report R13686) to give effect to the amendments contained in clause five, specifically:

·          Adding Selwyn Place (but excluding the rest of the ring roads); and

·          Adding “adopting an even lower speed limit than 30km/h” to the list of bullet points under the heading “Scope of Council decisions following Consultation”; and

7.    Directs officers to undertake further investigation relevant to the addition of Selwyn Place; and

8.    Approves commencement of the Special Consultative Procedure, with the consultation period to run from 13 July 2020 to 14 August 2020; and

9.    Approves the Consultation Plan (A2379502 of Report 13686); and

10.  Notes that the Consultation Plan (A2379502 of Report 13686) will include sufficient steps to ensure the Statement of Proposal will be reasonably accessible to the public and will be publicised in a manner appropriate to its purpose and significance; and

11.  Notes that the Consultation Plan (A2379502 of Report 13686) will result in the Statement of Proposal being as widely publicised as is reasonably practicable as a basis for consultation.

Skinner/Brand                                                                              Carried

 

9.       Nelson Regional Sewerage Business Unit 2020/21 Business Plan

Document number R13696, agenda pages 57 - 82 refer.

General Manager Regional Sewerage and Landfill, Nathan Clarke, presented the report. 

Mr Clarke answered questions regarding the Nelson Regional Sewerage Business Unit’s performance measures in the 2020/21 Business Plan, how carbon emissions were monitored, and the challenges involved in reducing carbon emissions.

Resolved IC/2020/038

 

That the Infrastructure Committee

1.    Receives the report Nelson Regional Sewerage Business Unit 2020/21 Business Plan (R13696) and its attachment (A2396455).

Brand/Edgar                                                                                 Carried

       

 

Karakia Whakamutunga


Committee members gave a karakia whakamutunga.

There being no further business the meeting ended at 3.34p.m.

Confirmed as a correct record of proceedings:

 

 

                                                       Chairperson                                     Date

        

 


 

Item 7: Draft 2021-31 Transport Activity Management Plan

 

Infrastructure Committee

26 August 2020

 

 

REPORT R14834

Draft 2021-31 Transport Activity Management Plan

     

 

1.       Purpose of Report

1.1      To approve the Draft Transport Asset Management Plan 2021-31 (TAMP) as the version to inform the Long Term Plan 2021-31 (LTP) and the Regional Land Transport Plan 2021-2028 (RLTP).

 

2.       Recommendation

That the Infrastructure Committee

1.    Receives the report Draft 2021-31 Transport Activity Management Plan (R14834)  and its Attachment (A2435268); and

2.    Approves the Draft Transport Activity Management Plan 2021-31 (A2443789) as the version to inform the Long Term Plan 2021-31; and

3.    Notes that the Draft Transport Activity Management Plan 2021-31 will be updated following Council workshops in December 2020 and January 2021.

 

 

3.       Background

3.1      Draft Activity Management Plans (AMP’s) are prepared for the approval of the Committee to inform development of the LTP’s. This TAMP will inform the development of the 2021-31 LTP and the development of the National Land Transport Programme via submission of the RLTP.

3.2      Following consultation and adoption of the LTP and RLTP, the AMP’s will be updated to align with the adopted LTP and RLTP. The final updated AMP’s will be brought back to Council early in 2021/22 for adoption.

3.3      The draft AMP takes account of previous Council and Committee resolutions and feedback at workshops on the proposed work programme and budgets. Officers have undertaken a high level review of budgets across Council activities however, the AMPs are at different stages of development and amendments may be required to the draft Plan once all AMPs have been received by their respective committees and, the cumulative effect of the AMPs has been considered at the workshops in December 2020 and January 2021.  Officers will update the Plan after these workshops. The final AMP will be brought to the Committee for approval after it has been updated to include decisions made during the LTP process.

4.       Discussion

4.1      The Draft TAMP sets out the background to Council’s transport system and includes details of the following:

·    Areas of focus for the activities during 2021-31;

·    Levels of Service;

·    The activity budgets for operations and maintenance, renewals and capital expenditure.

4.2      A series of transport related workshops have been held with Council this year to build the TAMP as detailed below. These workshops were held to confirm priorities for 2021-31 and seek direction from Council on any changes or additional priorities.

·    20 February 2020 - Transport AMP Introduction

·    26 February 2020 - Maintenance and Renewals

·    27 February 2020 - Surfacing and Pavements

·    4  March 2020 - Active Transport and Speed

·    19 March 2020 - Accessible Streets

·    12 May 2020 - Parking Strategy scope

·    26 May and 31 July 2020 - Public Transport (via the Regional Transport Committee)

·    2 July 2020 - Road Encroachment Policy

·    28 July 2020 - Transport AMP Summary

4.3      The following are the key outcomes from the numerous workshops:

4.3.1 Councils continued commitment toward developing and operating a transport system that seeks to deliver the following benefits:

- is effective at moving people and freight;

- is more accessible via all modes of transport;

- contributes to quality urban environments;

- feels safer and is safer;

- is more resilient;

- contributes to a healthy community and environment.

4.3.2 A fundamental shift in the approach to transport activity management planning which entails migrating from a deficiency database (which involves prioritising actions based on road hazards and deficiencies, and levels of risk) to Network Planning Mapping. The proposed approach minimises the capital works programme in the first three years of the AMP cycle and concentrates on development of an Activity Management Planning Map, with associated alignment with the Nelson Future Access Study (NFA) recommendations, as well as Council’s strategies, policies, plans and programmes.

4.4      At the 28 July 2020 workshop, Councillors signalled that the draft renewal programme and key projects were consistent with the desired focus to foster and support a more sustainable transport culture.

4.5      A second workshop was held with the Joint Councils Regional Transport Committees on 31 July 2020 to discuss the appropriate public transport budgets to include in the TAMP and Regional Public Transport Plan. Councillors signalled their support for improvements on staged approach beginning in Year 3 of the LTP when the new bus contract commences. Provisional budgets in the TAMP reflects this. 

4.6      Outcomes of the NFA consultation are not yet known, but common to all options is a short term package of interventions and the preliminary costs of these has been included in the TAMP budgets with significant investment of $9M per annum commencing in Year 6.

4.7      The Executive Summary of the Draft TAMP is appended as Attachment 1.

4.8      The Draft Transport Activity Management Plan (A2443789) is a significant document and is available on the Council’s website, 2021-31 Activity Management Plans page (www.nelson.govt.nz/2021-31-activity-management-plans). The document is very lengthy and includes narrative and business case format as required by Waka Kotahi (NZTA). The wording in Sections 8 and 9 of the draft is still in being developed with NZTA and is subject to change after 19 August 2020.

4.9      The draft TAMP is the culmination of a huge piece of work including no fewer than 9 workshops, close liaison with the Regional Transport Committee, Tasman District Council and a Council wide co-ordinated approach. It is a living document and will be updated/amended during the course of its life. 

5.       Options

5.1      The Committee has two options – either to approve the Draft TAMP or to not approve the Draft TAMP. 

 

Option 1: Approve the Draft TAMP 2021-31

Advantages

·   Meet requirements of Local Government Act 2002 and the Land Transport Management Act 2003.

·   Reflects the input of elected members during the numerous workshops.

Risks and Disadvantages

·   Nil

Option 2: Not approve the Draft TAMP 2021-31

Advantages

·    Nil

Risks and Disadvantages

·    Fail to meet requirements of Local Government Act 2002 and the Land Transport Management Act 2003.

 

6.       Conclusion

6.1      The Draft TAMP has been prepared to inform the LTP and the RLTP and will support Council in meeting its obligations under section 93 and Schedule 10 of the Local Government Act 2002.

 

Author:          Margaret Parfitt, Manager - Transport and Solid Waste

Attachments

Attachment 1:   A2435268  Executive Summary Transport Activity Management Plan 2021-31

 

 

Important considerations for decision making

1.   Fit with Purpose of Local Government

The Transport AMP supports the social and economic wellbeing of the Nelson community by enabling the movement of people and goods around the network in a way that creates a safer, more accessible, better connected and more resilient transport system.

2.   Consistency with Community Outcomes and Council Policy

Transport improvements support the following community outcomes:

“Our infrastructure is efficient, cost effective and meets current and future needs” and “Our communities are healthy, safe, inclusive and resilient.”

3.   Risk

Not adopting the draft TAMP will leave Council without a document to support the goal of developing and adopting the LTP and RLTP.

4.   Financial impact

There are no direct funding implications from the recommendation. The TAMP guides the funding in the proposed LTP and RLTP and will be subject to a consultation processes with the community.

5.   Degree of significance and level of engagement

This matter is of high significance because the adoption of an LTP and RLTP is a statutory requirement under the LGA Act 2002 and Land Transport Management Act. Consultation with the community will occur with the public advertising of the draft LTP and draft RLTP.

6.   Climate Impact

The draft TAMP considers the potential impacts and risks climate change presents to the City. Examples of proposed adaption, mitigation and leadership are demonstrated throughout the document.

7.   Inclusion of Māori in the decision making process

Māori will be approached directly for comment prior to calling for LTP public submissions.

8.   Delegations

The Infrastructure Committee has the power to consider and approve Activity Management Plans.

 

Areas of Responsibility:

o Transport network, including, roading network and associated structures, walkways, cycleways and shared pathways, footpaths and road reserve, street lighting, traffic management control and parking.

Delegations:

o Developing, approving, monitoring and reviewing policies and plans, including activity management plans and the Infrastructure Strategy.

 

 

 


Item 7: Draft 2021-31 Transport Activity Management Plan: Attachment 1

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

Item 8: Infrastructure Quarterly Report

 

Infrastructure Committee

26 August 2020

 

 

REPORT R19220

Infrastructure Quarterly Report

     

 

1.       Purpose of Report

1.1      To inform the Committee of the financial and non-financial results for the six months for the activities under its delegated authority.

 

2.       Recommendation

That the Infrastructure Committee

1.    Receives the report Infrastructure Quarterly Report (R19220) and its attachments (A2432783, A2428866 and A2430042).

Recommendation to Council

That the Council

1.    Approves additional unbudgeted funding of $382,210 to cover the impact of delays from COVID-19 on the following capital projects:

a.     $31,957 - Annesbrook Water Upgrade;

b.    $83,373 – St Vincent Street sewer renewal;

c.     $92,945 – Tahunanui Cycleway;

d.    $97,617 – Saxton Creek Stage 3;

e.     $14,318 -  Poormans Stream Culvert;

f.     $62,000 – Railway Reserve underpass; and

2.    Approves additional unbudgeted funding of $425,000 to fund the Hardy/Vanguard watermain renewal work to be undertaken in the 2020/21 financial year; and 

3.    Approves funding of $480,000 be brought forward from the 2021/22 financial year into the 2020/21 financial year, and $273,000 from the 2022/23 financial year into the 2020/21 financial year to allow the Tosswill Road Stormwater Upgrade to be completed ahead of schedule; and

4.    Approves funding of $1Million be brought forward from 2021/22 into the 2020/21 financial year to allow the Whakatu Drive (Storage World) Flood Protection upgrade to be completed in the 2020/21 financial year. 

 

 

3.       Background

3.1      Quarterly reports on performance are being provided to each Committee on the performance and delivery of projects and activities within their areas of responsibility.

3.2      The financial reporting focuses on the year to date performance (1 July 2019 to 30 June 2020) compared with the year-to-date (YTD) approved capital and operating budgets.

3.3      Unless otherwise indicated, all information is against approved operating budget, which is the 2019/20 annual budget plus any carry forwards, plus or minus any other additions or changes as approved by the Committee or Council.

3.4      More detailed project status reports are included (attachments) for the 37 projects that fall under the Infrastructure Committee. These have been selected if their budget is at least $250,000 for 2019/20, are multi-year projects with a budget over $1 Million, or have been assessed to be of particular interest to the Committee. The Provincial Growth Fund (PGF) funded projects have also been added.

3.5      Project status is analysed based on three factors; quality, time and budget.  From the consideration of these three factors the project is summarised as being on track (green), some issues/risks (orange), or major issues/risks (red).  Projects that are within 5% of their budget are considered to be on track in regards to the budget factor.

4.       COVID-19 cost impacts

4.1      The COVID-19 lockdown which lasted for Alert Levels 4 and 3 (total of seven weeks from 25 March to 13 May 2020) resulted, in the case of capital projects, stopping of all physical works on site and in the case of operational and maintenance contracts, the continuation of only essential services.

4.2      All capital works are back on site and operational aspects are back to business-as-usual.

4.3      As noted in several updates to committees and Council previously, officers have been processing a number of claims from contractors for both capital and operational contracts. These include, disestablishing and reestablishment of construction sites, time extension claims for the period of the shut-down, claims relating to social distancing protocols (which have slowed productivity on site) and claims for additional costs resulting from work now entering the wet season and changing site conditions.

4.4      All operational claims were processed in the 2019/20 financial year. However, the claims on capital projects have taken time to resolve and were not able to be finalised before the end of the 2019/20 financial year.

4.5      There were five capital projects on-site that were affected (these are detailed in the table over the page). The impact on the remaining capital projects has generally not been significant, with the main issue being delays of only a few weeks.

4.6      Due to the unprecedented nature of the event, it has taken some time to research and understand contractual impacts, and deal with a variety of submissions received from contractors including talking to other local authorities and Waka Kotahi NZ Transport Agency (NZTA).

4.7      For completeness, suspension notices were issued to all contractors as a result of the COVID-19 lockdown. This followed guidelines issued by  the Ministry of Business, Innovation & Employment (MBIE) guidelines, noted that the COVID-19 lockdown for contracts governed by NZS3910, constitute a variation and the associated costs of subsequent change or law are payable by the client.

4.8      Throughout the varying alert levels officers have worked closely with all contractors around claimable costs, with negotiations leaning heavily on existing relationships. The result is that agreement has been reached to pay only actual project related costs borne by the contractors over the period with all associated central government subsidies subtracted from their claims.

4.9      The COVID-19 lockdown has also resulted in a further unintended issue for Council to consider. As a result of the lockdown and late resumption of works on site, projects have moved into the winter season and this has made site conditions difficult resulting in additional cost and further delays. This has primarily affected the Railway Reserve underpass project and has resulted in increased costs due to the effects of wet weather. The main issue is that material that was to be re-used on site is no longer able to be used as it is now wet, thick, sludgy and full of clay.

4.10    Additional costs totalling $382,210 and have been processed under the normal NZS3910 terms of contract and are unable to be covered within the specific 2020/21 project budgets or contingencies so approval is required. The additional costs are summarised in the table below.

 

Project

COVID -19 lockdown

Wet weather

Annesbrook water upgrade           

$ 31,957 

St Vincent sewer renewal               

$ 83,373

Tahunanui Cycleway                          

$ 92,945

 

Saxton Creek Stage 3       

$ 97,617

Poormans stream culvert

$ 14,318

Railway Reserve underpass

 

$62,000

Total

$320,210

$62,000

4.11    Officers make the observation that this winter has been very wet and that there may be further additional costs for projects (that have been delayed by COVID19) as a result of wet weather. This will be monitored and reported back to the Committee.

5.       Hardy Street watermain upgrade

5.1      The Hardy/Vanguard watermain work has been progressing well and a construction date has been set for February 2021. However there has been an increase in costs due a variety of matters. To allow for future resilience and growth in this area, the pipe size diameter has been increased from 200mm to 300mm.  This has resulted in an increase cost of $206,000. Costs associated with traffic management has increased by $94,000 due to the complexity of the sites. There is also an increase in general costs above the original engineer’s estimate that was set pre-COVID. This has resulted in a $425,000 increase taking the project costs from $760,000 to $1,115,000.  Unfortunately officers were unable to include this in the Annual Plan process due to the timing of the confirmed costs received.

6.       Tosswill Road Stormwater

6.1      The Tosswill Road Stormwater upgrade project has been realigned to avoid going through private property and has allowed work, planned to be undertaken in 2021/22 and 2022/23 (as per the 2018-28 LTP), to be moved forward to the current financial year.

6.2      Officers are seeking to bring the total budget of $753,000 forward into the 2020/21 financial year - $480,000 from 2021/22 and $273,000 from 2022/23.

7.       Wakatu Drive (Storage World) Flood Protection

7.1      The project includes the installation of a new culvert under Whakatu Drive to allow secondary flow to drain from the Storage World site in response to the 2013 floods which affected the Whakatu Industrial Estate.

7.2      The original funding of $1.012M consulted on and in the current 2018-28 LTP was deferred and rephrased to allow further assessment of alternative options and a broader look at the wider Wakatu Estate requirements, with $80,000 in the current financial year to complete this work. The 2020/21 Annual Plan notes that detailed design and construction will be completed in 2021/22.

7.3      The project has moved at a quicker pace to allow the construction to be completed in the 2020/21 financial year and approval is sought to bring budget forward of $1M into 2020/21.

8.       Awatea Place sewer pump station

8.1      The Awatea Place sewer pump station project comprises two stages –the pump station itself and the installation of a storage tank in Beach Road. The overall project budget in the current LTP for this work is $7.1M.   

8.2      During the 2020/21 Annual Plan, the project was re-phased and the budget reduced from $3.65M to $1M. This re-phasing was necessary to better align with the timing of construction and finalisation of landowner agreements.

8.3      In order to move this project forward with pace however, the construction stages are been addressed separately with the storage tank planned to commence first in the current financial year.

8.4      The construction of the Awatea pump station is currently planned for 2021/22, but officers are hopeful that physical works will be able to commence in the current financial year. If this is possible, officers will address this in the next report to this Committee to ensure successful completion of this multi-year project.

8.5      The budget of $1M in the 2020/21 Annual Plan included for the construction of the storage tank and to finalise the design and consents for the pump station.

8.6      The revised estimate to undertake the above mentioned work has increased to $1.3M. The revised estimate follows additional operational requirements following detailed design of the storage tank as well as funding necessary to accelerate the Awatea pump station design that would allow for possible earlier commencement (2020/21 compared to 2021/22).

8.7      The Awatea Pump Station project was part of this Council’s submission to the “Shovel Ready” Crown Infrastructure Partners Fund (CIF).

8.8      Council will be receiving, as part of the “Three Waters stimulus and reform funding for councils” announced by central government in early August (subject of a separate report to the 20 August 2020 Council meeting), funding towards infrastructure projects. Advice received is that this funding can be used on projects submitted to the CIF to cover additional expenditure. Officers propose to direct this funding, once received, to this multi-year project to cover the additional expenditure.  

8.9      This funding opportunity has allowed the Beach Road storage tank (estimated at $1.3M) to be progressed immediately, allowing the appointment of specialist sheet piling sub-contractors. 

9.       Tenders Awarded

9.1      Tenders above $300,000 awarded under delegated authority in the last two quarters are listed below:

 

Project Name

Awarded to

Tender Price

Railway Reserve/Princes Drive underpass

KB Contracting and Quarries Ltd

$  421,746

Tahunanui Pathways Parkers to Beach Road

Downer NZ Ltd

$1,477,049

Maitai path upgrade

Asphalt & Construction Ltd

$  531,638

10.     Financial Results

10.1    There is a variance between actual and budgeted staff costs within cost centres but overall, actual staff costs are in line with budget. Finance is currently reviewing Staff Costs to reduce the variances going forward

10.2    Profit and Loss by Activity

Notes

·    The “Total Operating Budget” differs from the “Total Annual Plan Budget” in that it includes carry forwards and reallocations made after the final approval of the Annual Plan.

·    Base Expenditure is expenditure that happens year after year, for example yearly contracts or operating expenses.

·    Programmed Expenditure is planned work, or there is a specific programme of works. For example, painting a building.

·    Unprogrammed Expenditure is reactive or unplanned in nature, for example responding to a weather event. Budgets are included as provisions for these expenses which are unknown.

 

 

 

 

 

 

 

 

 

 

Operating Revenue

Operating Expenditure

 

 

 

 

 

 

 

Capital Expenditure

Terms Used

Ahead/behind – this indicates that the variance is due to timing, or that it is not yet known whether the variance will continue for the full year. This should be clarified in the commentary.

Over/under – this indicates that a budget has been overspent or underspent, and that it is likely there is an actual cost saving or overrun. This should be made clear by the commentary.

10.3    Transport

10.3.1 Subsidised Roading expenditure is less than budget by $233,000. Staff costs are over budget by $459,000 due to costs being allocated differently than expected. Staff costs are balanced to budget overall within the Transport activity. Un-budgeted COVID-19 response costs of $103,000 have been incurred.

Subsidised Roading costs are under budget across a variety of codes, in particular relating to delays caused by the COVID-19 shut-down. Major variances (over $50,000) include bridge maintenance ($61,000 under budget), footpath maintenance ($78,000 under budget), road safety promotion ($67,000 under budget), travel demand management ($157,000 under budget), condition inspections and data collection ($105,000 under budget) and TRACKS and SATURN modelling ($62,000 under budget).

10.3.2 Unsubsidised Roading income is less than budget by $65,000. Corridor Access Request recoveries are under budget by $91,000 due to works being on hold during the COVID-19 lockdown. This income is partially offset by below budget costs. Unsubsidised Roading expenditure is less than budget by $1.18 million. Staff costs are behind budget by $394,000 due to costs being allocated differently than expected. Staff costs are balanced to budget overall within the Transport activity. Champion Road roundabout grant is $470,000 under budget. The Champion Road roundabout grant has been reduced to $150,000 and deferred to 2020/21.  Depreciation is behind budget by $199,000. The end of year depreciation additions had not been completed at the time of writing this report.

10.3.3 Parking Regulation income is less than budget by $140,000. Parking officers did not patrol during the final quarter of the year (April – June 2020) due to the impacts of COVID-19.  

10.3.4 Parking and CBD Enhancement income is less than budget by $266,000. Parking meter fees were suspended during the final quarter of the year (April – June 2020) due to the impacts of COVID-19.

10.3.5 Public Transport income is less than budget by $88,000. New Zealand Transport Agency income is directly linked to costs, which are also under budget. Public Transport expenditure is less than budget by $332,000. Staff costs are behind budget by $123,000 due to costs being allocated differently than expected. Minor improvements expenditure is under budget by $210,000. SuperGold Card Concession expenditure is under budget by $51,000 because of COVID-19.

10.4    Wastewater

10.4.1 Wastewater income is less than budget by $124,000. Commercial Trade Waste income is under budget by $128,000. The reduction in Trade Waste volumes is assumed to be a result of the COVID-19 lockdown.

10.4.2 Wastewater expenditure is less than budget by $209,000. Staff costs are under budget by $174,000 due to costs being allocated differently than expected.  Atawhai Rising Main investigation costs are $87,000 under budget. Depreciation expenditure is under budget by $101,000. The end of year depreciation additions had not been completed at the time of writing this report. Wastewater reticulation reactive maintenance costs are over budget by $64,000 due to work required on reactive events, and unbudgeted COVID-19 response costs of $54,000 have been incurred.

10.5    Nelson Regional Sewerage Business Unit investment return income and share of expenditure are currently expected to be on-budget, however final full year figures were not available at the time of writing this report.

10.6    Stormwater

10.6.1 Stormwater expenditure is under budget by $221,000. Stormwater reticulation reactive maintenance costs are $108,000 under budget due to fewer reactive events than anticipated. Preliminary capital costs are $62,000 behind budget due to timing – the final calculation of these costs is still being completed. Depreciation expenditure is under budget by $69,000. The end of year depreciation additions had not been completed at the time of writing this report.

10.6.2 Flood Protection expenditure is less than budget by $78,000. Staff costs are under budget by $113,000 due to costs being allocated differently than expected. Depreciation costs are $51,000 over budget. The end of year depreciation additions had not been completed at the time of writing this report.

10.7    Water Supply

10.7.1 Water Supply income is greater than budget by $380,000. This 4.3% increase over budget could include factors such as the new water meters recording water usage with greater accuracy, as well as increased water usage during the COVID-19 lockdown. 

10.7.2 Water Supply expenditure is less than budget by $84,000. Staff costs are over budget by $71,000 due to costs being allocated differently than expected. Unbudgeted COVID-19 response costs of $59,000 have been incurred. Water reticulation reactive maintenance costs are under budget by $61,000. Insurance costs are under budget by $50,000 and electricity costs are over budget by $50,000.

10.8    Recycling expenditure is greater than budget by $89,000. Kerbside contract costs are $216,000 under budget. Unbudgeted fibre subsidy costs of $232,000 have been paid.

11.     Commentary on Capital Projects

11.1    All capital projects with a budget greater than $250,000 in this financial year or have an overall project budget of over 1M across the life of the project have a project sheet in Attachment 1 of this report. Officers note that the project sheets have changed as a result of the Capital Project team now utilising a new project management tool called Project Online. The reports are produced directly from this tool.

11.2    Orphanage Stream bunding between Saxton Road East and Suffolk Road, (a flood mitigation project following the extreme 2013 rainfall event), has been re-phased into 2020/21 and 2021/22. It is expected the project will be underway in October/November 2020.

11.3    Seafield Terrace Road Reinstatement has been delayed due to complexities with the resource consent, however construction is now scheduled to begin in 2020/21.

11.4    The Gracefield Sewer Diversion project is tracking one year ahead of programme with construction now anticipated to be completed in late 2020, ahead of the original programme of June 2022. Work is expected to commence approximately October 2020.

11.5    The odour control measures at the Neale Park Pump Station are now complete.

11.6    The budget for Saxton Creek Upgrade stage 4 (Main Road Stoke to Sea) in 2020/21 allows for the finalisation of landowner agreements, detail design and resource consents, with construction planned for 2021/22 onwards. As Council is aware, an application for funding of stage 4 Saxton Creek upgrade project was made to the COVID Response and Recovery Fund (CRRF). Council was advised on 24 July 2020 that it had been successful in being awarded $7.5M. The project must have a shovel in the ground by the end of May 2021.

11.7    The Tahunanui Cycleway Project Stage 2 continues to progress ahead of schedule even with the COVID-19 implications.

11.8    Footpath work was extensive during the 2019/20 year with 706 lineal meters renewed and 426 lineal meters added to the network. Work carried out this year has included improvement to connections between the Railway Reserve and Vanguard Street, Days Track, Kawai Street, Echodale Place, Main Road Stoke at Saxton Field, Tipahi Street, Grove Street, Songer Street path widening, Waimea Road at Bishopdale and Annesbrook Drive in conjunction with cycle path and water main work.

11.9    Resurfacing work was completed with 15.1 lane lineal kilometres completed in chip seal and 1.2 lane lineal kilometres completed in asphalt in the 2019/20 year. The 2019/20 work included resurfacing the Trafalgar Street Bridge adding 30 years to its expected life. The resealing program was interrupted during COVID-19 and as a result not all lower priority streets were able to be completed. However, officers and Council’s maintenance contractor worked to maximise the opportunity provided by COVID-19 alert level 4 to carry out essential repairs to the Main Road Stoke and Salisbury Road links which would have otherwise caused major traffic disruption. The forward works programme for the 2020/21 year is being finalised and will be included in the next quarterly report.

11.10  Under road maintenance and minor improvements, work was carried out on Arapiki Road between Main Road Stoke and the Ridgeway. COVID-19 did result in some delays and as a result the related work that will improve the crossing points for pedestrians at the Ridgeway intersection has continued into the 2020/21 year. In a separate project, following repeated crashes in the area, a 40m length of guard rail on Waimea Road near Quarantine Road has been upgraded and accompanied by streetlight improvements.

11.11  Electronic ticketing. A great deal of planning, preparatory testing and education has been required in the last year to culminate in the Bee Card launch on 3 August. Over a number of years, since 2014, officers have worked closely with the current NBus operator, the Regional Consortium, and Waka Kotahi (NZTA) to bring this project on line. More recently this became a truly cross-council project with teams from transport, finance, customer services, IT, libraries, people and capability, and communications all involved in bringing the much anticipated improvement to fruition. 

11.12  Bus shelters. In addition to the new shelters installed as part of the Tahunanui/Annesbrook Drive cycle path, two new shelters were erected outside Countdown on Main Road Stoke and another was repurposed to provide shelter for inward bound bus patrons near the Black Cat store on Annesbrook Drive.

11.13  Parking meter renewal. The city parking meters were replaced with new machines using PaybyPlate technology and became operational on 29 June. Some budget has been moved into the current year to enable ongoing education around new meter use and to update the enforcement equipment used by Council contractors. Eighty-eight new meters have been installed. Users can now pay for parking using coins, direct debit or paywave or by use of a parking App. New meters have been well received by retailers who have commented on the effect of freeing up parking for customers. The one hour free parking remains in place and can be used in 15 minute segments, but free parking is capped at one hour free per license plate in a 24 hour period.  At the time of report writing early data from 3-23 July indicates a favourable change in behaviour of long stay parkers. This data was collected during school holidays and while parking wardens were carrying out a more educative role than an enforcement one. Officers will have more recent data on parking patterns to speak to at the meeting.

12.     Provincial Growth Fund Projects

12.1    Raised Table at Waikawa and Beach Road – this project is well underway and being built as part of the Tahunanui Pathways Project.

12.2    Maitai path improvements – work on widening the footpath between Collingwood Street and Bridge Street has commenced.

13.     Status Report Update

13.1    Sand Bags

To inform a future Infrastructure report, officers will investigate what policy and practice other New Zealand Councils have in this area. Advice is being taken from Civil Defence. In addition, messaging about sandbags in general for Council communication will be improved (how they work, where to get them, how to install/dispose of).

13.2    Nelson Tasman Joint Regional Landfill (NTRLBU)

The Committee has requested further work on the matter regarding receiving material from Hazardous Activities and Industries List sites (HAIL). This is on the NTRLBU General Manager’s work programme and he is working towards gathering the necessary information to present back to the NTRLBU Board and then back to the Committee.

13.3    Hampden Terrace/Waimea Road Intersection Closure

An officer report was to have come to the Infrastructure Committee, within six months of the commencement of the trial closure.  Unfortunately at alert level 4 for COVID-19 all traffic counts were suspended and data required for the monitoring report was unavailable. Traffic counting has resumed and the report is planned to come to the October Infrastructure committee. Updates on the project have been provided on Shape Nelson for the purposes of gathering ongoing feedback.

14.     Commentary on operational projects

14.1    There is a detailed status report for one operational project (Inflow and Infiltration) included in the attachments.  This project has been selected for quarterly reporting as it has been assessed to be of particular interest to the Committee.

14.2    These operational projects are assessed on the same factors – quality, time and budget and noted as being on track, with some issues/risks or with major issues/risks. These project updates are appended in Attachment 1.

14.3    The Annual Plan has approved an organic food waste trial for this financial year using budget from the Climate change reserve. Officers have completed procurement and Community Compost will undertake the work which is expected to commence in October 2020.  

14.4    Waste minimisation.  A range of waste minimisation activities were undertaken in 2019/20, including continuing the promotion of home composting, promoting reuse through activities such as Secondhand Sunday, and initiating campaigns focusing on reducing single-use item such as the Cup Bond Subsidy programme.  Many of these activities have been delivered in partnership with Tasman District Council, and work is now underway on a more comprehensive programme for 2020/21, including a new branding campaign. It should be noted that the COVID-19 shut down required some activities to be suspended but this period did provide an opportunity to investigate and develop resources for deconstruction versus demolition/building waste.

14.5    Recycling collection changes commenced on 1 July and a comprehensive communications plan led up to that cessation of collection plastic types 3, 4, 6 and 7. It is too soon to report on contamination rates but contractors have not rejected more recycling bins, nor has council received complaints regarding the change, both positive signs of the success of the communication strategy.

14.6    The Kawai Street Innovative Streets project engagement was delayed due to COVID-19 but a community BBQ has since been held and ideas and feedback continue to be gathered to inform the detailed business case and planning. The implementation phase of the project will depend on funding and an application has been submitted to the second round of Waka Kotahi NZTA’s Innovative Streets for People fund which attracts a 90% subsidy. At the time of writing this report the outcome of the funding round was unknown and officers will report any update at the meeting.   

14.7    Proposed changes to the speed limit bylaw have been out for public consultation during July and August. Hearings are scheduled for 9 September and a deliberations report is scheduled to come to this committee on 30 September. 

14.8    On 13 July 2020 NZTA announced any fare revenue shortfall and direct operating cost increases for public transport services, as a result of the COVID-19 disruptions between July and December 2020, would be 100% funded. This 100% subsidy will be conditional on councils contributing at least their planned 2020/21 local share into public transport services. It will be reviewed for the following six months (January 2020 to June 2021) at a later date. In Nelson/Tasman the Nbus remained fare free until electronic ticketing (Bee Card) came on stream on 3 August. This forgone revenue will also be met by NZTA. Patronage patterns have been encouraging since Alert level 1 was introduced and whilst fares were free levels are sitting at 93% of last year’s patronage.

14.9    Total Mobility continued to be available throughout all alert levels. Usage patterns over the last few months show the clear impact of COVID-19 on trips made under various alert levels and the increased subsidy made available by Waka Kotahi throughout. On 1 July the scheme returned to normal.

Workshops

14.10  A number of workshops have been held since February to inform the Draft Transport Activity Management plan. These include workshops relating to Active Transport, Speed Management, and Maintenance and Renewals. In addition a workshop was held with elected members to discuss on what any future Parking Strategy should consider. The intention is to tender the work later in the year.

14.11  A workshop was held on 19 March to inform content of the Council’s submission to Waka Kotahi regarding collection of rule changes known as the Accessible Streets Regulatory Package. These rules are designed to improve safety for footpath users, encourage active modes of transport, and support the creation of more liveable and vibrant towns and cities. At the time of report writing the timeframe for central government decisions regarding the package and any potential implementation of rule changes is uncertain but is likely to be after the General Election in September. 

14.12  A workshop was held with elected members in early July to discuss the development of a Road Encroachment Policy to refresh the existing Road Occupation Policy (2006).

14.13  A workshop was held with elected members to discuss the proposed changes to the water supply by-law. Officers are planning to present the draft water supply by-law to the Committee by the end of the calendar year, prior to going out for public consultation.

15.     Other notable achievements, issues or matters of interest

15.1    Risks

15.1.1 The biggest risks through the last two quarters has been the effect of COVID-19, and the resulting alert level impacts.

15.1.2 Implications have been additional claims being lodged for onsite work, these include, shutting down and opening up sites and suspension of contracts through alert level 4. Ongoing risks are productivity loss, and potential moving between alert levels, extending construction into the winter months, along with the unknown impact on new work market pricing.

15.1.3 Risks to the successful completion of other projects includes land negotiations, resource consents and Cultural Impact Assessments.

15.2    Lindavia Intermedia in the Maitai Dam. Council officers recently found a low-density population of non-toxic Lindavia in the Maitai Dam. Officers are unable to ascertain how this algae entered the Maitai Dam. Lindavia is a non-toxic nuisance algae. It will not affect the quality of the Council’s drinking water supply, but does have the potential, if it blooms, to affect the day to day operations of the water treatment plant (increase in operational costs). Officers are confident at this stage that it will have minimal impact on the water treatment plant infrastructure and that it will have no effect on the Council’s ability to continue to supply safe potable water to the city. Council officers continue to investigate this issue and have a monitoring programme in place to monitor for changes.

16.     Key Performance Measures

16.1    As part of the development of the Long Term Plan 2018-28 (LTP) Council approved levels of service, performance measures and targets for each activity.  There are 35 performance measures that fall under the Infrastructure Committee.  The final results for each performance measure will be reported on through the Annual Report.

·    On track

·    Not on track

·    Achieved

·    Not achieved

16.2    Attachment 2 lists all performance measures within the Infrastructure Committee delegations, their status and commentary for the quarter.

 

 

 

 

 

 

 

 

 

16.3    Overall 28 out of the 35 performance measures can be confirmed as being achieved for the end of the financial year.

16.4    Twenty three out of 25 utilities performance measures can be confirmed as being achieved for the end of the financial year. Two performance measure relating to water reliability have not yet been measured as this requires the latest round of residential water meter readings, which was delayed due to COVID-19 and is currently being processed. 

16.5    Three of the seven transport measures were achieved, one not measured due to COVID-19 lockdown and three not achieved.

16.5.1   The road safety measure for transport was not achieved. There were two fatal crashes and 17 crash events resulting is serious injury on the local road network in the 2019/20 year. The number of crash events exceeds the 2018/19 year total by 1 so the reduced target has not been met.

16.5.2   The walking and cycling measure for transport as measured by the Nelson residents’ survey was not achieved. Sixteen percent of respondents indicated they journeyed to work by walking or cycling which is short of the 20% target. More encouraging is the census survey result which shows the number of Nelson students cycling or walking to education facilities exceeds national percentages with a combined total of 37.2% locally compared to 24.1% nationally.

16.5.3   The Nbus patronage growth measure was not achieved due to the COVID-19 lockdown.

16.5.4   The footpath quality surface measure was not measured due to COVID-19 lockdown, preventing the surveying being carried out. Both the 2017/18 and 2018/19 surveys however demonstrated that Council achieved this performance measure and a continual programme of footpath improvement work has been carried out since. 

16.6    Two of the three solid waste measures were achieved relating to e-waste and composting. One measure was not achieved relating to volumes of waste to landfill. At year end the total waste to landfill was 2% down on the 69,000 tonnes last year, however there was a significant drop in April due to COVID-19 which has skewed the overall result. Tracking indicates that without COVID-19 the overall result would have seen an increase of waste to landfill of 6%.

16.7    The review of performance for the final quarter for the Infrastructure Committee is included in this report, with project reports and performance measure updates attached, please note that the reports are presented in a new format.

 

17.     Options

17.1    The Committee has two decisions to consider.

17.2    With respect to the additional contractual implications from the COVID-19 lockdown – to either approve additional funding or not approve additional funding. Officers support Option 1.

 

Option 1: Approve additional funding

Advantages

·   Overspend as a result of COVID-19 is covered

·   Contractually robust

·   Builds on already solid contractor relationships 

Risks and Disadvantages

·   None

Option 2: Not approve additional funding

Advantages

·    None

Risks and Disadvantages

·   Reputational risk with contractors

·   Contractual disputes

 

17.3    With respect to bringing budget forward to this financial year – either approve or not approve this. Officers support Option1.      

 

 

Option 1: Approve bringing budgets forward

Advantages

·   Projects can progress earlier than expected in this financial year

·   Key to stimulating local economy

·    Shows leadership in difficult economic times

·    Builds on existing Council/contractor  relationships

Risks and Disadvantages

·   None

Option 2: Not approve bringing budgets forward

Advantages

·    Programme stays as is

Risks and Disadvantages

·   Economic stimulus slowed down

·   Reputational risk with contractors

 

 

 

 

Author:          Lois Plum, Manager Capital Projects

Attachments

Attachment 1:   A2432783 - Key page for new Quarterly one page reports

Attachment 2:   A2428866 - Infrastructure Quarter 4 one page reports

Attachment 3:   A2430042 - Infrastructure Key Performance Measures

 

 

Important considerations for decision making

1.   Fit with Purpose of Local Government

The construction projects are all part of the current LTP and 2020/21 Annual plan, meeting the requirements of fit with purpose of Local Government.

The projects meet all the well-being’s in the areas of environmental, economic and social.

2.   Consistency with Community Outcomes and Council Policy

The projects relating to COVID-19 impacts are all part of the Long Term Plan, and Annual plan and are in the construction phase. The Hardy Street Construction project is also part of the Long Term Plan and the 2020/21 Annual plan, with a construction start date of approximately February 2021.

The Beach Road facility will assist in stimulating the economy a key focus of this Council.

3.   Risk

The request for COVID-19 related funding will cover the additional costs associated with meeting the required contractual terms as set during Alert level 4 and 3. If funding is not approved Council will be at risk of contractual challenge.

If the request for additional funding for the Hardy Street Project is not approved, the project will be shelved until funding becomes available – impacting the service levels.

The request for additional funding for the Beach Road Storage facility is to allow an early contract start in early September. The Beach Road storage facility will be pushed into 2021/22 if funding is not secured.

4.   Financial impact

The additional expenditure of projects on site were as a direct result of the COVID19 pandemic and lock down.

The other requests for funding are as a result of officers been able to bring work forward, which will stimulate the economy. These projects are already either in the current LTP, Annual Plan and future LTP.

5.   Degree of significance and level of engagement

Engagement was undertaken with the Contractors to ensure a fair and reasonable outcome could be achieved on all contractual matters.

Engagement for Hardy Street works has been completed with all local retailers and affected parties, which includes the best time for construction, to minimise impact on retail.

Engagement for Beach Road facility has been completed and extensive consultation has taken place.

6.   Climate Impact

Funding requests are associated with existing projects that were designed and approved previously.

The Beach road facility is designed for overflow storage to reduce potential spills into the estuary, along with taking into account additional rainfall events as a result of climate change.

7.   Inclusion of Māori in the decision making process

No engagement with Māori has been undertaken in preparing this report.

8.   Delegations

The Infrastructure Committee has the following delegation:

Areas of Responsibility:

·    Transport network, including, roading network and associated structures, walkways, cycleways and shared pathways, footpaths and road reserve, street lighting, traffic management control and parking.

·    Water

·    Wastewater, including Bell Island Wastewater Treatment Plant

·    Stormwater and Flood Protection

Delegations:

The committee has all of the responsibilities, powers, functions and duties of Council in relation to governance matters within its areas of responsibility, except where they have been retained by Council, or have been referred to other committees, subcommittees or subordinate decision-making bodies. 

Powers to Recommend:

Unbudgeted expenditure relating to the areas of responsibility, not included in the Long Term Plan or Annual Plan

 

 


Item 8: Infrastructure Quarterly Report: Attachment 1

PDF Creator


Item 8: Infrastructure Quarterly Report: Attachment 2


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


Item 8: Infrastructure Quarterly Report: Attachment 3