Notice of the ordinary meeting of the

Infrastructure Committee

Kōmiti Hanganga

Date:		Tuesday 2 June 2020
Time:		9.00a.m. 
Location:		Council Chamber, Civic House
			110 Trafalgar Street
			Nelson

Agenda

Rārangi take

Chair               Cr Brian McGurk

Deputy Chair   Cr Rohan O’Neill-Stevens

Members         Her Worship the Mayor Rachel Reese

                       Cr Yvonne Bowater

                       Cr Trudie Brand

                       Cr Mel Courtney

                       Cr Kate Fulton

                       Cr Judene Edgar

Cr Matt Lawrey

Cr Gaile Noonan

                       Cr Pete Rainey

                       Cr Rachel Sanson

                       Cr Tim Skinner

Pat Dougherty

Chief Executive

Quorum: 7

Nelson City Council Disclaimer

Please note that the contents of these Council and Committee Agendas have yet to be considered by Council and officer recommendations may be altered or changed by the Council in the process of making the formal Council decision.

Infrastructure Committee

Areas of Responsibility:

·    Bylaws, within the areas of responsibility

·    Transport network, including, roading network and associated structures, walkways, cycleways and shared pathways, footpaths and road reserve, street lighting, traffic management control and parking.

·    Water

·    Wastewater, including Bell Island Wastewater Treatment Plant

·    Stormwater and Flood Protection

·    Solid Waste management, including transfer stations and waste minimisation

·    Regional Landfill

·    Recycling

Delegations:

The committee has all of the responsibilities, powers, functions and duties of Council in relation to governance matters within its areas of responsibility, except where they have been retained by Council, or have been referred to other committees, subcommittees or subordinate decision-making bodies. 

The exercise of Council’s responsibilities, powers, functions and duties in relation to governance matters includes (but is not limited to):

·       Monitoring Council’s performance for the committee’s areas of responsibility, including legislative responsibilities and compliance requirements

·       Developing, approving, monitoring and reviewing policies and plans, including activity management plans and the Infrastructure Strategy

·       Reviewing and determining whether a bylaw or amendment, revocation or replacement of a bylaw is appropriate

·       Undertaking community engagement, including all steps relating to Special Consultative Procedures or other formal consultation processes

·       Approving submissions to external bodies or organisations, and on legislation and regulatory proposals

·       Hear, consider and decide all applications for road stopping

Powers to Recommend to Council:

In the following situations the committee may consider matters within the areas of responsibility but make recommendations to Council only (in accordance with sections 5.1.3 - 5.1.5 of the Delegations Register):

·       Matters that, under the Local Government Act 2002, the operation of law or other legislation, Council is unable to delegate

·       The purchase or disposal of land or property relating to the areas of responsibility, other than in accordance with the Long Term Plan or Annual Plan

·       Unbudgeted expenditure relating to the areas of responsibility, not included in the Long Term Plan or Annual Plan

·       Decisions regarding significant assets

 


N-logotype-black-wideInfrastructure Committee

2 June 2020

 

 

Page No.

 

1.       Apologies

Nil

2.       Confirmation of Order of Business

3.       Interests

3.1      Updates to the Interests Register

3.2      Identify any conflicts of interest in the agenda

4.       Public Forum

5.       Confirmation of Minutes

5.1      7 May 2020                                                    6 - 12

Document number M9841

Recommendation

That the Infrastructure Committee

1.    Confirms the minutes of the meeting of the Infrastructure Committee, held on 7 May 2020, as a true and correct record.

     

6.       Chairperson's Report                        13

Document number R17032

Recommendation

That the Infrastructure Committee

1.    Receives the report Chairperson's Report (R17032).

 

 

7.       COVID-19 Implications for Infrastructure                            14 - 18

Document number R17024

Recommendation

That the Infrastructure Committee

1.    Receives the report COVID-19 Implications for Infrastructure (R17024).

 

 

8.       Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan                                            19 - 39

Document number R13697

Recommendation

That the Infrastructure Committee

1.    Receives the report Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan (R13697) and its attachment (A2375131); and

2.    Receives the Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan (A2375131).

 

       

COnfidential Business

9.       Exclusion of the Public

Recommendation

That the Infrastructure Committee

1.       Excludes the public from the following parts of the proceedings of this meeting.

2.       The general subject of each matter to be considered while the public is excluded, the reason for passing this resolution in relation to each matter and the specific grounds under section 48(1) of the Local Government Official Information and Meetings Act 1987 for the passing of this resolution are as follows: 

 

Item

General subject of each matter to be considered

Reason for passing this resolution in relation to each matter

Particular interests protected (where applicable)

1

Infrastructure Committee Meeting - Public Excluded Minutes -  7 May 2020

Section 48(1)(a)

The public conduct of this matter would be likely to result in disclosure of information for which good reason exists under section 7.

The withholding of the information is necessary:

·    Section 7(2)(i)

     To enable the local authority to carry on, without prejudice or disadvantage, negotiations (including commercial and industrial negotiations)

 

 

 

  


Infrastructure Committee Minutes - 7 May 2020

 

 

Minutes of an extraordinary meeting of the Infrastructure Committee

Via Audio-visual (Zoom), held on Thursday 7 May 2020, commencing at 10.01a.m.

 

Present:             Councillor B McGurk (Chairperson), Her Worship the Mayor
R Reese, Councillors Y Bowater, T Brand, M Courtney, J Edgar,
K Fulton, M Lawrey, R O'Neill-Stevens, G Noonan, P Rainey,
R Sanson and T Skinner

In Attendance:    Chief Executive (P Dougherty), Group Manager Infrastructure (A Louverdis), Group Manager Corporate Services (N Harrison), Governance Adviser (E-J Ruthven), and Governance Support
(K McLean)

Apologies :         Nil

 

Karakia Timatanga

 

Councillor McGurk gave a karakia timatanga.

 

1.       Apologies

There were no apologies.

Attendance:  Councillor Rainey left the meeting at 10.03a.m.

2.       Confirmation of Order of Business

There was no change to the order of business.

3.       Interests

There were no updates to the Interests Register, and no interests with items on the agenda were declared.

4.       Public Forum 

There was no public forum.

5.       Confirmation of Minutes

5.1      20 February 2020

Document number M6710, agenda pages 7 - 13 refer.

Resolved IC/2020/012

 

That the Infrastructure Committee

1.    Confirms the minutes of the meeting of the Infrastructure Committee, held on 20 February 2020, as a true and correct record.

Edgar/O'Neill-Stevens                                                               Carried

6.       Chairperson’s Report

Document number R14838, agenda pages 14 - 16 refer.

Councillor McGurk presented his report. 

Chief Executive, Pat Dougherty, and Group Manager Infrastructure, Alec Louverdis, answered questions regarding the streamlining of Procurement Policy processes to assist in the economic recovery following the Covid-19 shutdown, the timeframe for these changes, and how this linked to the upcoming review of the Procurement Policy.

Attendance:  Councillor Rainey returned to the meeting at 10.19a.m.

Councillor Courtney, seconded by Councillor Fulton moved:

That the Infrastructure Committee

1.    Receives the report Chairpersons Report (R14838); and

2.    Endorses the streamlined procurement process essential to the economic recovery of Nelson.

Mr Louverdis answered questions regarding kerbside recycling collection volumes, when the Materials Recovery Facility might become operational again, and communication regarding Council’s decision to cease collecting plastics 3, 4, 6 and 7 from 1 July 2020.

Mr Dougherty answered further questions regarding the streamlined Procurement Policy processes, and how they related to non-traditional subcontractors such as social enterprises.  A question was raised with respect to the food waste trial.

A point of order was raised that, in accordance with Standing Order 24.2(c), discussion of the food waste trial was an item not before the meeting.  The point of order was upheld.

Councillor Edgar, seconded by Councillor Noonan moved an amendment to the second clause of the motion:

2.    Notes the streamlined procurement process essential to the economic recovery of Nelson.

The amendment was put and became the substantive motion.

Resolved IC/2020/013

 

That the Infrastructure Committee

1.    Notes the streamlined procurement process essential to the economic recovery of Nelson.

Edgar/Noonan                                                                          Carried

Resolved IC/2020/014

 

That the Infrastructure Committee

1.    Receives the report Chairpersons Report (R14838); and

2.    Notes the streamlined procurement process essential to the economic recovery of Nelson

Courtney/Fulton                                                                       Carried

Attendance:  The meeting was adjourned from 10.48a.m. to 10.55a.m.

7.       COVID-19 Implications on Infrastructure

Document number R16991, agenda pages 17 - 20 refer.

Manager Capital Projects, Lois Plum, presented the report. 

Manager Transport and Solid Waste, Marg Parfitt, answered questions regarding the provision and use of public transport during Covid-19 alert levels 4 and 3, levels of glass recycling and single plastic use, support for food businesses to choose compostable takeaway containers and cups, and eftpos machine facilities at the transfer station.

Ms Plum answered additional questions regarding taking on additional project managers to manage the upcoming workload

Committee members acknowledged the work of officers and noted their appreciation for the smooth continuity of essential services during alert levels 4 and 3.

Resolved IC/2020/015

 

That the Infrastructure Committee

1.    Receives the report COVID-19 Implications on Infrastructure (R16991); and

2.    Notes the challenges facing the Infrastructure Group as a result of the COVID-19 shut-down including the risk of delivery and increased costs.

 

O'Neill-Stevens/Edgar                                                               Carried

 

8.       Accessible Streets Regulatory Package 2020: Submission to the Ministry of Transport

Document number R16939, agenda pages 21 - 40 refer.

Manager Solid Waste and Transport, Marg Parfitt, presented the report.  She answered questions regarding central Government investment in cycle lanes, footpath size and accessibility issues, cyclist use of footpaths and designating particular areas for pedestrians only.

Councillor Bowater left the meeting at 11.37a.m. due to internet connectivity issues.

Resolved IC/2020/016

 

That the Infrastructure Committee

1.    Receives the report Accessible Streets Regulatory Package 2020: Submission to the Ministry of Transport  (R16939) and its attachment (A2365818); and

2.    Approves retrospectively the Nelson City Council’s submission to the Ministry of Transport (A2365818) attached to Report R16939)

Noonan/Sanson                                                                         Carried


A division was called:

For

Cr McGurk (Chairperson)

Her Worship the Mayor

Cr Brand

Cr Courtney

Cr Edgar

Cr Fulton

Cr Lawrey

Cr O'Neill-Stevens

Cr Noonan

Cr Rainey

Cr Sanson

Against

Cr Skinner

Absent

Cr Bowater

The motion was carried 11 - 1.

 

9.       Infrastructure Fees and Charges 2020-2021

Document number R13674, agenda pages 41 - 46 refer.

Manager Solid Waste and Transport, Marg Parfitt, presented the report.

Councillor Bowater returned to the meeting at 11.44a.m.

Group Manager Infrastructure, Alec Louverdis, and Chief Executive, Pat Dougherty, answered questions regarding the 5% increase in landfill fees proposed through the Annual Plan 2020/21 and how this interacted with the proposed 8% increase in Solid Waste charges at the Pascoe Street Transfer Station.

Councillor Edgar, seconded by Councillor O’Neill-Stevens, moved:

That the Infrastructure Committee

1.    Receives the report Infrastructure Fees and Charges 2020-2021 (R13674) and its attachment (A2325209); and 

2.    Notes that the Consumer Price Index will be applied to all Utilities and Roading charges effective 1 July 2020; and

3.    Approves an 8% increase to Solid Waste charges at the Pascoe Street transfer station as reflected in Attachment A2325209 of Report R13674, effective 1 July 2020, subject to confirmation through the Annual Plan 2020/21.

Mr Louverdis answered questions regarding the standard timing and consultation practices regarding increased fees and charges considered annually, and how this had been affected this year due to Covid-19.

Ms Parfitt answered further questions regarding costs and practices in relation to the disposal of tyres, and confirmed that fees and charges were set at a level to recover costs.

Committee members discussed the motion and views for and against were expressed.

Resolved IC/2020/017

 

That the Infrastructure Committee

1.    Receives the report Infrastructure Fees and Charges 2020-2021 (R13674) and its attachment (A2325209); and 

2.    Notes that the Consumer Price Index will be applied to all Utilities and Roading charges effective 1 July 2020; and

3.    Approves an 8% increase to Solid Waste charges at the Pascoe Street transfer station as reflected in Attachment A2325209 of Report R13674, effective 1 July 2020, subject to confirmation through the Annual Plan 2020/21.

Edgar/O'Neill-Stevens                                                               Carried

Attendance:  The meeting was adjourned from 12.20p.m. until 1.02p.m., during which time Her Worship the Mayor left the meeting.

       

10.     Exclusion of the Public

Resolved IC/2020/018

 

That the Infrastructure Committee

1.    Excludes the public from the following parts of the proceedings of this meeting.

2.    The general subject of each matter to be considered while the public is excluded, the reason for passing this resolution in relation to each matter and the specific grounds under section 48(1) of the Local Government Official Information and Meetings Act 1987 for the passing of this resolution are as follows:

Bowater/Brand                                                                         Carried

 

Item

General subject of each matter to be considered

Reason for passing this resolution in relation to each matter

Particular interests protected (where applicable)

1

Nelmac - Utilities Maintenance and Operations Contract

 

Section 48(1)(a)

The public conduct of this matter would be likely to result in disclosure of information for which good reason exists under section 7

The withholding of the information is necessary:

·   Section 7(2)(i)
To enable the local authority to carry on, without prejudice or disadvantage, negotiations (including commercial and industrial negotiations)

2

Wastney Terrace Stormwater Upgrade - Property Negotiations

Involves land easement negotiations

Section 48(1)(a)

The public conduct of this matter would be likely to result in disclosure of information for which good reason exists under section 7

The withholding of the information is necessary:

·   Section 7(2)(i)

     To enable the local authority to carry on, without prejudice or disadvantage, negotiations (including commercial and industrial negotiations)

The meeting went into confidential session at 1.04p.m. and resumed in public session at 2.23p.m.

Karakia Timatanga

Councillor McGurk gave a karakia whakamutunga.

 

There being no further business the meeting ended at 2.24p.m.

 

Confirmed as a correct record of proceedings:

 

 

 

                                                   Chairperson              Date

         

 


 

Item 6: Chairperson's Report

 

Infrastructure Committee

2 June 2020

 

 

REPORT R17032

Chairperson's Report

     

 

1.       Chairs foreword

1.1      My Chair’s report provides an update on external funding received by this Council for projects and how this work will benefit the region.

 

 

 

2.       Recommendation

That the Infrastructure Committee

1.    Receives the report Chairperson's Report (R17032).

 

 

3.       Provincial Growth Fund

3.1      As noted in the officer report as part of this agenda, we have been successful in receiving Provincial Growth Funding for several projects in Nelson. These projects are crucial to the economic recovery of the region and officers are working at making these a reality.

3.2      The benefits to our community are however more than just economic. In the case of the Maitai footpath widening for example, the project will also provide much needed social and safety benefits to all users of the path.

3.3      One of the key criteria of the funding is that the work needs to commence with urgency and what this means is that all projects will need to be fast tracked to achieve the full benefits.

3.4      I’m hoping that the committee will share my delight in us receiving funding for these projects and support officers in making them a reality.  

 

Author:          Brian McGurk, Chairperson

Attachments

Nil


 

Item 7: COVID-19 Implications for Infrastructure  

 

Infrastructure Committee

2 June 2020

 

 

REPORT R17024

COVID-19 Implications for Infrastructure  

     

 

1.       Purpose of Report

1.1      To advise the Committee on the effects the COVID-19 lockdown has had on the Infrastructure Group

 

 

2.       Recommendation

That the Infrastructure Committee

1.    Receives the report COVID-19 Implications for Infrastructure  (R17024).

 

 

 

3.       Background

3.1      The COVID-19 lockdown and moving into different alert levels has slowed Council’s capital delivery programme affecting projects to varying degrees.

3.2      The anticipated original expenditure for Capital Projects delivery of $23.9 million to the end of June will not be achieved. Work recommenced on construction sites on 27 April and the updated expected forecast spend is $20.2 million.

3.3      The implication of the lockdown and changing alert levels will result in a carry-over of around $2.9m putting the capital projects expected spend for 2020/21 at around $31.1m. This is in addition to any carry forward included in the draft Annual Plan. It is also noted that further changes to 2020/21 figure will have been included in the Annual Plan documentation post completion of this report (R17024).

3.4      The “back-to-work” protocols have resulted in some slowing of onsite work, however the crews are learning new ways of achieving outcomes.

3.5      Council continues to process several time extension claims for additional costs from contractors as a result of COVID-19 shut-down.

4.       Provincial Growth Fund 

4.1      Council’s application to the Provisional Growth Fund (PGF), which included around 85 separate projects, has been successful with funding for five roading projects secured as shown below.

 

Project

Estimated Total Cost (plus GST)

NCC Beach Road Raised Table

$180,000

Bullivant road cycleway

$100,000

Planting & Tracks Eves Valley

$100,000

Maitai pathway improvement (Collingwood to Bridge)

$600,000

York road resurfacing

$250,000

Total

$1,230,000

4.2      NCC as administering authority for the NRSBU and Regional Landfill Business Units, co-ordinated applications for these resulting in the success of three projects – two for the Regional Landfill and one for the NRSBU.

4.3      An internal management group has been set up to ensure the success of these projects. Project managers have been assigned to each project and discussions with MBIE staff have taken place.

4.4      Conditions of funding include providing MBIE with regular monthly progress updates and commencement of works within two months of COVID-19 Alert Level 3 being lifted – i.e. two months from 14 May 2020.

4.5      The Maitai path improvement project will be fast tracked and is focused on the section between Collingwood and Bridge Street, taking the path from 1.4m to between 3 and 3.5m in width, ensuring a safe width for all users.

5.       Discussion

Public transport

5.1      Public transport on Nbus continued throughout levels 4 and 3 on a timetable based on Saturday services. Patronage was down by approximately 90% throughout this time. The full timetable service resumed on Thursday 14 May, with the exception of the Late Late bus which will not recommence until hotel bars and nightclubs resume operation.

5.2      Service operators and Council continue to follow national guidance regarding extra cleaning, contact tracing, physical distancing on buses, and avoiding driver customer interaction by making the service free of charge. Discussions are held with Waka Kotahi NZ Transport Agency (NZTA) on a regular basis and at this stage officers are cautiously optimistic that fares will remain free until 30 June. Officers have requested free travel is extended until 4 August for Nelson to coincide with the confirmed date for electronic ticketing going live locally. When the electronic ticketing goes live NZTA has a strong expectation that fares will be recovered as they can be in a contactless manner with no driver interaction i.e. using tag on/tag off.

5.3      Officers are monitoring bus patronage under Alert Level 2. Capacity on buses is limited due to the physical distancing requirements. If there is a need to provide extra services at peak times on Nbus routes, the cost is approximately $2,000 per bus per week. At the time of writing this report the exact number of buses required is uncertain. NZTA has signalled it would provide additional funding until June 30 to meet demand.

Total Mobility

5.4      Reduced fares on Total Mobility services will continue to be available until 30 June 2020 (irrespective of New Zealand’s COVID-19 Alert Level), after which time normal fare payment processes will resume.

Transport and roading matters

5.5      The Trafalgar Street/Halifax Street traffic signals will be changed to a full-time Barnes Dance crossing from late June. The Barnes Dance crossing will allow pedestrians to cross both perpendicularly and diagonally across the intersection to improve pedestrian levels of service and reduce waiting times. This intersection change was proposed as part of the response to COVID-19 and is being trialled before consideration for other intersections. An education campaign about the changes is planned.  With the exception of the Waimea Road crossing at Hampden Street School and the NZTA controlled signals at Tahunanui all other pedestrian phases at Nelson traffic signals remain automated to reduce COVID-19 infection risk.

5.6      The transport team has been working closely with officers in the City Development team on potential changes to the City Centre streets post COVID-19. That project has been discussed at Council in a separate report. In addition Council has submitted a funding application to NZTA in relation to the early investigative and engagement work that commenced in Kawai Street. Funding decisions will be made the first week in June.

5.7      A workshop was held with councillors on 12 May to provide guidance on the scope of Parking Strategy development, pending approval of the draft Annual Plan.

5.8      The combined Nelson/Tasman public transport review work continues and is being workshopped through the Regional Transport Committees.

           Waste minimisation

5.9      A number of activities were put on hold during the COVID-19 lock down, however, this hiatus did provide an opportunity to look at a new work programme investigating deconstruction versus demolition for building waste for future engagement with the building sector, with a project initiated to support this for the Mediterranean Warehouse. During Level 2 work is underway to develop and finalise the work programme for 2020/21.

Recycling, landfill and transfer station

5.10    The Material Recycling Facility (MRF) was closed for level 4 and 3. During this time collected recycling in the yellow lidded bins was landfilled. As of 18 May the MRF was again opened and all kerbside recycling collections will be sorted as per usual. The public drop off for recycling was also opened on 18 May.

5.11    Throughout level 4 and 3 glass has been collected and sent to Auckland for sorting and recycling. Total weight collected is similar to normal.

5.12    The Pascoe Street transfer station, public recycling drop off and reuse shop were all re-opened on 18 May.

5.13    The Joint Regional landfill has been open through all levels.

           Utilities

5.14    As previously reported, the services managed within the Utilities Business Unit were an essential service and have continued to operate throughout COVID-19. Business as usual has returned for managing these services under level 3 and 2.

Activity Management Plans

5.15    It is unclear at this stage what impact COVID-19 will have on the development and delivery of the 2021–31 Activity Management Plans (AMPs), particularly with Council priorities, growth projections and financial affordability. Officers will provide an update on this at the next Infrastructure Committee meeting in July.   

Capital Projects

5.16    Capital Project Delivery – an update of major projects is provided below.

·    Tahunanui Cycle Path, Annesbrook watermain, Saxton Creek stage 3, St Vincent Street sewer, Poormans stream culvert and the Railway Reserve cycle underpass work are all back on site.

·    A risk to the successful completion of these works will be delays from weather as we move into the winter months.

·    Public consultation has continued and been managed via mail-drops, and Shape Nelson.

·    The streamlined procurement process has allowed early conversations with contractors, allowing open discussions on risk, timing and constructability.  Officers are also looking at flexibility around timelines so the contractors can better plan their work programmes.

·    Anzac to Maitai shared path work will start construction following the completion of the Tahunanui Cycle path work as it is the same crew doing this project – approximately September 2020.

·    Officers are expecting the Beach Road Storage Facility August 2020 Gracefield diversion and Awatea Pump Station approximately October 2020.

 

Author:          Lois Plum, Manager Capital Projects

Attachments

Nil

 

 


 

Item 8: Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan

 

Infrastructure Committee

2 June 2020

 

 

REPORT R13697

Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan

     

 

1.       Purpose of Report

1.1      To receive the Draft 2020/21 Nelson Tasman Regional Landfill Business Unit (NTRLBU) Business Plan (Business Plan).

 

 

2.       Recommendation

That the Infrastructure Committee

1.    Receives the report Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan (R13697) and its attachment (A2375131); and

2.    Receives the Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan (A2375131).

 

 

 

3.       Background

3.1      The NTRLBU was established by the Nelson City Council (NCC) and Tasman District Council (TDC) in April 2017 and became operational from 1 July 2017.

3.2      The approved Terms of Reference (TOR) require that the Draft Business Plan be presented annually to each Council by 31 October each year and allow for each Council to provide feedback on the draft Business Plan.   

3.3      The Draft 2020/21 Business Plan was prepared by the NTRLBU Acting General Manager and was presented to the Board who resolved on 13 September 2019, as follows:

 

 

 

Moved Cr Maling/Cr Walker

RLBU19-09-2

That the Nelson-Tasman Regional Landfill Business Unit:

2.       receives and approves the Draft Business Plan 2020/21 and the proposed landfill charges for 2020/2021 subject to minor changes approved by the Chairman; and

3.       recommends the Draft Business Plan 2020/21 be presented to the Tasman District Council and Nelson City Council for their feedback.

CARRIED

3.4      The NTRLBU can only formally adopt the Draft Business Plan after receiving and considering comment from the two Councils and is then required to present the final Business Plan to the Councils by 31 May for inclusion in each Council’s draft Annual Plan.

3.5      The Infrastructure Committee considered the Draft Business Plan on the 21 November 2019 and provided feedback to the Acting General Manager. That feedback required:

3.5.1   more details of the studies required for the Long Term Capital Programmes; and

3.5.2   a timeline of when the Hazardous Activities and Industries List review would be undertaken.

3.6      The Committee resolved:

Resolved IC/2019/001

Receives the report Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan (R11477) and its attachment (A2279731); and

Provides comments back to the Nelson Tasman Regional Landfill Business Unit Acting General Manager on the draft 2020/21 Business Plan (A2279731)”.

3.7      The General Manager considered that feedback, amended the Business Plan and presented that to the NTRLBU Board on the 1 May 2020, where they resolved as follows:

Resolved RLBU/2020/002   

That the Nelson Tasman Regional Landfill Business Unit:

1.   Receives the report Nelson Tasman Nelson Tasman Regional Landfill Business Plan 2020-2021(RR16987) and its attachment (A2375357 and A2375131); and

2.   Receives and approves the Draft Business Plan 2020/21 (A2375131) subject to minor changes approved by the Chairman; and

3.   Recommends the Draft Business Plan 2020/21 be presented to the Tasman District Council and Nelson City Council.

4.       Discussion

4.1      The revised Draft Business Plan is appended as Attachment 1 and the newly appointed General Manager will be present at the meeting to answer any questions.

           Options

4.2      The Committee has already consider the draft Business Plan and provided feedback to both the Acting General Manager and General Manager, who has addressed that feedback in the revised Business Plan and presented that back to the Board for approval. The Board has subsequently approved the Business Plan.

4.3      All that remains is for both Council’s to receive that the Business Plan in line with the TOR.

5.       Conclusion

5.1      The NTRLBU Draft 2020/21 Business Plan has been approved by the NTRLBU Board and is now presented to the two Councils.

 

Author:          Alec Louverdis, Group Manager Infrastructure

Attachments

Attachment 1:   A2375131 - NTRLBU Business Plan 2020-2021

 

 

Important considerations for decision making

1.   Fit with Purpose of Local Government

The NTRLBU is a joint committee constituted pursuant to the provisions of Schedule 7 to the Local Government Act 2002. A regional landfill contributes to the four Local Government well-beings of social, economic, environmental and cultural.

2.   Consistency with Community Outcomes and Council Policy

The draft Business Plan is required under the TOR to be received by Council and included in the 2020/21 Annual Plan.

3.   Risk

This report is of low risk as the Committee has already considered the Business Plan and provided comment back to the Acting General Manager. The risk of not receiving the Business Plan is that this could delay the NTRLBU implementing their Business Plan for 2020/21.

4.   Financial impact

The NTRLBU 2020/21 Business Plan signals an increase in landfill fees and charges and this has been included in the 2020/21 Annual Plan.

5.   Degree of significance and level of engagement

The NTRLBU is a Joint Committee of the two Councils and its activities are included in the Long Term Plans and Annual Plans of each Council.  Consultation is undertaken by both Councils in the preparation and adoption of these plans.

6.   Climate Impact

The draft Business Plan includes a long-term objective on greenhouse gas emissions with the commitment to measure and reduce greenhouse gas emissions from the landfill.

7.   Inclusion of Māori in the decision making process

No engagement with Māori has been undertaken in preparing this report, but iwi have representation on the Board.

8.   Delegations

The Infrastructure Committee has the following delegations to consider the Nelson Tasman Regional Landfill Business Plan:

5.6.1       Relevant Areas of responsibility: 

•       Regional Landfill

5.6.2       Delegations:

The exercise of Council’s responsibilities, powers, functions and duties in relation to governance matters includes

•      Developing, approving, monitoring and reviewing policies and plans, including activity management plans and the Infrastructure Strategy

 

 


Item 8: Nelson Tasman Regional Landfill Business Unit 2020/21 Business Plan: Attachment 1

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator