N-logotype-black-wide

OPEN

ATTACHMENTS

 

Ordinary meeting of the

 

Works and Infrastructure Committee

 

Thursday 22 October 2015

Commencing at 9.00am

Wakapuaka Hall

460 State Highway 6

Main Road, Wakapuaka

Nelson

 

ATTACHMENTS UNDER SEPARATE COVER

TABLE OF CONTENTS

PAGE

 

8      Transportation Asset Management Plan 2015-2025

2      A1156705 - Transport Asset Management Plan 2015-2025         2                                  


Transport

Asset Management Plan

2015 - 25

 

 

 

 

 

 

 

 

 

 

 

 

 

Part 1

 

 

 
 

 

 


N-logotype-black-wide

 


Quality Assurance Statement

 

Version No.

Date

Description

Prepared by

Reviewed by

Approved by

1

24/3/14

draft for
assets review

R Palmer

Assets Team

A Louverdis

2

5/5/14

draft including financial and work programmes

R Palmer

Assets Team

A Louverdis

3

19/5/14

draft for SLT

R Palmer

SLT

A Louverdis

4

5/6/14

draft for Council workshop

R Palmer

Councillors

A Louverdis

5

18/12/14

Approved by

Council

R Palmer

SLT

A Louverdis

6

15/10/15

Approved by Council to match LTP

R Palmer

Councillors

Council

 

Yellow highlighted text indicates changes to version 5 as a result of the LTP

Blue highlighted text indicates changes to version 5 as a result of the other factors

 

 


CONTENTS PAGE

Part 1

Executive Summary. 1

1................ Introduction.. 12

1.1.                Purpose. 12

1.2.                Plan structure. 12

1.3.                The transport activity. 12

1.4.                The stakeholders 13

1.5.                The end users 14

1.6.                The legislative context 15

1.7.                Strategic context 15

2................ WHAT ARE THE FUTURE DEMAND ISSUES TO CONSIDER?. 19

2.1.                Arterial Traffic. 21

2.2.                Accessibility. 22

2.3.                Sustainability. 23

2.4.                Environmental risks 24

2.5.                Regional considerations 24

2.6.                Funding. 25

2.7.                Funding Risk. 26

2.8.                Transport network resilience. 26

2.9.                Consultation. 27

2.10.             Procurement strategy. 28

2.11.             Prioritisation process for projects 28

3................ What’s the direction?. 29

3.1.                Context 29

3.2.                What are the impacts of moving people and goods?. 31

3.3.                A brief history of street design and improvements programme. 32

3.4.                What are the options?. 33

3.5.                A balanced approach. 34

4................ The delivery of a balanced approach. 35

4.1.                Defining the Targets and the Delivery. 35

4.2.                Local roads, walking, cycling and schools 35

4.3.                Arterial traffic. 48

4.4.                Safety. 50

4.5.                Public transport 54

4.6.                Parking. 55

4.7.                Value for Money principles 57

4.8.                Systems to Measure, Monitor and Report on Performance Indicators 59

Part 2

5................ Technical Performance measures/Asset management Systems/lifecycle. 63

5.1.                Asset lifecycle. 63

5.2.                Asset failure modes 64

5.3.                Roads 64

5.4.                Road structures 67

5.5.                Pedestrian network. 70

5.6.                Cycle network. 74

5.7.                Public Transport 77

5.8.                Traffic control and equipment, street lighting, signs and markings 79

5.9.                Safety. 81

5.10.             Parking. 84

6................ Valuation.. 87

7................ Financial Forecasts and Development Contributions. 88

8................ Risk management. 90

9................ Performance Monitoring and Improvement Plan.. 99

 

List of Appendices

Appendix A             Relevant transport legislation. 102

Appendix B             Nelson’s Strategies and Policies 103

Appendix C             Strategic documents, studies and models providing demand data. 107

Appendix D            Growth indicators 109

Appendix E             How the focus areas link with the government’s, NZ Transport Agency’s and Council’ s strategic documents 142

Appendix F             Definition of Levels of Service. 145

APPENDIX G          STREETS WITHOUT FOOTPATHS. 148

Appendix H            Annual Peak travel time delays on Rocks Road and Waimea Road. 149

Appendix I              Previous LEVEL OF SERVICE and why they have changed. 152

Appendix J              SUMMARY activity descriptions 153

Appendix K             Regional Land Transport Programme 2015-2021. 161

APPENDIX l            10 YEAR LONG TERM PLAN – PROGRAMME. 166

Appendix M            minor improvement and footpaths Priority List 171

Appendix N            Footpath Rehabilitation Sites 175


List of Tables

Table 1.1                 Te Tau Ihu Settlement Bill Proposed Redress 14

Table 1.2                 Council Community Outcomes 17

Table 2.1                 NZ Transport Agency Financial Assistance Rates 25

Table 4.1                 Level of Service Relating to Walking and Cycling. 36

Table 4.2                 Level of Service Relating to Maintenance of Footpaths 36

Table 4.3                 Footpath Rating Descriptions and Summary. 38

Table 4.4                 Level of Service Relating to Local Road Maintenance and Renewals 40

Table 4.5                 Practical seal lives in Nelson. 42

Table 4.6                 Proportion of Road Surface in Nelson by Type and Traffic Volume. 43

Table 4.7                 Level of Service Relating to Efficient Transport System.. 48

Table 4.8                 Level of Service relating to Road Network and Its Services 49

Table 4.9                 Level of Service Relating to Road Safety. 50

Table 4.10              Level of Service Relating to Road Safety at Intersections 51

Table 4.11              Level of Service Relating to Road Safety and Cyclists 52

Table 4.12              Level of Service Relating to Road Safety and Pedestrians 52

Table 4.13              Level of Service Relating to Public Transport Services 54

Table 4.14              Level of Service Relating to Short Stay Parking. 56

Table 4.15              Level of Service Relating to Parking. 56

Table 4.16              Level of Service Relating to Long Stay Parking. 56

Table 4.17              Level of Service Relating to Public Satisfaction. 58

Table 5.1                 Key Stages in the Asset Lifecycle. 63

Table 5.2                 Range of Asset Failure Modes 64

Table 5.3                 Road Surface Valuation. 64

Table 5.4                 Road Basecourse Valuation. 64

Table 5.5                 Road Surface Data Reliability Analysis 66

Table 5.6                 Road Base Data Reliability Analysis 66

Table 5.7                 Bridges Valuation. 67

Table 5.8                 Retaining Wall Valuation. 67

Table 5.9                 Road Structure Data Reliability Analysis 69

Table 5.10              Footpaths Valuation. 70

Table 5.11              Walkways Valuation. 70

Table 5.12              Footway Data Reliability Analysis 72

Table 5.13              Cycleways Valuation. 74

Table 5.14              Cycle Infrastructure Data Reliability Analysis 76

Table 5.15              Fares as at July 2014. 78

Table 5.16              Street Signs Valuation. 79

Table 5.17              Line Marking Valuation. 80

Table 5.18              Streetlights Valuation. 80

Table 5.19              Traffic Signals Valuation. 80

Table 5.20              Car Parking Valuation. 84

Table 5.21              Car Parking Spaces in Nelson and Stoke. 84

Table 5.22              Car Parking Data Reliability Analysis 85

Table 7.1                 Forecasted Subsidised Annual Expenditure. 88

Table 8.1                 Likelihood Ratings (Semi Qualitative Measure) 90

Table 8.2                 Semi-Quantitative Measures of Consequence and Areas of Impact 90

Table 8.3                 Risk Priority Rating (Semi Quantitative) 91

Table 8.4                 Business Risk Schedule. 92

Table 8.5                 Asset Risk Schedule. 96

Table D.1                Peak Hour Volumes 109

Table D.2                Population projections, 2015-2045. 139

Tabel F.1                 Definition of Levels of Service. 145

Table F.2                 Nelson Arterial Traffic Study Network Performance Summary Statistics 147

Table F.3                 Nelson Arterial Traffic Study Network Performance Summary Statistics 147

 


List of Figures

Figure 1.1               Relationship between Statutes and Policy Documents 17

Figure 2.1               Projected Population and Households Growth. 21

Figure 3.1               2013 Residents Survey. 33

Figure 4.2               Main Means of Travel to Work. 38

Figure 4.3               Average Road Roughness Standards by Road Classification. 41

Figure 4.4               Expected Future Resurfacing Costs/Liability. 44

Figure 4.5               Road Network Surface Condition. 45

Figure 4.6               Number of Fatal and Serious Injuries on Local Roads in Nelson. 50

Figure 4.8               Number of Cyclist Crashes in Nelson City. 52

Figure 4.9               Number of crashes involving pedestrians in Nelson City. 53

Figure 4.10             Percentage of Public Dissatisfied with the Transport Activity. 58

Figure 5.1               Remaining Asset Life of Retaining Walls 68

Figure 5.2               Existing and Proposed Cycle Network. 75

Figure 5.3               Zone Structure and Bus Routes 77

Figure D.1               Nelson Arterial Traffic Volumes 110

Figure D.2               Waimea-AM Peak Hour Ending 0900. 111

Figure D.3               Waimea – Peak Hour Ending 1700. 112

Figure D.4               Waimea – Midday Peak Hour Ending 1300. 113

Figure D.5               Waimea – Weekday AM Peak Hour Ending 0900. 114

Figure D.6               Waimea – Weekday PM Peak Hour Ending 1700. 115

Figure D.7               Waimea – Weekday Midday Peak Hour Ending 1300. 116

Figure D.8               Rocks Road -AM Peak Hour Ending 0900. 117

Figure D.9               Rocks Road– PM Peak Hour Ending 1700. 118

Figure D.10            Rocks Road– Midday Peak Hour Ending 1300. 119

Figure D.11            Rocks Road – Weekday AM Peak Hour Ending 0900. 120

Figure D.12            Rocks Road– Weekday PM Peak Hour Ending 1700. 121

Figure D.13            Rocks Road – Weekday Midday Peak Hour Ending 1300. 122

Figure D.14            Main Road Stoke –AM Peak Hour Ending 0900. 123

Figure D.15            Main Road Stoke – PM Peak Hour Ending 1700. 124

Figure D.16            Main Road Stoke – Midday Peak Hour Ending 1300. 125

Figure D.17            Main Road Stoke – Weekday AM Peak Hour Ending 0900. 126

Figure D.18            Main Road Stoke – Weekday PM Peak Hour Ending 1700. 127

Figure D.19            Main Road Stoke– Weekday Midday Peak Hour Ending 1300. 128

Figure D.20            Waimea – Rocks Road - AM Peak Hour Ending 0900 - Screenline. 129

Figure D.21            Waimea – Rocks Road - PM Peak Hour Ending 1700 - Screenline. 130

Figure D.22            Waimea – Rocks Road - Midday Peak Hour Ending 1300 - Screenline. 131

Figure D.23            Waimea – Rocks Road – Weekday AM Peak Hour Ending 0900 - Screenline. 132

Figure D.24            Waimea – Rocks Road – Weekday PM Peak Hour Ending 1700 - Screenline. 133

Figure D.25            Waimea – Rocks Road – Weekday Midday Peak Hour Ending 1300 - Screenline. 134

Figure D.26            Pedestrian Counts 135

Figure D.27            Pedestrian – 7 hr Count Total 135

Figure D.28            2010 Comprehensive Cyclist and Pedestrian Count 136

Figure D.29            Cyclists – 24 hrs Estimates 137

Figure D.30            Cyclists – 24 hrs Estimates (All Routes Above) 137

Figure D.31            2010 Comprehensive Cyclist and Pedestrian Count 138

Figure D.33            Nelson - Projected population, 2015-2045. 139

Figure D.34:          Population projections by age groups, Nelson. 140

Figure F.1               Nelson-Tasman Transportation Model Link LoS Criteria. 146

Figure H.1               Annual Average Morning Peak Travel Times – Waimea Road. 149

Figure H.2               Annual Average Evening Peak Travel Times – Waimea Road. 149

Figure H.3               Annual Average Morning Peak Travel Times – Rocks Road. 150

Figure H.4               Annual Average Evening Peak Travel Times – Rocks Road. 150

 


Executive Summary

The transport activity

The Transport services and assets associated with this activity are primarily focussed on the safe, efficient and effective transport of people and goods around the Nelson region. This includes the provision, operation and maintenance of physical infrastructure on the road reserve such as for driving, parking, cycling and walking as well as the provision of safety, traffic control and public transport services.

The replacement cost of these assets is approximately $700 million, and the depreciated value is $570 million. This represents nearly 43% of Council assets.

This Asset Management Plan provides evidence based information on how transport activity in Nelson is performing, based on measurable levels of service and performance indicators. It is based on a sustainable whole of system approach that supports the type of City we want Nelson to be; safe, accessible and affordable to all.

National and local policy on transport

This Transport Asset Management Plan (TAMP) provides Council with the year to year financial guidance on the allocation of transport funds. It is a tactical, locally focussed document; developed around national and regional transport funding guidelines as indicated by the requirements of the New Zealand Transport Agency (NZTA) and the Government Policy Statement (GPS) on Land Transport Funding. It will guide the transport spending for the years 2015-2018, as updated each year by the annual plan. The project programme in this TAMP will inform the transport spending in the Long Term Plan, both for the subsidised and unsubsidised sectors.

Previously this document has been developed within the broad guidelines set by the 2009 Regional Land Transport Strategy (RLTS) which supported a safe, efficient, integrated, sustainable land transport system. These guidelines have influenced the management of transport, specifically the subsidised policy, in Nelson over the last 6 years.

The Draft Government Policy Statement 2015 (GPS) on Land Transport Funding is issued by the Minister of Transport every three years. It has set out the below 3 government’s priorities for expenditure from the National Land Transport Fund over the next 10 years, broadly continuing the overall direction set by the Government Policy Statement in 2012 & 2009.

·      A strong and continuing focus on economic growth and productivity – The government’s investment in land transport should support increased economic growth and productivity in New Zealand.

·      Value-for-money – Land transport services should be delivered better and smarter. Asset management will be improved to boost performance of roading infrastructure. The Government Policy Statement 2015 makes it clear that getting more out of what is spent is expected.

·      Road safety – Road safety is a transport priority for the government. Safer Journeys, the Government’s road safety strategy, will be supported through the next National Land Transport Programme.

The Draft Regional Land Transport Plan 2015 – 2021 (RLTP) (due for public consultation in November 2014) sets out the subsidised transport prioritised programme for the six years in accordance with the NZ Transport Agency’s Investment and Revenue Strategy and in accordance with the GPS and this TAMP.

This approach in Nelson will continue to influence the management of private vehicle use by encouraging transport behavioural change, providing an integrated transport network that encourages all forms of transport, providing and improving modal choice and reducing the demand for travel.

The RLTP 2015 – 2021 has been adopted and confirms the direction detailed above.

The available means of achieving this are complex and inter-related. It is clear that no single measure in isolation will be successful in meeting the high level objectives and an integrated package of measures is required.

Key Issues

SUSTAINABILITY

Council has taken a “sustainable” approach to its transport network since the development of the 2009 Regional Land Transport Strategy. That strategy supported maintaining our existing transport infrastructure, increasing walking, cycling and passenger transport travel choices, and a targeted focus on growth areas. The direction started in the Regional Land Transport Strategy has been extended in this Asset Management Plan by rebalancing spending to projects of need, that increase mode choice and safety, rather than pursuing uneconomic low value for money projects. This direction is supported by the draft 2015 GPS objectives ‘providing appropriate transport choices’, ‘appropriately mitigates the effects of land transport on the environment’ and ‘addresses current and future demand’ by targeting growth areas. It also recognises the need for economic growth and the importance of efficient and effective freight transport to the Nelson region.

Arterial Traffic

The Arterial Traffic Study, in agreement with NZ Transport Agency in 2010 determined that:

·      There is not a significant traffic problem in Nelson, nor is one forecast to develop over the modelled time period of the study – the next 25 years.

Council’s resolution differed from the NZ Transport Agency approved study’s recommendations insofar as:

·      Council retain protection of the Southern Arterial Corridor only.

Ongoing traffic monitoring of the arterial routes shows that the traffic volumes are flat to declining in line with national and global observed trends. The decline is likely to be a result of many influences such as, technology developments reducing need to travel, an increase in walking, cycling and bus patronage, increases in car occupancy rates, reduction in teen drivers, ageing population travelling less and outside of peak times and increased cost of fuel.

Following the National Election in 2014 the Government announced that they would investigate the Southern Arterial Corridor using their Future Investment Fund.

Maintenance Operations and Renewals

Maintaining the transport infrastructure is key to ensuring we provide the desired level of service in the most cost effective manner. One of the key high cost components of the transport asset is the seal surface that waterproofs the pavement structure. Council currently has a backlog of surfaces that are overdue for resealing and treating this backlog is important to ensure that the life of our pavement structure is maximised.

Street lighting also has a backlog of aged fittings. Of greatest priority is the replacement of the inefficient and polluting mercury vapour lights on the network with LED fittings.

Condition assessments of the key transport assets are undertaken to ensure that they are maintained and renewed at the most cost effective time, however our knowledge of the remaining life of the assets and thus their depreciation needs improving in order better manage the maintenance and renewal future liability. This is a key component of the improvement plan.

PARKING

A parking study was undertaken in 2014 that informed the development of the draft ‘Parking Strategy 2014-2024’.

Survey data collected in 2005, 2008 and 2012 shows there is an appropriate supply of parking. Forecasting indicates there is unlikely to be any significant increase in demand over the next ten years.

The engagement undertaken has indicated that the Nelson public consider the key parking issues to broadly include enforcement, cost and payment options and all day CBD parking.

Subsequent to the draft parking strategy being prepared, Council, in response to the concerns of inner city retailers, resolved to remove the charge for parking for a winter trial period. As a result, finalisation of the strategy has been delayed until after this AMP has been completed. This AMP allows for the implementation of the actions detailed in the draft parking strategy but recognises that the direction and content of the parking strategy may change and some actions may not be necessary or other options may be trialled to ascertain their impact before the future direction is set.

Council resolved during the LTP deliberations to continue with the first hour of parking being free to users and then costing $1.50 per hour after that. The actions contained in the AMP appropriately reflect the intent of the draft strategy and no changes are necessary.

Nelson and Stoke CBD ENHANCEMENT

A number of projects identified in the Heart of Nelson – Central City Strategy have been completed to date. As part of the Long Term Plan 2015-25 (LTP) development Council will need to prioritise the remaining projects during 2015/16, determining which are still relevant, and considering if there are any new projects that should be added.  To inform this work data is being collected on the retail, employment and economic dynamics in the city. In conjunction with reporting back on the free parking trial period this will provide guidance on future projects within the Central City.

It is also clear residents feel Stoke CBD has been neglected over recent years and projects to revitalise the area, continue to provide for growth and facilities are overdue for funding. This TAMP includes Stoke CBD traffic and parking projects.

FREIGHT

Port Nelson as the maritime gateway to the region is extremely important to the economic development of Nelson and the wider region as it provides the ability for primary production to be exported. In the year ending June 2013 2.6M revenue tonnes were exported or imported via Port Nelson over the road network. With the greatest reliance on the primary industries of any region in the country it is critically important that the local road network is resilient and efficient for freight especially the routes to and from the port.

NZTA are predicting an increasing freight task of approximately 2% per annum with a key component of that a peak log harvest for the Nelson Marlborough Tasman area in the 2020 – 2025 period of double the current tonnage.

The 50 MAX vehicles have recently been introduced to allow more freight to be carried on fewer trucks on the local road network. 50 MAX High Productivity Motor Vehicles (HPMV) are trucks that are slightly longer than the standard 44 tonne vehicles. The modified design means that these trucks can carry more, but they perform on the road in the same way as a standard 44 tonne truck. The 50 MAX vehicles have an improved safety record and should not increase wear and tear on the road network. This TAMP proposes improvements to the bridges in the Maitai Valley to allow 50Max vehicles to access the adjacent forestry blocks.

FUNDING

The NZ Transport Agency, like Council, works on a three year funding cycle. The Transport Agency allocates funding to local authorities through the National Land Transport Plan which it adopts in July 2015, after considering each Regional Land Transport Plan (RLTP).

The Funding Assistance Rate (FAR) is the co-investment rate for transport activities that Council receives from the NZ Transport Agency In 2013 and 2014 the NZ Transport Agency reviewed the principals and methods used in setting the FAR. The NZTA have confirmed recently advised that there will be a single FAR for all activities and that Nelson’s FAR will increase. Nelson’s 14/15 current effective FAR for all activities was 46%. For the 2015/16 year the NZ Transport Agency has confirmed indicated that the FAR will be 47% and will rise by 1% per annum to 51% over five years.

This Asset Management Plan proposes a significant increase in expenditure for renewing the existing network.

There are several transport activities that Council already funds from rates without any co-investment. As investment rules tighten, Council always has the option of continuing with the activity or improving the level of service for an activity by increasing the activity’s funding from rates over the three year TAMP time frame.

The NZ Transport Agency introduced the One Network Road Classification (ONRC) at the end of 2013. It is proposed that this replaces Councils’ Road Hierarchy over time. This classification is to be implemented nationwide in order to provide more consistency in levels of service and the corresponding funding levels between regions. The effects of the ONRC on NZTA’s investment levels in Nelson City are uncertain at this stage.

During the development of the National Land Transport Programme the NZ Transport Agency did not fund the maintenance and operations budget to the level requested in the RLTP or this AMP.

The LTP retained a total of $325,000 in years two and three of the Long Term Plan so Council will be in a position to take up any additional funding should the NZ Transport Agency make it available for transportation renewals as originally proposed by the Regional Land Transport Plan and this TAMP.

 

Public satisfaction with the Transport activity

The 2014 Residents survey also showed that levels of satisfaction with the transport activity have remained relatively static over the last three years as can be seen in the figure below.

2014 Public Satisfaction With The Transport Activity

Residents who were dissatisfied with transport gave this rating because they felt public transport was limited (35%), or that cycleways need improvement (33%). Twenty nine per cent identified the roads need improvement.

A Balanced approach to transport strategy

The 2012 Transport Asset Management Plan adopted a “balanced approach” towards transport in Nelson and that approach has been continued through to this Plan.

Nationally and internationally, current transport planning has supported the encouragement of sustainable and alternative forms of transport for many years now, and Nelson has been at the forefront of actively supporting these forms of transport for over 15 years. Nelson has adopted a strategic momentum towards providing greater quality transport choices through the Asset Management Plans, the Regional Land Transport Strategy, Plan Changes and Council’s strategic sustainability policies. This has been effective in improving the walking and cycling networks in Nelson, and has supported the development of improved reliable public transport that offer viable options to residents. Nelson has developed a distinct travel choice culture.

This approach is fundamental to this TAMP and to the continued integrated delivery of projects by NCC over coming years. This will result in lower cost local road upgrades which are fit for purpose, provide opportunities for travel choices optimised whenever any project permits, and the travel needs of all road users recognised and catered for as feasible. In doing so Council:

·      Recognises the importance of well located, strong transport corridors that offer the potential for the efficient and safe flow of people and freight to assist the economic vitality of our region, and;

·      Acknowledges that more integrated approaches to traffic flow (the importance of slower speeds and placing a greater emphasis on walking, cycling and a sense of place) are necessary on our local roads and residential streets to promote social and community networks, supportive neighbourhoods, urban centres and safe streets.


Level of Service Summary Table

It must be recognised that Council has varying ability to influence some of these levels of service.

 

Level of Service

Performance Indicator

Current Performance

AMP Section Reference

Performance Target

MAINTENANCE

The Network, and its services in good condition and are “fit for purpose”

Smooth Travel Exposure*

87%

4.2.3, 4.2.4, 5.3

87% based on NZ Transport Agency standard roughness limits in ONRC

The Network, and its services in good condition and are “fit for purpose”

Average road roughness standard (National Association of Australian State Roading Authorities) by road classification.

Arterial/Principal, 69/90

Collector/Sub C, 97/117

4.3, 5.3

The following maximum average road roughness are not exceeded:

Arterial/Principal, 100

Collector/Sub C, 110

The Network, and its services in good condition and are “fit for purpose”

Average road roughness standard (National Association of Australian State Roading Authorities) by road classification.

Local, 106

Rural Sealed, 97

4.2.3, 4.2.4, 5.3

The following maximum average road roughness are not exceeded:

Local,120

Rural sealed, 120

The Network, and its services in good condition and are “fit for purpose”

The percentage of the local road (non State Highway) that is resurfaced annually*

4.8%

4.2.3, 4.2.4, 5.3

6.4% - 7.4%

The Network, and its services in good condition and are “fit for purpose”

The percentage of footpaths that meet or exceed the maximum acceptable roughness*

95%

4.2.1, 5.5

95% of the footpath network by length has a condition rating of ≤ 3

LOCAL ROADS, WALKING, CYCLING AND SCHOOLS

Walking and cycling are easy and attractive alternative transport choices.

Percentage of the community that travel to work by walking or cycling (based on Nelson City Council Annual Residents Survey and/or national census).

16% walked or cycled from the 2014 survey of residents. 2013 census data shows that 18.3% walked or cycled to work.

4.2.1, 4.8.1, 5.5, 5.6

25% of all journeys to work trips are by walking or cycling by 2018.

ARTERIAL TRAFFIC

An efficient transport system that enables people and freight to move efficiently.

Average AM and PM peak hour travel times on Waimea Road and the State Highway between Annesbrook and Haven Road roundabout

Rocks Road PM peak delay = 3min

Waimea Road AM peak delay = 2min

4.3, 4.8.2

Average peak hour travel time delays are no greater than 5 minutes above uncongested travel times.

ROAD SAFETY

Road Safety

Number of fatalities and serious injury crashes on the local road network*

The target of a maximum of 12 fatalities and serious injuries in 2013 was met with 12 recorded for that year.

4.4, 4.8.3, 5.9

The number of fatalities and serious injuries on local roads reduces by 4% per year from a base of 2007

Road safety

Number of injury crashes per kilometre of road.

2012 Calendar year rate is below maximum. Complete data for 2013 not available yet

4.4, 4.8.3, 5.9

The collective risk for each year reduces by at least 4% per year from a base of 2007

Road safety

Annual social cost of crashes (injury and non-injury) at intersections.

Target not met for 2012 after good performance in 2010 and 2011. The social cost of crashes was marginally above the target

4.4, 4.8.3, 5.9

The social cost for each year reduces by at least 4% per year from a base of 2007

Road safety

Number of crashes involving cyclists.

Target met for 2013. The number of cycle crashes (23) was the same as the target 2007 number.

4.4, 4.8.3, 5.9

Nelson City cycle crash numbers do not increase from those in the base year of 2007

Road safety

Number of crashes involving pedestrians

Target not met for 2013. The number of crashes involving pedestrians was 12, 100% more than the target number of 6.

4.4, 4.8.3, 5.9

Number of crashes involving pedestrians each year reduces by at least 4% per year from a 2007 base.

Road Safety

Total five year average social cost of urban crashes (injury and non-injury) at the worst 10 intersections

The social cost for 2013/14 worst 10 intersections was $4.2million compared with an average of $4.6million for the previous five years.

4.4, 4.8.3, 5.9

The annual total social cost is below the previous five year average.

PUBLIC TRANSPORT

Public transport services that meet the transport needs of the community with an equitable sharing of costs.

The farebox recovery ratio

Approximately 60% in 2012/13 and 62% in 2013/14

4.5, 4.8.4, 5.7

50%


 

Level of Service

Performance Indicator

Current Performance

AMP Section Reference

Performance Target

PARKING

The supply and pricing of short stay parking is managed to encourage commercial activity in the Central Business District.

Percentage of short stay parking spaces occupied in midweek peak in December

December 2012 - 81%

4.6, 4.8.5, 5.10

85%

The supply and pricing of long stay parking is managed to incentivise greater use of travel options other than cars.

Occupancy of long-stay parking spaces between peak travel times measured at 5 locations within the CBD fringe.

Not currently measured but will be in the future.

4.6, 4.8.5, 5.10

A reducing trend.

VALUE FOR MONEY PRINCIPLES

Public satisfaction.

Percentage of public satisfied and dissatisfied with the transport activity (based on Nelson City Council Annual Residents Survey).

Target not met

55% of respondents are either very satisfied or satisfied

17% of respondents are either dissatisfied or very dissatisfied

4.7, 4.8.6

More than 50% of respondents are either very satisfied or satisfied, and less than 10% are either dissatisfied or very dissatisfied.

Customer Responsiveness

Response to service requests*

95% in 2014

4.7, 4.8.6

80% of service requests responded to within 5 working days.

* Level of Service measure required by Local Government Act 2002.

 


Strategies, studies, reports and surveys

The following are planned for the next three years to enable and inform Council on future decisions. These are identified in the table below:

Study/strategy

AMP Section Reference

2015/16

2016/17

2017/18

Parking surveys

2.81, 4.6, 4.12, 5.10 App J

$50,000

25,000

25,000

Traffic counting and monitoring

2.81, App J

$50,000

$50,000

$50,000

Stoke Foothills Traffic Needs Study

2.8.1, App J

 

$100,000

 

 

Atawhai Foothills Traffic Needs Study

2.8.1, App J

$100,000

 

 

CBD West Traffic Study

2.8.1, App J

 

$100,000

 

As a result of the LTP deliberations and staff fine tuning the methodology, the cost of parking surveys in 2016/17 and 2017/18 have been reduced to $10,000 per year as only a representative sample of car parks will be surveyed rather than the majority of the CBD. The Atawhai Hills study has been moved to 2016/17. The CBD West Study has been moved to 2017/18.

Major new operation and maintenance activities
(2015/16 to 2017/18)

·      $50,000 pa for the operation and maintenance of the Stock Effluent facility;

·      $100,000 pa for small scale emergency works, response and recovery;

·      An additional $200,000 pa for public transport. Options include a potential increase the arterial route frequency and extending the Stoke network coverage.

·      In response to NZTA changing their initial advice on the way emergency events would be funded, the emergency works budget has been reduced from $200,000 to $100,000 per year cumulating.

Major new RENEWAL AND CAPITAL activities (2015/16 to 2017/18)

·      Reseals budget of $1.33M/year due to the significant number of sites where the seal has reached the end of its useful life;

·      Increase the streetlight renewal budget to convert aged fittings to LED’s;

·      Earthquake strengthening of road bridges;

·      New footpaths budget to close missing links and provide footpaths on existing roads that have none;

·      Increase structural replacement programme for the road pavement;

·      Todd Bush Road upgrade in 2015/16;

·      CBD Nelson and Stoke Enhancement initiatives;

·      Give effect to the outcomes of the Draft Parking Strategy;

·      Road upgrades with walking and cycling network benefits in the Wigzell Park area;

·      Projects included in the Regional Land Transport Plan, including:

o    Implement walking, cycling and schools package (includes Rocks Rd, Tahunanui Network and the bridge across Saltwater creek on the Maitai Path);

o    Minor Improvements Budget of $650,000 pa.

 

Significant projects, (greater than $500,000) proposed for the following seven years

·      Implement the outcomes of the Stoke and Atawhai Foothills studies;

·      Complete the street upgrades in The Wood area;

·      CBD Nelson and Stoke Enhancement initiatives;

·      Give effect to the outcomes of Draft Parking Strategy;

·      Marsden Valley Road / The Ridgeway intersection upgrade – subject to investigation;

·      Marsden Road / Main Road Stoke intersection upgrade – subject to investigation;

·      Marsden Valley Road Upgrade

·      Rocks Road Plant and Food to Maitai Path - Walk Cycle link

DEFERRED CAPITAL ACTIVITIES

Council, in the 2012 AMP, refocused its capital expenditure priorities away from upgrading local low traffic, low pedestrian and cycle volume roads that require a high cost to upgrade (e.g. hillside road upgrades). It targeted investment to maintaining the existing road infrastructure and contributing its local share to the regionally funded projects identified in the Regional Land Transport Plan. The remaining unsubsidised capital was prioritised on projects with significant traffic volumes and / or safety issues.

Several less urgent road upgrades identified in previous LTP's have been either deferred or removed.

This AMP proposes to fund street and intersection upgrades that provide walking and cycling network improvements such as the Wigzell Park area north of the Hospital.

The Wigzell area improvements have been replaced with a general “shared zone” project to the value of $100,000 per year under the Work Category 341: Minor Improvements.

Key ASSET MANAGEMENT ISSUES

·      Outcomes from the One Network Road Classification (ONRC) framework that will drive national level of service consistency through the NZ Transport Agency funding mechanisms;

·      Outcomes from the Central region freight analysis/study;

·      Outcomes from the NBus review which include funding and service levels;

·      Deterioration of footpath surfacing due to increased costs to meet desired level of service, resulting in less renewal length being achieved;

·      Outcomes from the Parking Strategy 2014;

·      The updating of key transport policy documents;

o    Structures on Road Reserve;

o    Licence to occupy Road Reserve;

o    Road Occupation Policy.

 

Key assumptions and uncertainties

As well as the general assumptions that apply across Council’s work, assumptions specific to transport include:

·      The National and Regional funding identified in the Draft Regional Land Transport Plan will be supported in the National Land Transport Programme.

·      The NZ Transport Agency financial assistance rates will increase from the current 46% to 47% in 2015/16 and rise by 1% per annum to 51% over five years.

·      The NZ Transport Agency will co-fund the regions passenger transport at an increased level from 2012-15 RLTP.

·      Tasman District Council will contribute $80,000 per year to the Nelson / Richmond passenger transport service which has been confirmed in their LTP.

·      Public transport patronage will be at a level that continues to support the public transport level of service.

·      Energy prices will not increase/decrease significantly over the next three years with a consequent effect on vehicle use or shifts to other modes of transport.

·      The number of vehicles and vehicle movements per household will continue at no greater than 2013 levels over the period covered by this Asset Management Plan.

·      Parking meter revenue is collected at a level of $460,000 pa.

·      That paid parking in the CBD is applied other than during the winter months.

·      Tasman District Council will continue to promote free parking within Richmond.

·      Free parking for the first hour and an increase thereafter to the rate of $1.50 per hour continues over the period covered by this Asset Management Plan.

·     

 


1.       Introduction

1.1.     Purpose

Council manages activities and assets on behalf of the ratepayers of Nelson to a value in excess of $1 billion. The assets are part of the city’s physical infrastructure and are important because many public services rely upon them and because they represent a significant investment by the community, built up over the last 100 years and more. The activities are equally important, and represent the way in which services are delivered to ratepayers.

The Local Government Act 2002 and the Land Transport Management Act 2003 places a legal obligation on Council to manage its assets to provide a specified standard of service in a cost effective manner. Council has committed to undertake this obligation in accordance with the Asset/Activity Management Policy using Asset and Activity Management Plans.

1.2.     Plan Structure

The Plan is divided into two parts. Part 1 has four sections:

·      Introduction;

·      What are the future demand issues to consider?;

·      What’s the direction?;

·      The delivery of a balanced approach.

Optimised delivery requires consideration of the transport network to enable the financial forecasts to be developed. The second part contains a more detailed analysis of the transport assets and activities, set out as follows:

·      Asset Management Systems;

·      Valuation;

·      Financial Forecasts and Development Contributions;

·      Risk Management;

·      Performance Monitoring and Improvement Plan.

1.3.     The Transport Activity

The Transport services and assets associated with this activity are primarily focussed on the safe, efficient and effective transport of people and goods around the region. This includes the provision of physical infrastructure on the road reserve such as for driving, parking, cycling and walking as well as the provision of safety, traffic control and public transport services.

The transport assets owned by Council include:

·      The vehicle network (road pavements, bridges, retaining walls);

·      The cycle network (cycle lanes, shared paths, cycle paths);

·      The pedestrian network (footpaths, walkways, bridges);

·      Infrastructure on road reserve (kerbs and channels, sumps, storm water control, street furniture;

·      Network control and management (traffic lights, signs, line markings);

·      Safety (streetlights, fences, guardrails);

·      Parking (on and off street car parks, parking meters and parking enforcement);

·      Passenger Transport (bus services/stops, total mobility services);

·      The replacement cost of these assets is approximately $700 million, and the depreciated value is $570 million.

1.4.     The Stakeholders

Council does not consult on its Asset Management Plans but does consult via the LTP, Regional Land Transport Plan and individually on transport planning and engineering projects and activities depending on the significance and location. Below is a list of key stakeholders, key user groups and area specific user groups that may be consulted to enable the implementation of this Plan.

1.4.1.   Key Stakeholders

Key stakeholders identified in this plan are:

·      The community of Nelson, including Tangata Whenua comprising six Iwi;

·      New Zealand taxpayers who fund the co-investment provided by the NZ Transport Agency;

·      Other asset and activity user such as visitors and tourists;

·      The Ministry of Transport and the NZ Transport Agency;

·      Tasman and Marlborough District Councils;

·      New Zealand Police, fire and ambulance services;

·      The Nelson Marlborough District Health Board;

·      The Accident Compensation Corporation.

·      The installers of ultra-fast broadband cables, power and telecom lines.

·      Other key users groups that may be identified on a project by project basis.

1.4.2.   Te Tau Ihu Treaty Settlement Act 2014

The Te Tau Ihu Treaty of Waitangi Settlement Acts 2014 (the Acts) for the eight iwi of Te Tau Ihu:

·      Ngati Kuia,

·      Rangitane o Wairau,

·      Ngati Toa Rangatira,

·      Ngati Koata,

·      Ngati Rarua,

·      Ngati Tama ki Te Tau Ihu,

·      Te Atiawa o Te Waka a – Maui,

·      Ngati Apa ki te Ra To

provide statutory obligations for Council in respect to general decision making processes, and specifically in RMA process and decision making. The Acts passed into legislation on the 1st of August 2014. Each Act provides each of the eight iwi with redress for past grievances dating back to 1840 in the Top of the South with an apology from the Crown. There are three types of redress provided for in the settlements as identified in Table 1.1 below. The redress that is shaded indicates that which are relevant to Asset Management Plans and the LTP. Council will be working with the eight iwi of Te Tau Ihu on relationships establishment and implementation of the settlements in relation to Councils governance and decision making processes through the 2014/15 year. For asset management planning undertaken in 2014 Council has held a workshop with iwi beginning a process of partnership and establishment of good working relationships for managing areas of significance such as the coastal marine area, freshwater bodies and catchments, reserves management and heritage.

The Ngāti Kōata, Ngāti Rārua, Ngāti Tama ki Te Tau Ihu, and Te Ātiawa o Te Waka-a-Māui Claims Settlement Act 2014, Ngāti Apa ki te Rā Tō, Ngāti Kuia, and Rangitāne o Wairau Claims Settlement Act 2014 and the Ngati Toa Rangatira Claims Settlement Act 2014 (The Acts) provides statutory obligations for Council in respect to general decision making processes. The Acts are the culmination of Central Government’s resolution of claims lodged by the eight iwi for redress of past wrong’s and provides for Cultural, Relationship and Financial redress.

Statutory acknowledgments may impact works programmes within the Asset Management Plan and the eight iwi will potentially be considered as affected parties under section 95E of the Resource Management Act, which the settlement legislation provides for.

Table 1.1       Te Tau Ihu Settlement Bill Proposed Redress

Note: Items relevant to asset management planning are shaded.

 

 

 

Cultural Redress

Statutory kaitiaki over a number of Department of Conservation administered Crown lands and the Coastal Marine Area

Vesting of sites in iwi ownership

Overlay classifications which require the Crown to acknowledge iwi values in that area

Statutory acknowledgments and deeds of recognition which are recognised under the RMA 1991 and Historic Places Act 1993

Statements of association, place names changes, crown payment, pouwhenua and mineral fossicking rights

 

 

 

Relationship Redress

Promotion of the relationship between iwi and local authorities of Te Tau Ihu

Protocols which encourage good working relationships on matters of cultural importance to iwi

Letters of introduction to museums and film archives

River and freshwater advisory committee to be set up and provide input into local authority decision making in relation to the management of rivers and freshwater under the RMA 1991

Memorandum of Understanding between iwi and the Department of Conservation

 

Financial Redress

Financial settlement

Commercial redress which involves properties being purchased by iwi and then leased back to the Crown, and first right of refusal over a number of properties

1.5.     The End Users

The end users of this plan are the Council staff in the transport asset management and operations departments. They will use this plan to manage the city’s assets and activities on the road reserve in a cost effective, sustainable, well planned and coordinated manner to provide agreed levels of service.

This document is also part of the business case to support the RLTP for the local road component and assists in informing the LTP.

1.6.     The Legislative Context

The overall legislative framework for planning, funding and managing the land transport system includes Acts, Regulations and Rules, a list of these fundamental to transport are provided in Appendix A.

1.7.     Strategic Context

1.7.1.   Government Outcomes

Forward Plan for Transport

The government’s policy direction for transport over the next decade is outlined in “Connecting New Zealand”, published August 2011. This publication is still very relevant as government policy has not changed significantly since 2011 but it does still refer to the previous Government Policy Statement. The publication identifies the big issues for transport systems as being:

·      Population growth;

·      Ageing population;

·      Global freight growth;

·      Fuel prices and volatility;

·      Transport emissions;

·      Transport security; and

·      New technology.

The publication clearly identifies that central government is responsible for responding to issues that are beyond its direct control, such as oil prices, ageing population and the effects of climate change, and that local government is responsible for regional and local transport planning and delivery.

A fundamental policy evident from the publication is that the government wants the costs associated with transport choices to be as clear as possible, and for the price of using each mode to match actual cost as much as possible. This will enable businesses and individuals to make the transport decisions that best meet their needs.

The publication provides a reality statement in regard to travel demand management initiatives and their effectiveness in relieving congestion. It states “We need to make sure that the arteries of our cities do not become clogged and that access to our key rail hubs, air and sea ports remain free moving, and that the corridors along our key supply chains also remain protected from congestion. In some cases, the government is taking a lead infrastructure approach to land transport investments, leading improvements in capacity ahead of them being required to encourage economic growth. In doing so, the government is being careful to respond to predicted incremental changes in transport demand and trends, rather than seeking wholesale mode shift for non-economic reasons. The latter would lead to a deadweight economic loss by encouraging inefficient transport choices.”

The publication also reiterates the governments focus on delivering value for money, it states “Improving performance and productivity right across the public service is a high priority for the government, including the transport sector. The government needs to be confident that the transport sector (central and local government in particular) is delivering the right infrastructure and services to the right level and for the best possible price.”

Government Policy Statement 2015/16 to 2024/25

The Government Policy Statement on Land Transport Funding is issued by the Minister of Transport every three years. It sets out the government’s priorities for expenditure from the National Land Transport Fund over the next 10 years.

The Government Policy Statement influences decisions on how money from the National Land Transport Fund will be invested in activity classes, such as state highways and public transport. It also guides the NZ Transport Agency and local government on the type of activities that should be included in regional land transport plans and the National Land Transport Programme. Regional Land Transport strategies must take account of the Government Policy Statement and Regional Land Transport plans must be consistent with the Government Policy Statement.

The Draft Government Policy Statement 2015 broadly continues the overall direction set by the Government Policy Statement in 2012 & 2009 and contains three priorities:

·      A strong and continuing focus on economic growth and productivity – The government’s investment in land transport should support increased economic growth and productivity in New Zealand.

·      Value-for-money – Land transport services should be delivered better and smarter. Asset management will be improved to boost performance of roading infrastructure. The Government Policy Statement 2015 makes it clear that getting more out of what is spent is expected.

·      Road safety – Road safety is a transport priority for the government. Safer Journeys, the Government’s road safety strategy, will be supported through the next National Land Transport Programme.

·     

1.7.2.   NZ Transport Agency Outcomes

The NZ Transport Agency has identified the impacts it wishes to deliver through the implementation of its investment and revenue strategy. These are:

·      better use of existing transport capacity;

·      more efficient freight supply chains;

·      a resilient and secure network;

·      easing of severe urban congestion;

·      more efficient vehicles;

·      reductions in deaths and serious injuries;

·      more transport mode choice; and

·      reduction in adverse environmental effects from land transport.

1.7.3.   Council’s Strategies, Plans and Policies

Nelson City has a well-developed set of strategies and policies relating to the city’s environment, its land use and transport systems, and its community. A summary of these is provided in Appendix B. The present suite of relevant documents has been developed over the past two decades, in line with statutory and associated requirements. Some of the separate strategies are not binding in a statutory sense, but help to elucidate the Council’s intended directions or approaches.

The strategies and policies have been developed with significant community input, and can be said to reflect the directions which the community wishes to follow to achieve the City we want Nelson to be.

Council-supplied transport infrastructure and transport planning contributes to achieving the following Council Community Outcomes:


 

Table 1.2       Council Community Outcomes

Outcomes/Goals

How transport contributes to achieving the outcome goals

Our unique natural environment is healthy and protected.

Through providing a range of transport modes that minimise the impact on the environment.

Our urban and rural environments are people-friendly, well planned and sustainably managed

Through taking into account the impact on public spaces when providing transport infrastructure.

Our infrastructure is efficient, cost effective and meets current and future needs

Optimisation of both maintenance and renewal expenditure is undertaken to ensure the least cost for the whole of the assets life.

Through providing an effective and efficient transport system that meets the needs of residents and businesses.

Our communities are healthy, safe, inclusive and resilient

Through providing a safe and resilient transport network that provides for all modes.

Our communities have opportunities to celebrate and explore their heritage, identity and creativity

The transport asset provides the space and means to allow our community to interact.

Our communities have access to a range of social, educational and recreational facilities and activities.

The transport asset provides the space and means to allow our community to interact.

Our Council provides leadership and fosters partnerships, a regional perspective, and community engagement

Through providing a transport network that takes account of our regional placement.  Through engaging with our community as the transport network is developed.

Our region is supported by an innovative and sustainable economy

Through providing an effective and efficient transport system that meets the needs of residents and businesses.

1.7.4.   Linkage Diagram to Planning Documents

Figure 1.1     Relationship between Statutes and Policy Documents

 


2.       WHAT ARE THE FUTURE DEMAND ISSUES TO CONSIDER?

There are several demand drivers that need to be taken into account when considering the future delivery of transport assets and activities. The development of a number of strategic documents, studies and models has enabled access to a vast amount of knowledge on several of the key demand drivers in Nelson and it is not intended to repeat the data contained within those documents in this plan. The demand drivers, document names, source reference and relevant notes are provided in Appendix C. Within these documents data on population, traffic, heavy commercial vehicles, port cargo, airport use, walking, cycling, passenger transport, travel demand management, fuel price rises, sea level rise and funding are provided.

The Arterial Traffic Study, which is the most comprehensive transport study undertaken in Nelson in recent years, provides a definitive assessment of the demand issues for the region and a comprehensive analysis for each mode, given expected population growth and the region’s demographics.

An overview of the documents in Appendix C indicates the following key trends, although it needs to be emphasised that future environmental, economic and social shocks have the potential to significantly alter these trends:

Population

Nelsons population is expected to grow as shown in Figure 2.1 below. This information is based on population projections by Statistics New Zealand published on 19 February 2015, using Census 2013 demographics and trends as a base (2013-based). The medium growth series has been used as Statistics New Zealand advised at the time that the medium projection is considered suitable for assessing future population change.

Nelson’s population is expected to grow by 5,000 3,600 over the next ten years, to almost 55,000 53,320 residents in 2025. Continuing the present trend, over half of the growth will be driven by increasing population in Stoke, and the populations in Nelson Central, Nelson North and Tahunanui are also expected to increase. about a quarter is from Nelson Central.

·      An ageing population with an increasing median age and an increasing proportion of older people

·      The proportion of the population aged under 15 years will decrease after 2018, from 18% to 16% in 2025 and to 15% by 2045. The number of children is likely to keep increasing until around 2025

·      Smaller households with an increase in one-person households

Population growth is expected to slow down after 2025, resulting in an increase of 4,700 residents over the 20 years between 2025 and 2045, to almost 60,000 in 2045. Most of the growth in these later years is again driven by an increasing population in Stoke but the rest of Nelson (Nelson North, Nelson Central and Tahuna) are also projected to have increasing populations.

Congestion

The Arterial Traffic Study determined that overall there is likely to be a 26-28% increase in peak hour trips in the next 30 years, a reduction in average trip length and an increase in interpeak and off-peak directions along the current arterial routes and little or no increase in peak direction traffic.

Traffic count data collected since late 2009 provides detail as to the distribution of trips throughout the day and by direction on the key arterial routes. This data shows that in general, traffic volumes on Rocks Road and Waimea Road in the busiest direction (northbound in the AM peak and southbound in the PM peak) have remained flat or slightly decreasing. In the opposing direction traffic volumes during these times traffic volumes have increased. During the midday peak the traffic volumes travelling into Nelson have remained static and reduced in the Richmond direction.

The data collected for Main Road Stoke is at a location south of Saxton Road. That data shows the traffic volume on this arterial route is generally trending downwards in the southbound direction and is static to slightly decreasing in the northbound direction.

Refer to Appendix D for traffic flow data on the main arterials.

Car trips

·      Overall car trips per capita have remained flat or decreased over the last three years. This has resulted in a corresponding reduction in arterial traffic volumes, refer Appendix D for traffic flow data on the main arterials.

Freight

The National Freight Demand Study 2014 predicts growth in freight movements from 18.6 million tonnes in 2012 to 28.04 million tonnes in 2042 for the Nelson/Marlborough/Tasman region. This corresponds to an average annual growth rate of around 2%. That Freight Demand Study also highlighted a peak log harvest for the Nelson Marlborough Tasman area in the 2020 – 2025 period of double the current tonnage.

Passenger Transport

·      Modelling undertaken for the arterial traffic study indicates low patronage uptake unless there is a significant increase in vehicle use costs (i.e. fuel prices and/or parking charges). There has been strong growth in demand for public transport over the last three years but this is expected to plateau in the medium term without further increases in the route frequency or coverage.

Walking

·      The results of the 2014 Residents Survey show that around 8% of residents walk to work. This percentage has dropped over the last four years from 10%, refer Appendix D for historic pedestrian counts.

Cycling

·      Records show an 8-9% growth per year over the last three years, although it is uncertain whether this growth can be sustained. Refer Appendix D for historic pedestrian counts.

Demographic Change

·      Census data indicates that generally the region’s population is ageing, over half of Nelsons population growth was in Stoke and the local demographic profile includes a “gap” in the 15 to 40 year cohorts (such trends are found nationwide with the gap being typical of provincial cities). This is likely to contribute to more off-peak journeys and slightly reduced traffic growth over time, due to the travel patterns of the growing number of older people and an increasing demand for services for the over 65 years age group, i.e. improved total mobility services and footpaths and shared paths designed for the sight impaired and those who use mobility scooters.

·     


Figure 2.1     Projected Population and Households Growth

Forecasting Assumptions

The Council produces a LTP every three years to set the strategic direction for the city over the following ten years. It enables integrated decision-making, land use planning, infrastructure and facilities development, environmental protection. It outlines how Council will provide services as the population increases and summarises Council’s financial allocation and prioritisation process.

Forecasting assumptions are crucial to gaining the right direction and use of public funds. Forecasting for growth considers three key components being population growth, growth in property and growth in economic activity. For transport the Council records the relevant assumptions within the transport activity in the LTP.

2.1.     Arterial Traffic

The development of the city’s State Highway and arterial network has been a fraught process over recent years. A 1967 study originally mooted a highway between Nelson city and Richmond to relieve forecast traffic growth along Main Road Stoke, Annesbrook, Tahunanui, Rocks Road and Waimea Road, bypassing Stoke on the seaward side and heading over the Bishopdale hill down the railway reserve where the railway lines were lifted in 1955.

In 2001 the first half of this highway, bypassing Stoke, was completed by Transit New Zealand and named Whakatu Drive. The second part, known most notably as the Southern Link, was rejected by the Environment Court in 2004 and led to the commissioning of the joint NZ Transport Agency, Nelson City Council and Tasman District Council study of the wider Nelson – Richmond transport issues, known as the North Nelson to Brightwater Strategic Study in 2008.

This culminated in a long term vision to 2026, including a combination of public transport, cycling, traffic management and travel demand management measures to support road improvements. No final decision was made on this strategy; consequently in 2009 the Nelson Regional Transport Committee completed the draft Regional Land Transport Strategy which acknowledged a need for additional road capacity as well as a significant improvement in public transport services in the region. The railway reserve was acknowledged as a logical potential transport corridor if ever required.

In 2009 - 2010 NCC undertook the Arterial Traffic Study to determine the best transport option between Annesbrook and QE11/Haven Rd roundabouts that would improve the City as a whole.

The Arterial Traffic Study was a significant piece of work completed in 2011 to enable a better understanding of short to medium term demand issues as they relate directly to Nelson. The outcome has a fundamental bearing on how network growth is addressed in the region. Essentially the Arterial Traffic Study, in agreement with the NZ Transport Agency, determined that:

·      There is not a significant traffic problem in Nelson, nor is one forecast to develop over the modelled time period of the study – the next 25 years.

·      Of the four options that were assessed in the study Option A - Peak Hour Clearways and Option B – Southern Arterial both offered positives but also had negatives.

·      Elements of Option A can be done in stages to provide additional capacity when needed, for example – the study recommended progressing the walk/cycleway around the waterfront in the short term.

·      Option B – the Southern Arterial route should be protected as a long-term future dedicated transport corridor should things change.

The Council considered the Arterial Traffic Study and preferred the Southern Arterial Corridor as the best long term transport option route. NCC officers were directed to prepare an issues definition report assessing the options available for protecting the Southern Arterial Corridor. The Corridor Management Plan was completed in late 2013.

Following the National Election in 2014 the Government announced that they would investigate the Southern Arterial Corridor using their Future Investment Fund.

2.2.     Accessibility

Accessibility can be viewed as the "ability to access" and often focuses on people with disabilities or special needs and their right of access, although it is universal and impacts on us all whether we are young, old, rural, urban, able-bodied or have a disability.

The needs of all sectors of the community should be considered when designers maintain and build Council’s infrastructure.

Typical issues that have been raised by the accessibility sector for which demand for action by Council is growing include:

·      Quality of some footpaths and crossing points which cause barriers for pushchairs, mobility scooters and wheelchairs;

·      Lack of appropriately located parking spaces for mobility impaired

·      Lack of footpaths on some roads;

·      Poor pedestrian crossing facilities on the following main transport corridors - Rocks Road, Annesbrook Drive, Waimea Road, Nayland Road;

·      Council has recently formally joined the regional A4A (Accessibility for All) forum where regional accessibility issues can be raised and improvements considered. Council has also recently made a significant improvement in the routes and frequency of public transport which will improve accessibility for many Nelson residents.

2.3.     Sustainability

2.3.1.   Overview of Sustainability

The Local Government Act 2002 sets out principles that local authorities must act in accordance with. The legislation requires local authorities to ensure prudent stewardship and the efficient and effective use of its resources in the interests of its district or region; and in taking a sustainable development approach, take into account:

·      The social, economic, and cultural interests of people and communities; and

·      The need to maintain and enhance the quality of the environment; and

·      The reasonably foreseeable needs of future generations

In 2011 Council began work on a 50 year vision of what Nelson could become, using sustainability principles. The vision statement was adopted in the LTP 2012-22 and the full Strategy in 2013. It identified ten goals that the Nelson community said were priorities for action and Council is now working to ensure that these goals and sustainability principles are integrated into all the decisions made about its activities.

Sustainable development actions and approaches are embedded throughout this asset management plan. These include the following:

Goal 3

Our natural environment – air, land, rivers and sea – is protected and healthy

·      The Balanced Approach to managing the transport assets moves the emphasis away from purely providing increasing road capacity. The emphasis is instead on providing for an appropriate mix of transport modes while maximising the efficient operation of the road assets we already have. The continued funding and resulting growth in NBus use contributes to a reduction in vehicle emissions, especially in the slower moving air sheds around Stoke, Victory, Hospital and Bishopdale areas.

·      The focus on providing improved safety for pedestrians and cyclists has the effect of encouraging use of these transport modes further and in turn also contributing to a reduction in vehicle emissions.

Goal 5

We are able to rapidly adapt to change

·      Programmed for year two of this AMP, the Atawhai Hills transport study is at least partially focussed on increasing the resilience of the road network between the northern suburbs and the Nelson CBD.

·      Constant monitoring of the traffic conditions and the split of mode choice will enable us to monitor trends in key performance indicators and allow us to respond early to any emerging issues. As detailed in the Improvement Plan improvements to how this data is collected and analysed are planned in the next three years.

Goal 6

We move from using fossil fuels to renewable energy sources

·      As with Goal three, the investment in the alternative transport modes of cycling, walking and public transport encourages their use. In turn any growth in use of these modes reduces use of fossil fuels.

Goal 9

Everyone in our community has their essential needs met

·      There are three main groups within the Nelson community that are transport disadvantaged; the youth, elderly and those at the lower end of the socio-economic spectrum. The ongoing provision of the NBus is targeted at meeting this essential need for this group of the community.

Councils approach to its transport network has taken a “sustainable” approach since the development of the 2009 Regional Land Transport Strategy. That strategy supported increasing walking, cycling and passenger transport travel choices, and placed a reduced emphasis on providing for future traffic growth. The direction started in the Regional Land Transport Strategy has been continued in this Asset Management Plan by rebalancing spending to projects of need, which maintains the existing transport infrastructure and increase mode choice and safety, rather than pursuing uneconomic low value for money projects. It has also included whole of life assessment of the transport assets and the development of long term management strategies to protect the life of the asset to maximise value for money and investment.

2.4.     Environmental Risks

Environmental risks include earthquakes, heavy rainfall, slips and storm surges. Council does not specifically fund large scale environmental risks for roading but has acknowledged that it will be required to increase loan funding to pay for 30 to 50 percent half of the cost to repair the roading infrastructure should a large scale event occur. The NZ Transport Agency funds the balance other half through the National Land Transport Fund.

An assessment of the roading bridges has been undertaken and those on lifeline routes up the Maitai and Brook valleys are prioritised for seismic strengthening subject to NZ Transport Agency funding approval to secure access to the city water supply infrastructure.

2.5.     Regional Considerations

There are several differences in the way Nelson manages its Transport Network compared to Tasman. It is important to recognise those differences to enable an understanding of the extent to which they affect the Nelson network and community.

Nelson views the provision of improved passenger transport services as essential in providing greater mode choice but also as a means of reducing peak hour congestion between Nelson and Richmond. The cooperation and support of passenger transport by Richmond‘s residents and governing bodies is important if Nelson is to achieve efficient and resilient connectivity with its nearest regional centre. Recently the two councils have been working together to achieve this. Tasman District Council have included a $80,000 pa allowance in their LTP and 2015-2025 Asset Management Plan to assist in funding the bus service.

There are differences between Nelson and Richmond parking policies which implies a more fundamental philosophical difference in transport policy between the two regions. The funding of passenger transport and the charging and restricting of parking are essential tools in managing the transport network to influence mode choice.

Another regional consideration is the allocation of Nelson’s “R” funding. Currently the NZ Transport Agency has confirmed that it is to be spent within the “region”, and will be spent on the highest ranking projects in terms of NZ Transport Agency’s investment and revenue strategy. This effectively means that Nelson projects are competing for priority with NZ Transport Agency’s state highway projects.

There are likely to be differences in the way Nelson manages its transport assets compared to Tasman as, being a city, it has to deal with different issues. This is probably reflected most in the Land Development Manual, footpath resealing policy, capital works prioritisation method, cycling and walking policies, Regional Passenger Transport Plan, Regional Land Transport Plan, minor safety polices, street lighting, and growth management strategies.

2.6.     Funding

Financial Assistance Rates are used to determine what portion of a project or programme could be funded from the National Land Transport Fund, which is administered by the NZ Transport Agency through the National Land Transport Programme.

In 2013 and 2014 the NZ Transport Agency reviewed the principals and methods used in setting the FAR. Recently the NZ Transport Agency advised there will be one rate for all activities and that Nelson’s FAR will increase. Nelson’s current effective FAR for all activities was 46%. For the 2015/16 year the NZ Transport Agency has confirmed indicated that the FAR will be 47% and will rise by 1% per annum to 51% over five years. The table below details the FAR that Nelson will receive for each year from 2015/16:

Table 2.1       NZ Transport Agency Financial Assistance Rates

Financial Year

Financial Assistance Rate

2014/15

46%

2015/16

47%

2016/17

48%

2017/18

49%

2018/19

50%

2019/20

51%

Council have a risk sharing arrangement with the NZ Transport Agency whereby elevated funding assistance rate for emergency works of subsidised assets. Recent preliminary advice indicates that The subsidy would available only for out of ordinary short duration natural events that have a recovery and reinstatement cost greater than $100,000 .

NZ Transport Agency have yet to announce the FAR for emergency works. Their preliminary advice is that it may be 10% above the standard FAR.

The funding assistance rate that applies to emergency works within each financial year is:

·      For cumulative claims the total costs of emergency works up to 10% of the total cost of the subsidised maintenance programme for the year, the normal FAR

·      for the part of cumulative claims of total costs of emergency works that exceeds 10% of the approved maintenance programme for the year, the normal FAR. plus 20%.

 

In 2012 The NZ Transport Agency advised that due to national financial constraints the ‘R’ funding can be spent up to 2018 rather than 2015.

There are several other sources of funding to support the Transport network along with NZ Transport Agency co-investment and rates. These are Development Contributions, private / public partnerships, utilisation and expansion of parking revenue (which has been contributing towards cost of democracy for last 20 years).

Council’s Development Contributions Policy does not permit contributions from growth on roads classified as local although many of Council’s projects are designed to cater for future growth, through providing walking and cycling infrastructure on local roads. Previous roading policy determined that 20% of network usage was attributable to growth when a new road is built or upgraded. It is suggested that this proportion of growth could be applied to all new roads and roading improvements, not excluding local roads as these are more likely to service growth areas. It is also proposed that development contributions should also be taken, at the same proportions for walking, cycling and passenger transport infrastructure. These proposals are now being considered in the Development Contributions Policy review.

Council’s new Development Contributions Policy, adopted as part of the LTP process, has included projects on all road classifications.

2.7.     Funding Risk

There are already several transport activities that Council funds from rates without any co-investment. As investment rules tighten, Council always has the option of continuing with the activity or improving the level of service for an activity by increasing the activities funding from rates. If Council chooses to increase rates funding then The NZ Transport Agency will view the activity as affordable by Council and will be unlikely to ever fund that activity to a greater extent again.

The NZ Transport Agency, like Council, works on a three year funding cycle. The NZ Transport Agency allocates funding through the National Land Transport Programme which it adopts in July 2015, after considering each regional land transport plan. There is a risk that activities which may be eligible for funding, and budgeted to receive funding in the LTP, are declined funding after the Council has adopted its LTP. This will mean that some activities will have to be reconsidered by Council to decide if additional funding is provided, or the projects are postponed.

This risk has been a key component on some local projects in recent years where there has been uncertainty over a project receiving co-investment due to delays in approvals, leading to confusion, especially when community engagement is required early on in the design of a project.

2.8.     Transport Network Resilience

The Regional Land Transport Plan aims to maximise the efficiency of the transport system with minimal expenditure through encouraging the community to shift to more sustainable ways of moving around the City. This concept is developed further in the next section, resulting in a proposed balanced approach (Section 3.5) to managing the transport network.

Other aspects of a communities resilience relies on Council’s other strategic documents such as sustainability strategy, social wellbeing policy and, of critical importance, it’s long term growth strategy implemented through the resource management plan.

2.8.1.   Planning for Growth

Growth is planned for in a number of ways. The most formalised process is through Resource Management Plan Changes.

Investigation has been recently completed on a number of transport issues that are related to future growth, these are:

·      Nelson City Council / NZ Transport Agency / Tasman District Council 3 roundabouts project;

·      Parking Strategy;

·      Southern Transport Corridor - Issues Definition Report;

·      Rocks Road walk and cycle investigation;

·      Waimea Road Enhancement Study and intersection improvements;

·      Tahunanui Cycle Network.

Investigation is planned for the following:

·      Stoke Foothills Transportation Study – investigation into intersection and surrounding network to accommodate growth in the Stoke foothills;

·      Atawhai Hills Transportation Study - investigation into intersection and surrounding network to accommodate growth in the hills to the north of the City;

·      Annesbrook / Parkers and Quarantine Road modelling [Discuss status with NZ Transport Agency]

·      CBD West intersection modelling update - scheduled for Year 3.

2.8.2.   Building for Growth

Council is concentrating on providing services to areas that are zoned for development (Residential, Rural Zone High Density Small Holdings, Suburban Commercial and Industrial) but are covered by the Services Overlay because one or more servicing constraints have been identified as needing to be addressed prior to the development of that property / area. The projects to facilitate future growth identified in this AMP therefore only consist of works required to eliminate servicing constraints on sites zoned for development and these have been prioritised in accordance with Council’s strategic planning process.

The projects identified in the Asset Management Plan which have a substantial growth component (>50%) are identified below, along with the years they are programmed:

·      2023/24, Marsden Valley Road / The Ridgeway intersection – subject to investigation;

·      2023/24, Marsden Road / Main Road Stoke intersection – subject to investigation;

·      2022/25, Marsden Valley Road Upgrade;

·      2015/16, Todd Bush Road;

·      2021/22, Lucas Terrace Upgrade.

 

Council resolved during the LTP and Development Contributions Policy deliberations to bring a minor improvement for Marsden Valley Road / The Ridgeway forward to 2015/16. This does not have any budget implications as the rest of the projects in the minor improvements database will be reprioritised.

 

The Lucas Terrace Upgrade was removed from budgets as this upgrade will be funded by the developer as the development is the only benefactor.

 

2.9.     Consultation

The Council recognises that it has obligations to seek the views of the local community on issues, plans and strategies that may directly or indirectly affect them. It also wants to encourage best practice by engaging public involvement for transport schemes in order to create a sense of ownership by local residents and to ensure that residents, businesses and stakeholders have the opportunity to provide valuable input.

Additional budgets have been included in all transport schemes to provide public engagement. This is to ensure the Council makes informed decisions and that Stakeholders are getting value for money. Views will be considered and responded as is appropriate. We will provide information regarding the outcome of the decision making process and the reasons for the decision.

Key principles of public engagement that the Council wish to improve on, are building consultation into the planning process from the start, and providing access to information by various means to cater to the needs of all people.

2.10.   Procurement Strategy

This Strategy documents Nelson City Council’s approach to procurement of activities funded through the National Land Transport Programme.

The Strategy aims to achieve desired outcomes and quality at the lowest overall whole of life cost and sustain a pool of suppliers in the region of varying sizes and capabilities to meet the needs of the Council.

The objectives of this Procurement Strategy are:

·      To attain value for money;

·      To encourage competitive and efficient markets;

·      To enable fair competition;

·      To operate an efficient procurement process.

Maintenance contracts have been reviewed and grouped to provide a good balance between price and quality, and use either prequalification or price/quality supplier selection methods. The methods used to procure capital projects will differ depending on the size of the project, but will be either lowest price or price/quality.

Council maintains an in-house professional services capability balanced with external consultants as required to achieve best value for money. Additional professional services are sometimes required and will be procured following the guidelines of the NZ Transport Agency Procurement Manual whereby a supplier will be directly appointed for contracts under $100,000, and a closed contest will be used for work between $100,000 and $200,000. The supplier selection method will be determined depending on the services being procured, but will commonly be price/quality.

2.11.   Prioritisation Process for Projects

The Council recognises that it has obligations to seek the views of the local community on issues, plans and strategies that may directly or indirectly affect residents. It also wants to encourage best practice by engaging public involvement for transport schemes in order to create a sense of ownership by local residents and to ensure that residents, businesses and stakeholders have the opportunity to provide valuable input.

Projects identified for funding in the Regional Land Transport Plan are subject to prioritisation through the Regional Land Transport Plan development process. This relies on the NZ Transport Agency investment and revenue framework.


3.       What’s the direction?

3.1.     Context

The Transport Asset Management Plan has to take long term higher level direction from the GPS and short term direction from the Regional Land Transport Strategy. The long term vision and mission underpinning the Regional Land Transport Strategy is:

“A sustainable transport future for Nelson”

and

“To have a land transport system that is safe, efficient, integrated and responsive and that meets the needs of the region in ways that are environmentally, socially and economically sustainable”.

The Draft Regional Land Transport Plan 2015 – 2021 (under development) sets out the subsidised transport priorities for the next three years that contribute to the vision for the region in accordance with the GPS on Land Transport.

The RLTS has been superceded by the 2015-2021 RLTP. The objectives contained in the RLTP are split into regional and local objectives as follows:

 

GPS Objectives

Regional Objectives

Policy/Direction

Measures of success for our communities

A land transport system that addresses current and future demand

 

1) A sustainable transport system that is integrated with well planned development, enabling the efficient and reliable movement of people and goods to, from and throughout the region

2) Supporting economic growth through providing better access across the Top of the South’s key journey routes

Target investment in regional route improvements to key journey routes

Consider Top of the South options to collaborate and improve road operations and maintenance delivery mechanisms

Target investment in projects that reduce travel times and vehicle operating costs on key journey routes

Develop and apply ONRC transition plans and programmes to close the Customer Level of Service gaps

 

Travel times between SH 6/60 and Port Nelson, and on SH1 between Picton and the Marlborough boundary are consistent

Reduction in the distance per capita travelled in single occupancy vehicles

ONRC is fully established by 2018

Routes available to HPMV increase over time

 

A land transport system that is reliable and resilient

 

3) Communities have access to a resilient transport system

4) Communities have access to a reliable transport system

Reduce the risk of disruption on lifeline routes

Improve network resilience along key journey routes

Improve network reliability along key journey routes

 

Reduction in the number of hours that sections of the key journey routes are closed due to unplanned disruptions

Travel time variability on our key journeys does not increase

 

GPS Objectives

Nelson Objectives

Policy/Direction

Measures of success for our communities

A land transport system that addresses current and future demand

 

1) A sustainable transport system that is integrated with well planned development, enabling the efficient and reliable movement of people and goods to, from and throughout the region

2) Supporting economic growth through providing better access across the Top of the South’s key journey routes.

Target investment in regional route improvements to key journey routes

Consider Top of the South options to collaborate and improve road operations and maintenance delivery mechanisms

Target investment in projects that reduce travel times and vehicle operating costs on key journey routes

Develop and apply ONRC transition plans and programmes to close the Customer Level of Service gaps

Travel time variability on SH6 and Waimea Road are consistent

 

Reduction in the distance per capita travelled in single occupancy vehicles

 

ONRC is fully embedded by 2018

 

Routes available to HMPV increase over time

 

A land transport system that is reliable and resilient

 

3) Communities have access to a resilient transport system.

4) Communities have access to a reliable transport system.

Reduce the risk of disruption on lifeline routes

Improve network resilience along key journey routes

Improve network reliability along key journey routes

Reduction in the number of hours that key journey routes are closed due to unplanned disruptions

Travel time variability on SH6 and Waimea Road are consistent

A land transport system that provides appropriate transport choices

 

N1) Communities have access to a range of travel choices to meet their social, economic, health and cultural needs

N2) Enable access to social and economic opportunities by investing in public transport

Extend walking and cycling networks and improve urban routes for cyclists where this can be achieved at reasonable cost

Maintain and grow public transport patronage by reconfigured and extended networks and improved ticketing methods

Increase in total trips travelled by walking, cycling, and public transport at peak times

 

Increase in total trips travelled by walking, cycling, and public transport

A land transport system that appropriately mitigates the effects of land transport on the environment.

 

N3)The transport system supports national strategies for energy efficiency and climate change, and protects natural systems and community values

Invest in local environmental mitigation measures with investment targeted on the most adverse cases

Invest in methods to reduce fuel related vehicle operating costs

Invest in travel demand management measures and infrastructure that enables more efficient trips

Reduction in the distance per capita travelled in single occupancy vehicles in Nelson

Increase in total trips travelled by walking, cycling, and public transport at peak times

Increase in total trips travelled by walking, cycling, and public transport

A land transport system that is a safe system, increasingly free of deaths and serious injury

 

N4) Deaths and serious injuries on the Nelson network are reduced at reasonable cost

Adopt a ‘Safe System Approach’ to road transport

Ensure road safety audits are undertaken on new roads or improvements to roads

Safety budgets targeted to improvements that deliver road safety improvements with a focus on reducing deaths and serious injuries.

Increase safe cycling through improvement of cycle networks

Reducing trend in deaths and serious injuries on the transport network

A flat or declining number of cycle crashes on the network

A declining number of pedestrian crashes on the network

 

3.2.     What Are The Impacts of Moving People and Goods?

While the transport services and assets associated with this activity are primarily focussed on the safe, efficient and effective transport of people and goods around the region it is important for Council to recognise the potential negative effects on the community. Briefly these are summarised as:

Economic

·      The economic cost resulting from road congestion;

·      The economic cost resulting from operating, maintenance, renewal and investing in transport assets and services;

Environmental

·      Air, water and particle pollution from motor vehicles;

·      Disturbance of the natural environment from road construction;

·      Contribution to climate change.

Social

·      Noise and community severance from busy roads;

·      Social cost of road congestion, accidents and injuries;

·      Health effects from transport infrastructure which either inhibits, or does not promote, physical activity.

3.3.     A Brief History of Street Design and Improvements Programme

Historically transport development in Nelson has pursued infrastructure improvements that have primarily focussed on catering for predicted future traffic volumes. The greatest contributor to the city’s roading network has been through residential and industrial growth. The progressive standardisation of street design in new subdivisions and industrial estates, determined by varying versions of the Engineering Standards, can be seen throughout the city.

With expansion into the hillsides as flat land is becoming scarce; the impact of the standards on development costs and the environment has led to a demand for less onerous standards which reduce the impact on the environment. At the same time the costs of Council’s own roading improvements, fundamentally based on providing footpaths in the older subdivisions where they were not built at the time of the original development, has increased dramatically as the flatter streets are completed and the costlier hillside streets are prioritised. Indications also showed that the public were particularly concerned about vehicle speeds in residential streets. Questions started to be asked about the necessity for footpaths in every street (however narrow or hilly) as being the key driver for a large proportion of transport expenditure.

The Land Development Manual 2010 addressed many of these issues and was welcomed by the local construction industry and key stakeholders. It provided a more holistic approach to the transport network and set down the fundamental importance of sustainable road design, road hierarchy and accessibility. This change was reflected by Council planners by prioritising the following plan changes:

·      Plan Change 21 – Parking and related changes;

·      Plan Change 18 – Nelson South;

·      Plan Change 17 – Enner Glynn and Brook Valley structure plan;

·      Plan Change 14 – Residential subdivision, Land Development Manual and Comprehensive housing;

·      Plan Change 13 – Marsden Valley.

The new direction signalled by the Land Development Manual and the Plan changes is now incorporated into all Council’s transport actions.

So historically, street upgrades that have been driven by a footpath prioritisation programme have been using most of Council’s capital expenditure programme, including renewals and reseals funding which could have been spent on maintaining the existing transport infrastructure.

The 2009 and 2012 Asset Management Plans recognised that there was an increasing level of deferred maintenance resulting from this funding strategy and diverted the renewals and reseals funding to maintaining the existing transport infrastructure.

The 2013 Residents survey shows that the Transport activity remains the one Council activity the public are most dissatisfied with. Figure 3.2 shows that Transport is the one activity that ratepayers would like to see Council putting more effort into based on the 2013 resident survey. This data was not collected in the 2014 survey.


 

Figure 3.1     2013 Residents Survey – Activities Which Residents Would Like Council To Put More Effort Into

In Council’s 2011 Annual Plan further changes were made with the deferment of several hillside street upgrades and an increase in street lighting and minor improvements funding.

In 2011 Council recognised that the Community has a high demand for Passenger Transport improvements and initiated increasing service frequency by increasing parking charges to fund improvements.

3.4.     What Are The Options?

Transport choices made today will determine the competitiveness, quality of life and resilience of Nelson for decades to come.

If we do nothing but maintain the existing network, public dissatisfaction with transport can be expected to increase.

The Draft Government Policy Statement clearly expects regions to focus investment on projects and services that offer increased economic growth and productivity, while also providing value for money through good asset management to improve the performance of the local networks and road safety. It is important to recognise the following impacts which the Draft Government Policy Statement expects and which relate more to the local transport networks:

·      A secure and resilient transport network;

·      More transport choices, particularly for those with limited access to a car;

·      Improvements in the provision of infrastructure and services that enhance transport efficiency and lower the cost of transportation through better use of existing transport networks;

·      Reductions in adverse environmental effects from land transport;

·      Reductions in road deaths and serious injuries as a result of road crashes.


The advantage of following the Draft Government Policy Statement path is the opportunity to build future resilience into the network and at the same time contribute towards the direction identified in the Council’s 2060 (Sustainability) Strategy. Optimisation of our existing network combined with a lesser reliance on private vehicles and a greater encouragement of other modes can lead to:

·      lower energy costs;

·      increased quality of life;

·      greater value for money;

·      fast, safe, affordable transportation;

·      vibrant streets and green areas;

·      clean and healthy environment;

·      cities for people.

3.5.     A Balanced Approach

The 2012 Transport Asset Management Plan adopted a “balanced approach” towards transport in Nelson and that approach has been continued through to this Plan.

Nationally and internationally, current transport planning has supported the encouragement of sustainable and alternative forms of transport for many years now, and Nelson has been at the forefront of actively supporting these forms of transport for over 15 years. Nelson has adopted a strategic momentum towards providing greater quality transport choices through the Asset Management Plans, the Regional Land Transport Strategy, Plan Changes and Council’s strategic sustainability policies. This has been effective in improving the walking and cycling networks in Nelson, and has supported the development of improved reliable public transport that offer viable options to residents. Nelson has developed a distinct travel choice culture.

This approach is fundamental to this TAMP and to the continued integrated delivery of projects by NCC over coming years. This will result in lower cost local road upgrades which are fit for purpose, provide opportunities for travel choices optimised whenever any project permits, and the travel needs of all road users recognised and catered for as feasible. In doing so Council:

·      Recognises the importance of well located, strong transport corridors that offer the potential for the efficient and safe flow of people and freight to assist the economic vitality of our region; and

·      Acknowledges that more integrated approaches to traffic flow (the importance of slower speeds and placing a greater emphasis on walking, cycling and a sense of place) are necessary on our local roads and residential streets to promote social and community networks, supportive neighbourhoods, urban centres and safe streets.


4.       The delivery of a balanced approach

This Asset Management Plan sets out how this balanced approach, initially implemented in the 2012 AMP, is to be delivered in a cost effective manner. It aligns Council’s expenditure to its strategic planning direction while at the same time positions itself to qualify for national funding by aligning with Government direction wherever possible.

The following six focus areas are proposed:

·      Local roads including walking, cycling and schools;

·      Arterial traffic, including freight;

·      Safety;

·      Public transport;

·      Parking;

·      Value for money principles.

Appendix E identifies how these focus areas link to Councils strategic plans and the Government’s desired impacts.

This section identifies levels of service, performance indicators, three year performance targets, the current performance level and preliminary details of the projects, activities and plans proposed to deliver the performance targets.

Funding has been allocated to these focus areas at a higher level than the total transport expenditure in recent years in recognition of the improvement that is necessary in the transport activity to bring its public satisfaction rating into line with Councils other assets and activities.

4.1.     Defining the Targets and the Delivery

This section identifies the levels of service, performance indicators, three year performance targets, the current performance level and preliminary details of the projects, activities and plans proposed to deliver the performance targets.

Performance targets identified below are for three years because the Asset Management Plan is reviewed every three years. Council has ten year targets in the Regional Land Transport Plan which are reported on annually to the Regional Transport Committee.

The performance targets don’t always directly relate to the implementation package as in most cases it is difficult to measure the impacts of the packages over the short term and targets have to be SMART[1].

Section 261B of the Local Government Act 2002 (Amendment Act 2010) specifies that the Secretary for Local Government must make rules specifying performance measures in relation to the provision of roads and footpaths. This rule was published in February 2014 and is now operative.

4.2.     Local Roads, Walking, Cycling and Schools

These services provide the essential services that contribute to the community outcome of People-friendly places – “We build healthy, accessible and attractive places and live in a sustainable region”. The service levels are fundamental in delivering softer approaches to traffic management (the importance of slower speeds and placing a greater emphasis on walking, cycling and a sense of place) to promote social and community networks, supportive neighbourhoods and safe streets.

A service level statement for the road network identifying the basic transport needs follows:

·      Roads are safe to use and provide a comfortable and reliable means of travel.

·      The footpath and cycle network is considered to be suitable, accessible, safe and well maintained.

·      Road markings are maintained to provide clear delineation and direction for roads, parking, and cycle lanes at all times.

·      Bridges and related structures are designed and maintained to provide safe access across the network.

·      Traffic signals are designed and maintained to improve traffic flow in the roading network.

·      Appropriate signage is maintained to enable safe and efficient way finding across the transport network.

·      Adequate street lighting is maintained to enable safe neighbourhoods and easy night driving on all urban streets.

·      Stormwater is removed efficiently from road surfaces.

4.2.1.   Walking and Cycling

The guiding level of service relating to walking and cycling is:

Table 4.1       Level of Service Relating to Walking and Cycling

Level of Service

Performance Indicator

Performance Target

Walking and cycling are easy and attractive alternative transport choices.

Percentage of the community that travel to work by walking or cycling (based on Nelson City Council Annual Residents Survey and/or national census).

25% of all journeys to work trips are by walking or cycling by 2018.

Table 4.2       Level of Service Relating to Maintenance of Footpaths

Level of Service

Performance Indicator

Current Performance

Performance Target

MAINTENANCE

The Network, and its services in good condition and are “fit for purpose”

The percentage of footpaths that meet or exceed the maximum acceptable roughness*

95%

95% of the footpath network by length has a condition rating of ≤ 3

The measure Council uses to monitor walking and cycling is the journey to work data as it is a Census question as well as a question in Council’s annual residents’ survey. Figure 4.1 below shows the journey to work data from 1996 to 2013 from the census and Figure 4.2 shows similar data from the annual residents’ survey.


Figure 4.1     Journey to Work Data

The graph above shows that over half of the population travel to work by car, truck or van, although a higher proportion walk or cycle in Nelson than the rest of the country, averaging around 17% of all journeys to work.


Figure 4.2     Main Means of Travel to Work

In the 2014 residents’ survey 16% of journey to work trips were by walking and cycling. This was slightly less than previous years although it is worth noting that the absolute numbers of residents travelling by these modes increased.

The condition of the footpaths is of particular interest to the community, especially relating to the surface condition and how this relates to safe use by the increasing number of elderly and disabled residents. Council has developed a new condition rating for use locally. Table 4.3 shows the descriptions of each rating as well as the percentage, by length, of the footpath network that meets the criteria.

Table 4.3       Footpath Rating Descriptions and Summary

Rating

Description

Percentage length with rating (2014)

1

As new, no significant cracking, even surface.

15%

2

Good condition, safe to use, some minor cracking and/or scabbing/ravelling.

48%

3

Average condition, could be some cracking, scabbing/ravelling and/or untidy but safe to use, no significant hazards.

32%

4

Poor condition, will need maintenance in near future, cracking more significant, may be some settlement or sections may be lifting, surface may be uneven, small bumps or ruts forming, broken edges, lichen, service covers may be raised or low.

4%

5

Very poor condition, needs to be fixed now, not safe to use, significant tripping hazards, holes, humps and bumps, ruts and/or very uneven surface, service covers and/or tree roots hazardous.

1%

Table 4.3 shows that around 48% of the footpath network is in good condition with a further 32% in average but still safe condition.

4.2.2.   The Walk/Cycle/Schools Package

A Walk/Cycle/Schools Package of Capital Works was adopted by Council through the Regional Land Transport Programme in 2012-15 focussing on walking, cycling and infrastructure around schools. The objectives are:

·      To increase peak hour walking and cycling throughout the City (acknowledging that journey to school mode is critical to reducing congestion and achieving the other Regional Land Transport Strategy 2009 objectives).

·      Increasing walking and cycling at all other times.

This package is more than just the resolution of an issue. It is a strategic direction for a community with limited funds that has identified its direction through many strategic and policy documents (identified above). It aligns with many outcomes of the Government Policy Statement and allocates a share of the available regional funds to some local roading projects. A key driver for the support for this Package is the outcome of the Arterial Traffic Study which did not support the immediate progression of the southern arterial.

A range of projects and measures across all activities were selected to extract maximum value from previous investment, to complete significant network connections and to encourage a further step forward in opportunities to walk and cycle within Nelson. The package when completed will result in a well integrated network with overall greater network safety.

There were two State Highway network infrastructure projects critical to making walking and cycling an easy choice for Nelson. These are aimed at providing increased walking and cycling opportunities on or alongside state highways and providing connection to the local network facilities.

The proposed local infrastructure projects went towards completing separated cycle facilities across the city (including linkages to Richmond), allowing the full benefit of previous investment to be realised. New off road facilities from the Central Business District to the Port along the banks of the Maitai River will provide excellent connections for pedestrians, children, and less confident cyclists. On-road facilities will fill the missing links in the key routes from Tahunanui to Stoke. These key projects will be supported by a number of smaller projects which will provide linkages within parks and reserves, better lighting of roads and cycleways, and improved cycle parking.

The following projects are programmed for the 2015-2018 period covered by this Asset Management Plan under the walk/cycle/schools package:

·      Rocks Road shared path;

·      Tahunanui to Stoke cycle link;

·      Maitai path bridge across Saltwater Creek.

·     

·      The Maitai to Rocks Road link was added to the Walk Cycle Schools package in order to meet the funding criteria for the Urban Cycleways Fund.

Targets for the package are:

·      Extend and further develop existing key walking and cycling networks.

·      Target schools to make walking and cycling for schools children easier and safer, thereby reducing peak hour vehicle congestion.

·      Reductions in deaths and serious injuries as a result of road crashes.

·      More transport choices, particularly for those with limited access to a car.

·      Reductions in adverse environmental effects from land transport.

·      Contributions to positive health outcomes.

4.2.3.   Local Road Maintenance and Renewals

The guiding level of service relating to local road maintenance and renewals is:

Table 4.4       Level of Service Relating to Local Road Maintenance and Renewals

Level of Service

Performance Indicator

Current Performance

Performance Target

MAINTENANCE

The Network, and its services in good condition and are “fit for purpose”

Smooth Travel Exposure*

87%

87% based on NZ Transport Agency standard roughness limits in ONRC

The Network, and its services in good condition and are “fit for purpose”

Average road roughness standard (National Association of Australian State Roading Authorities) by road classification.

Local, 106

Rural Sealed, 97

The following maximum average road roughness are not exceeded:

Local,120

Rural sealed, 120

The Network, and its services in good condition and are “fit for purpose”

The percentage of the local road (non State Highway) that is resurfaced*

4.8%

7.4%

Every formed Council owned road is recorded in the Road Asset Maintenance Management database. This database records pavement and surfacing, streetlights, footpaths, construction and maintenance history, inspection data and traffic volumes.

NZ Transport Agency uses the National Association of Australian State Roading Authorities[2] reading to determine the average road roughness. Nelson City Council has used National Association of Australian State Roading Authorities ratings to determine if additional funding is necessary to maintain the roads to an adequate roughness level. Figure 4.5 below shows the current average road roughness standard (National Association of Australian State Roading Authorities) by road classification. This shows a long-term decline (improvement) in roughness linearly, but an increase (worsening) in roughness during the last year for principal, sub collector and local roads.


 

Figure 4.3     Average Road Roughness Standards (National Association of Australian State Roading Authorities) by Road Classification

Smooth Travel Exposure (STE) provides a measure of the proportion of vehicle travel that occurs on roads that meet the roughness limits. Due to the complications in assessing the financial implications of committing to a higher target than already being achieved further analysis will be undertaken once the ONRC is operative. The current level of STE is expected to be maintained for the next three years due to the resurfacing of a large section of Waimea Road and has been used as the performance target in this AMP. A new limit will be set for the next Transport Asset Management Plan once the new ONRC results can be interrogated.

The upper limit of the performance target of 7.4% of the network to be resurfaced annually has been set based on the area estimated as able to be resurfaced with the budgets detailed above. The lower limit of 5.4% of the target allows for some level of uncertainty associated with the cost fluctuations in raw materials increases in contract labour costs and poor ground conditions. The range also allows for the programme to be changed should opportunities for further optimisation be identified.

4.2.4.   Road Surfaces

Up until the last six years, NZTA supported the use of theoretical seal lives that had been previously published by their predecessor, Transit NZ in 2005. Since then, Councils have been required to extend the life of all of the pavement surfaces that they maintain until all of their practical life has been utilised. In order to provide some assessment of the likely future costs associated with maintaining Nelsons roads, a revised seal life table has been developed that more accurately reflects the practical life of the sealed surfaces in Nelson. These seal lives have been based on the following factors:

·      The current age of the existing surfaces

·      The age of the surfaces programmed for reseal after visual inspection

·      The experience of Council’s road maintenance staff

The practical seal lives are shown in Table 4.5 with each entry colour coded according to the confidence that Council officers have for each particular entry. Green represents areas of very high confidence, orange represents moderate to high confidence and red represents low confidence.

Table 4.5       Practical seal lives in Nelson

While the table above seems to illustrate a high level of uncertainty overall, the areas shown in red do not represent a very high proportion of the sealed area in the Nelson road network. The proportion of each surface type and corresponding traffic volume range is shown in Table 4.6.


 

Table 4.6       Proportion of Road Surface in Nelson by Type and Traffic Volume

Table 4.6 shows that almost all of the road network (approximately 93%), by area, is of a type that there is high confidence in the practical surface life. The revised surface life table is therefore considered to be fit for purpose in assessing the likely forward renewal cost of the sealed surface.

It is noted that the practical surface life table above details lives for each surface type in a location that is appropriate. For example, AC16 will almost always last a lot longer if used in the same location as AC10. In practice though, AC16 is never used in the same location and is instead reserved for use in much higher stress situations.

Currently there is a change in seal technology towards more environmentally sound and safer to use products. Further effect on the seal lives are driven by the changes in the New Zealand vehicles fleet to front wheel power steering cars in particular. These newer vehicles put the road surface under additional stress.

With these changes comes uncertainly around the life of the surfaces. As a result the surface life table will need to remain a live document that is revised regularly to reflect the latest information that Council has about its road surfaces. The table will be updated at least every three years after the major inspection and programming of critical surfaces for resurfacing that takes place in order to inform both the next Transport AMP and RLTP.

The practical seal life table allows an assessment of the whole network how much of it is due for reseal in each year. To follow this, a likely cost can be calculated. The following assumptions were made in undertaking this assessment.

·      All asphalted surfaces will be replaced with asphalt at an average cost of $30/m2

·      All non-asphalt surfaces will be replaced with a two coat grade 3/5 chipseal or similar at an average cost of $6.80/m2

·      Council staff time programming and managing the reseals is 4% of the total cost

·      Lifting services and remarking is 5% of the total cost

Figure 4.4 shows the projected resealing maintenance (or backlog) liability, proposed spend and remaining liability after spend for each of the ten years beginning in the 2015/16 financial year.

Figure 4.4     Expected Future Resurfacing Costs/Liability

In summary Figure 4.4 shows the following:

·      There is a very large backlog of surfaces that have exceeded their practical lives and need to be replaced urgently. This is supported by Council staff observations that have shown that they have been unable to reseal all of the critical surfaces in the 2014/15 financial year and as a result will need to undertake more repair work.

·      If Council was to catch up and keep up with the reseals that are needed, when they are needed then around $6.3M would need to be spent in the 2015/16 financial year followed by $1.3M and $1.1M for the two years following.

·      It is proposed to spread the backlog over the next 8 years as shown by the red bars. This results in a spend of $1.33M each year for the 2015/16, 16/17 and 17/18 financial years followed by $1.4M each year for the following three years. The spend then drops to around $1.1M from 2021/22. The spend in each year includes a proportion of the backlog plus the area due for replacement in that particular year with the backlog likely to be prioritised first.

·      Even though the backlog has been spread over eight years the discharging of the overall maintenance liability associated with the reseals essentially takes a full 10 years from 2015/16.

Of note is the fact that the presence of this backlog will result in a future ‘hump’ that will occur approximately every 15-16 years requiring an annual investment of around $2.8M at peak. This does not show in the ten year period covered by this Transport AMP but first begins to appear again in around 2030/31.

Figure 4.5 shows the Surface Condition Index, which is a measure of various survey faults (cracking, flushing, potholes, rutting, scabbing, shoving, patches) and surface age. (The lower the surface condition index the better the pavement is). The figure shows an improvement in the Surface Condition Index since 2008 after a significant increase (worsening) between 2004 and 2008.

Figure 4.5     Road Network Surface Condition

 

The results in Figure 4.7 above show that we are effectively managing the aged surfaces by targeting those in worst condition. More high volume roads in the network have been asphalted which has further contributed to the improvement in the Surface Condition Index. This data is a snap-shot in time only and does not provide any assessment of future maintenance needs in time to allow effective response to any issues.

4.2.5.   Pavement Renewals

For pavement renewals Council utilises field measurements, maintenance history and engineering judgement to programme works. The quality of renewals undertaken may be affected by the requirement to justify planned works with NZ Transport Agency prior to funding approval. Works which cannot be justified from a whole of life maintenance analysis will not receive a subsidy and as a result may be deferred. Funding applications are yet to be completed for the renewals work identified in section 5.3.3 so at this stage the extent of deferred renewals, if any, is unknown.

4.2.6.   Implementation Package for Local Roads, Walking and Cycling and Schools

4.2.7.   Walking, Cycling and Schools

There is a clear correlation in Nelson between arterial congestion in the peak hours and school term times. Around 56% of New Zealand children are driven to school each day, increasing from 45% in 1998.

Driving to school instead of walking reduces children’s physical activity and increases traffic congestion and air pollution. Nearly every part of the city is within 500m from a school, which is considered an acceptable walking distance for most children. Clearly improving the walking and cycling facilities around schools has the potential to change the way students travel to school and alleviate peak hour congestion at the same time.

Some of the projects, activities and plans proposed that relate to schools are:

·      Encourage Walking School Buses, Feet First & Walk to School promotions, Bike Wise, and other events and activities designed to promote and encourage using active transport as a mode of travel to and from school, with liaison with the schools.

·      Improvement of School Entrances and frontages to encourage active modes.

·      Increased parking enforcement around schools.

·      Delivery of cycle skills education courses in both schools (and the wider community) as part of the regional RIDE ON cycle strategy. This strategy includes working alongside recreational providers to run activities that encourages cycling in general and in particular safe cycling practice.

·      Ongoing encouragement of active modes delivered through council publications and media such as Live Nelson.

4.2.8.   Local Roads

Local roading investment requires expanding if overall service levels are to be maintained. In 2012 the reseal budget was increased although the roading maintenance budgets were frozen and have not kept pace with the expansion of the network though subdivision development, or inflation. This has led to deterioration in the performance of the network.

Additional local roading maintenance and renewal projects proposed to maintain the existing level of service are:

·      Increase sealed pavement maintenance budgets from $469,000 to $500,000.

·      Resurfacing budget from $1.33 million/year for the first three years before increasing to $1.4 million for years 4-6 and then reducing to $1.1million/year for year 6-9 to ensure the sealed surfaces keep the high value base course layers dry.

·      Increase structural replacement programme for bridges and retaining walls via the structures component replacement budget of approximately $330,000 pa.

·      Increase for streetlight renewals costing approximately $270,000/year to allow the replacement of poor performing lights with LED luminaries.

·      Provide a pavement renewal budget in the order of $350 pa.

·     

·      The LTP has amended the following:

·      For years 6-9, the reseal budget remains at $1.4 million.

·      Structures component replacement budget reduced to $295,000 in year 1 but increased to $500,000 in year 2.

·      It is noted that the level of funding to be received from NZTA is less than originally budgeted for maintenance and renewals. There is potential for additional funding to become available from the NZ Transport Agency in years 2 and 3. In response, Council has retained the renewals budget in years 2 and 3. This will ensure that the local share will be available should NZTA provide further funding. If not, the renewals budget will be varied in these years at the annual plan stage.

Other local roading capital projects proposed to improve the Levels of Service are:

·      Continue to implement street lighting upgrade programme to enable safe and easy night time driving, and expansion of lighting to shared walk/cycleways such as the Railway reserve.

·      Safety upgrades at the intersection of Toi Toi Street and St Vincent Street.

·      Upgrade only those roads where traffic volumes, safety issues or utilities upgrades justify a full upgrade.

·      Increase in the Minor Improvement Programme to $650,000 pa.

·      Finish implementation of the walking/cycling and schools package identified in the Regional Land Transport Programme 2012-15. Note that it is not intended to update the Council’s Pedestrian Strategy (2005) or Cycling Strategy (2006). Nelson is far enough advanced in its walking and cycling implementation that it would not add any benefit to its Walk / Cycle funding package, rather walking and cycling is included in this AMP and in the RLTP.

·      Continue to enhance the Central Business District through works identified in Heart of Nelson and other new priorities. $100,000 has been allowed for in year 1 and $500,000/year for years 2-10.

·      Provide a footpath improvement budget of $50,000 for the first year for design and the $200,000/year for years 2-10 to provide missing footpath links.

The budgets for CBD enhancement were changed to $50,000 in year 1, $250,000 in years 2 and 3 and $300,000 in year 4. No budget has been allocated for years 5-10.

POLICY NOTE: - With the installation of the ultra fast broadband cabling in many streets and footpaths there is an opportunity to provide a small proportion of funding to resurface the total width of the footpaths when the trenches are being reinstated. This is excellent value for money although the opportunity to upgrade these footpaths to the 2010 Land Development Manual standards is limited. It is proposed that the footpath renewals budget be utilised to facilitate this and similar future opportunities.

Other local roading capital projects proposed to cater for growth are:

·      Rural Road seal extensions - It is proposed to use recycled asphalt millings to seal rural roads. These will not be reconstructed to full Land Development Manual standard but surfaced to minimise the ongoing maintenance required, reduce dust issues and improve safety.

·      Todd Bush Road.

·      Marsden / Ridgeway intersection.

Council has an ownership responsibility to manage the road reserve in a cost effective, sustainable, well planned and coordinated manner to agreed levels of service. Council has a number of individual policy and procedures, many of which require updating. It is proposed that an overarching Road Management Policy is developed to include:

·      Road Reserve Management Policy and Procedures;

·      Road Reserve Operations and Maintenance Policy;

·      Road Occupation Policy (Structures on Road Reserve);

·      Parking Policy;

·      Road Stopping, Sale and Acquisitions Policy;

·      Speed complaints procedure;

·      Signage Policy;

·      Power and Telecom Undergrounding Policy;

·      Roading Improvement Policy.

4.3.     Arterial Traffic

These service levels provide the other half of a balanced network approach by recognising the importance of well located, strong transport corridors that offer the potential for the efficient and safe flow of people and goods to assist the economic vitality of our region. The service levels contribute to the government outcomes providing “an efficient transport system that supports high levels of economic productivity, provides strong international connections for freight, business and tourism, and meets international obligations” and the community outcome of people friendly places - “We build healthy, accessible and attractive places and live in a sustainable region”.

Council’s main arterial corridor is from the Queen Elizabeth II / Haven Road roundabout, along Haven Road, Halifax Street, Rutherford Street, Waimea Road and Main Road Stoke and the link from the State Highway / Annesbrook roundabout to Main Road Stoke along Annesbrook Drive. The other corridor routes, between Annesbrook roundabout and the Beatson Road roundabout, and along the state highways are owned and managed by NZ Transport Agency.

Delays in arterial traffic travel times and a widening of the peak travel periods are an indication of inefficient use of transport routes and have a negative impact on economic productivity. By monitoring travel times and peak spread on key routes we can see whether these routes are efficient. Appendix H shows graphically the peak spread and delays on the Rocks Road and Waimea Road corridors.

The current average delays have been measured to be 3 minute on Rocks Road and 2 minutes on Waimea Road. It is noted that the dataset for this measurement is very small due to the complexities associated with collecting the data. Nelson City Council has partnering with NZTA and installed a wireless detection system to measure travel times. This improvement in technology will allow a much larger sample to be collected and improve the effectiveness of this measure.

Table 4.7       Level of Service Relating to Efficient Transport System

Level of Service

Performance Indicator

Performance Target

An efficient transport system that enables people and freight to move efficiently.

Average AM and PM peak hour travel times on Waimea Road and the State Highway between Annesbrook and Haven Road roundabout.

Average peak hour travel time delays are no greater than 5 minutes above uncongested travel times.

The Nelson to Brightwater Corridor Study model provides levels of service for the transport corridors. Generally a level of service of C or above is considered appropriate for local arterial transport roads. The definition of the level of service along with classification of the key corridors is provided in Appendix F.

The 2009 modelling predicts that current levels of service are below C around the three roundabouts which connect the State Highway 6 to Main Road Stoke and Salisbury Road, close to the Nelson/Tasman boundary and along parts of Waimea Road. Observations of these intersections confirm that they continue to operate at a level of service worse than C and are likely to continue to in the foreseeable future.

The 5 minute delay defined as the performance target represents an average delay of around 1 minute per kilometre over the measured distance. Based on the Austroads Guide to Traffic Management Part 3: Traffic Studies and Analysis, Sections 5.2.2 and 5.2.3, this level of delay is expected to result in a level of service of C for the route as a whole. The descriptions of the level of service flow characteristics contained in the Austroads guide are similar to those contained in Appendix F.

Nelson City Council has used National Association of Australian State Roading Authorities ratings to determine if additional funding is necessary to maintain the roads to an adequate roughness level. Figure 4.3 shows the current average road roughness standard (National Association of Australian State Roading Authorities) by road classification, along with proposed target levels.

Table 4.8       Level of Service relating to Road Network and Its Services

Level of Service

Performance Indicator

Performance Target

The network, and its services in good condition and are "fit for purpose".

Average road roughness standard (National Association of Australian State Roading Authorities) by road classification.

The following maximum average road roughness are not exceeded:

Arterial/Principal, 100

Collector/Sub C, 110.

4.3.1.   Implementation Package for Arterial Traffic

Many of the local roading maintenance and renewal initiatives identified in 4.2 above also include, and prioritise the arterial roads. These budgets are not split between local and arterial roads and it is not considered necessary to do so, but the budgets allocated include all local roads and arterial roads.

The 2012 AMP included an action to update the transportation modelling, undertaken as part of the Arterial Traffic Study, once the 2013 census data became available. Closer examination of the traffic data on the main arterial routes has shown that, while all of the growth in population and households assumed in the model has been realised, the arterial traffic volumes have been reducing to a level well below those predicted in the model. As a result an update of the model will not change any of the Arterial Traffic Study recommendations other than to push the need for any works further into the future than previously recommended. It is proposed instead to monitor traffic volumes closely and look to update the model after the next census unless it is carried out sooner by the NZTA for the purposes of investigating the Southern Arterial.

Council has investigated some of the transport issues that relate to the poor peak hour travel time performance of the arterials, such as the arterial traffic study, the NZ Transport Agency / Nelson City Council / Tasman District Council three roundabouts study and the Waimea Road intersections.

Capital projects to improve the level of service and provide for future arterial traffic growth include:

·      Annesbrook Drive crossing facilities;

·      Update and review the transport model following the 2018 Census (in partnership with NZ Transport Agency and Tasman District Council as the model ownership is equally shared);

·      Provide off-street car parking in Tahunanui near the Bisley Avenue intersection to allow reinstatement of the two southbound through lanes;

·      Complete the cycle link on SH6 between the Crop and Food building and the recently completed Maitai walkway;

·      Rocks Road walking and cycling facilities;

·      Projects identified in the Regional Land Transport Plan;

·      Increase frequency of NBus on the arterial routes.

A number of intersection improvements proposed by the Arterial Traffic Study have been found to delay through traffic on the arterial roads to a level that any major improvements to the intersections cannot be progressed on economic grounds. Instead it is proposed to undertake more modest work in order to improve safety in particular.

4.4.     Safety

This service level is an essential part of managing the transport network and has been chosen to align with “Safer Journeys” which is the government’s strategy to guide improvements in road safety over the period 2010 to 2020. The strategy’s vision is “a safe road system increasingly free of death and serious injury”.

The safe system approach to road safety recognises that drivers make mistakes but should not die or be seriously injured as a result. As a local road controlling authority, Nelson City Council has a part to play in providing safe roads and roadsides along with safe speeds on the roads that it administers.

The road safety service level statement is:

“To work towards a safe road system increasingly free of death and serious injury”.

The Local Government Act 2002 requires all road controlling authorities to have a level of service relating to the number of fatalities and serious injuries and report on these annually.

 

Table 4.9       Level of Service Relating to Road Safety

Level of Service

Performance Indicator

Performance Target

Road safety.

Number of deaths and serious injuries in road crashes

Reducing at 4% per year from a base of 2007

Figure 4.6 below shows that since 2007 the number of fatalities and serious injuries on Nelsons Roads has fluctuated at or above the target maximum.

Figure 4.6     Number of Fatal and Serious Injuries on Local Roads in Nelson

Around half of all urban crashes on the network are at intersections, and of these intersection crashes, the worst intersections account for a significant proportion of the overall social cost.

Table 4.10     Level of Service Relating to Road Safety at Intersections

Level of Service

Performance Indicator

Performance Target

Road safety.

Annual social cost of crashes (injury and non-injury) at intersections.

The social cost for each year reduces by at least 4% per year from a base of 2007.

Figure 4.7 below compares the social costs of all intersection crashes since 2007.

Figure 4.7     Total Social Cost of Urban Intersection Crashes (Injury and Non-injury)

It is important that the focus on road safety is driven by robust criteria for selecting intersections for improvement works. As with anything associated with road safety it is critical that specialist road safety engineers assess any intersections identified to confirm the need for their inclusion in any forward work program.

In general, crash rates at intersections between local (non state highway) roads are lower than the thresholds that can justify standalone safety improvement works. Instead, the intersections with higher crash rates in the Nelson context will be treated via use of the minor improvements budget.

Nelson cyclists initially appear to be over represented in casualty data compared to other peer group locations. This measure of over representation has traditionally been the number of cycle crashes as a proportion of total crashes. This does not provide a reliable measure of performance when compared to the rest of peer group B (Palmerston North, Napier and Invercargill) as the number of people cycling on the network is not taken into account. Instead it is important that Nelson City strives to provide continued improvement to its cycle network to reduce the vulnerability of cyclists regardless of what other regions in New Zealand are achieving.

With the intention to continue to provide infrastructure and promote cycling in Nelson City it is important that any development of cycling infrastructure be done in a sustainable safe manner. As a result the indicator for cycle crashes recognises the likelihood of increased cycle use.

 

Table 4.11     Level of Service Relating to Road Safety and Cyclists

Level of Service

Performance Indicator

Three Year Performance Target

Road safety.

Number of crashes involving cyclists.

Nelson City cycle crash numbers do not increase from those in the base year of 2007.

 

 

 

Figure 4.8 shows that the number of crashes in the last three years has gradually increased to be above the target maximum of 23 crashes in any one year.

Figure 4.8     Number of Cyclist Crashes in Nelson City

The total social cost for cycle crashes measures the overall cost of the crashes in terms of medical, economic, productivity and physical cost associated with causalities in particular. In 2012 the total social cost of all cycle crashes in Nelson was $8.8M, a high for the last complete five year period. This reduced to around $5.7M in 2013. This measure provides some context in relating the cost of safety improvements for cyclists and the potential savings.

Pedestrian crashes in Nelson are typically clustered around the three main business districts in Nelson, Tahunanui and Stoke as well as around each of the schools in the area. In particular, any crash that involves a pedestrian has a much higher chance of resulting in serious injury or death. This results in relatively focused areas where safety related spending for pedestrians can be concentrated. With this in mind a falling cap of pedestrian related crashes is appropriate as follows.

Table 4.12     Level of Service Relating to Road Safety and Pedestrians

Level of Service

Performance Indicator

Three Year Performance Target

Road safety.

Number of crashes involving pedestrians.

The number of crashes involving pedestrians each year reduces by at least 4% per year from a base of 2007.

Figure 4.9 shows that the number of crashes involving pedestrians has increased above the number in 2007 and are not reducing in line with the target maximum. This indicates that further effort and spending in this area of road safety is needed.

Figure 4.9     Number of crashes involving pedestrians in Nelson City

4.4.1.   Implementation Package for Safety

The Safer Journeys: New Zealand’s Road Safety Strategy 2010-2020 published by the Ministry of Transport proposes a Safe System approach which focuses on creating safer roads, safe speeds, safe vehicles and safe road use. Clearly local authorities are tasked with three of these four focus areas, and delivering in these areas will also contribute to the levels of service identified above.

The Safe System approach is implemented in a coordinated way with other sectors of the Nelson Community (Tasman District Council, New Zealand Police, Accident Compensation Corporation, Nelson Marlborough District Health Board, NZ Transport Agency) through the Nelson Tasman Road Safety Action Plan.

Some of the projects, activities and plans proposed for safer roads are:

·      Intersection improvements, targeting high risk intersections.

·      Capital works providing improved walking and cycling facilities.

·      Targeted minor improvements programme focussing on schools, walking and central business district minor safety projects.

·      Improved line marking and street lighting.

Some of the projects, activities and plans proposed for safe speeds are:

·      Targeted minor improvements programme focussing on speed issues.

·      Speed limit reviews that consider changes over local roading areas i.e. around hospital and Waimea Road.

·      Local road treatments to reduce the speed environment such as through intersection changes, line marking upgrades, the installation of flush medians, installation of street trees etc, where appropriate.

·      Lobbying government to make changes to the Road User Rules to allow greater speed enforcement to be used to reduce speeds rather than rely on expensive road treatments.

·      Implementation of the speed reduction methods in the Land Development Manual and Shared space ideals when considering roading capital improvement projects.

·      Implementation of an urban speed reduction programme delivering stopping distance demonstrations, including emphasis on speed around schools, a “Wipe off 5” multimedia campaign (similar to that run in Victoria, Australia), and a community development and neighbourhood ownership programme calling for safer speeds and increased acceptance of traffic calming on local roads.

·      Install arterial pedestrian and cycle crossings.

Some of the projects, activities and plans proposed for safe road use are:

·      Campaigns that promote to motorists the “share the road” message will be run along with ongoing support for data collection through 0800CYCLECRASH.

·      Youth Education and information initiatives to this high risk sector will continue to be delivered.

·      Continuation of the RYDA programme which co-ordinates the efforts of local road safety experts, driving instructors, the Police, recovering victims of road crashes, drug and alcohol educators and insurance and financial services personnel in such a way that 1500 year 11 students are made aware of the privilege, cost and responsibilities of owning and driving a motor vehicle.

·      Six motorcycle training courses using qualified instructors with at least two of these courses aimed at the younger scooter riders, publications on license requirements and a print based publication aimed at riders and other motorists.

4.5.     Public Transport

In early 2012 Council commenced an improved passenger transport service funded from increased parking charges. Council’s strategic direction on Passenger Transport is outlined in the Draft Regional Public Transport Plan [under development in 2014 in parallel with the Regional Land Transport Plan].

The service level is targeted towards providing the user with transport choices and as a means of reducing traffic congestion.

A review of the new service was undertaken in 2013. This review report can be found at A1119385. The review found that the service is operating well on the arterial routes. However the collector routes are less successful.

In 2014 some early and late services on the collector routes were cancelled to fund a weekend service on the Waimea Main Road Stoke Arterial Route.

Table 4.13     Level of Service Relating to Public Transport Services

Level of Service

Performance Indicator

Performance Target

Public transport services that meet the transport needs of the community with an equitable sharing of costs.

The farebox recovery ratio.

50%

Since the introduction of the NBus public transport system the fare recovery ratio has increase from around 60% in the 2012/13 year to 62% in 2013/14. Prior to this period the bus system was privately run and the fare recovery ratio is unknown.

4.5.1.   Implementation Package for Public Transport

·      Update and implement the Regional Public Transport Plan for 2015-18 including:

·      Increase network coverage in Stoke

·      Continue with public transport promotion to encourage an increase in patronage.

·      Continue with the bus shelter installations and upgrades.

·      Conduct user and non user surveys every 2 years and use feedback to improve services.

·      Construct additional infrastructure on hail and ride routes to increase visibility of service.

·      Continue to work with Tasman District Council with a view to improve the network coverage in Richmond

·      Implement real time bus tracking

4.6.     Parking

Parking revenue, sundry rents such as street dining and street stalls are used to fund the Inner City Enhancement account. Inner city expenditure covers many activities such as maintenance of the meters and brickwork, rental charges for private land occupied by the public, rates, grants for inner city co-ordinator, hanging baskets, Central Business District litter collection and depreciation, operations and maintenance, renewals and enhancement works. Council also recognised in the 2011 Annual Plan that increasing parking charges was a useful travel demand management tool to encourage sustainability and to optimise the networks resilience by using the additional income to subsidise the passenger transport improvements. Recently however, Council has indicated that the contribution to passenger transport will cease to come from the Inner City Parking account at the end of the 2014/15 financial year and come from general rates.

Currently, any surplus or deficit in the Inner City Parking account, once the contribution to passenger transport is made is transferred to or from the Parking Reserve and if there are not sufficient funds, the shortfall is borrowed. The Parking Reserve also acts as the balancing account for Parking Enforcement and the Millers Acre property account.

As most vehicular journeys involve parking at both the start and end of each trip, the availability and cost of car parking can influence decisions on transport mode used, the time of travel and, potentially, the choice of destination. The provision of parking facilities also impacts on the urban environment and may take up valuable space, thereby increasing property development costs.

A balance must be struck between the provision of an adequate supply of parking to meet the needs of a dynamic, competitive economy, optimising valuable city centre land and encouraging the use of good alternatives to single occupancy vehicles.

Essentially short stay parking should be of sufficient capacity, carefully costed, well located and accessible. Long stay parking should not compete with short stay capacity, and should align with the wider transport policy.

The Parking service level statement is:

“Parking is easy to use, and is rationed fairly and equitably”.

There are approximately 1,440 short stay parking spaces in the central core area; these had a peak midweek and Saturday occupancy in December 2012 of around 90%. This equates to around 140 free spaces in the central area at peak times. These peak times tend to be in the middle of the weekdays, between 11am and 4pm and between 11am and 12.30pm on Saturdays.

Table 4.14     Level of Service Relating to Short Stay Parking

Level of Service

Performance Indicator

Performance Target

The supply and pricing of short stay parking managed to encourage commercial activity in the city centre.

Percentage of short stay parking spaces occupied in midweek peak in December.

85%

Table 4.15     Level of Service Relating to Parking

Level of Service

Performance Indicator

Current Performance

Performance Target

PARKING

The supply and pricing of long stay parking is managed to incentivise greater use of travel options other than cars.

Occupancy of long-stay parking spaces between peak travel times measured at 5 locations within the CBD fringe.

Not currently measured but will be in the future.

A reducing trend.

Should occupancy rates drop constantly below the performance target then Council should consider relaxing the short stay time restrictions. Should occupancy rates be constantly above the performance target then Council should consider increasing parking fees or making more short stay spaces available within the CBD.

The distance recognised in the New Zealand Pedestrian Planning Guide as being the optimum maximum distance commuters should be expected to walk from their car to their work is 1.6 kilometres, which is a 20 minute walk at 5 kilometres/hour for a fit healthy adult (ie 450m takes 5 minutes and 900m takes 10 minutes). This distance puts much of the fringe area of the Central Business District within parking distance of the core of the Central Business District. Uncontrolled all day commuter parking currently occurs in many residential, commercial and light industrial areas of the Central Business District fringe area. It is important that as pressure on parking grows in the future this uncontrolled parking should be rationalised to minimise its impact on the viability and value of the fringe areas and more use of multiple occupant vehicles and public transport encouraged.

An acceptable walking distance is a relatively fluid concept. Some people happily walk many kilometres, while even short walks are difficult for the elderly, disabled or children. By far the majority of city centres are about 1km across. This means a walk of a kilometre or less will bring pedestrians around most of the functions of the city.

Table 4.16     Level of Service Relating to Long Stay Parking

Level of Service

Performance Indicator

Performance Target

The supply and pricing of long stay parking managed to incentivise greater use of transport options other than cars.

Occupancy of long-stay parking spaces between peak travel times measured at five locations within the CBD fringe.

A reducing trend.

A parking study was undertaken in 2014 that informed the development of the draft ‘Parking Strategy 2014-2024’.

Survey data collected in 2005, 2008 and 2012 shows there is an appropriate supply of parking. Forecasting indicates there is unlikely to be any significant increase in demand over the next ten years.

The engagement undertaken has indicated that the Nelson public consider the key parking issues to broadly be:

·      Enforcement – Since September 2013 parking enforcement has been undertaken by EIL. This has returned the level of enforcement to those prior to 2011. There is a perception this level of enforcement is too stringent and that enforcement should be more flexible.

·      Cost and payment options – Users of the parking in the CBD want payment options that provide more choice and flexibility.

·      There is a desire for more all day parking within the CBD together with an overall increase or redistribution of parking.

Subsequent to the draft parking strategy being prepared, Council, in response to the concerns of inner city retailers, resolved to remove the charge for parking for a winter trial period. As a result, finalisation of the strategy has been delayed until after this AMP has been completed. This AMP allows for the implementation of the actions detailed in the draft parking strategy but recognises that the direction and content of the parking strategy may change and some actions may not be necessary or other options may be trialled to ascertain their impact before the future direction is set.

Council resolved during the LTP deliberations to make the first hour of parking free to users and then increase the hourly rate to $1.50 for any time after.

4.6.1.   Implementation Package for Parking

·      Provide more payment choices at parking meters;

·      Manage the current parking supply to ensure the most sought-after parking spaces are available to be used by visitors to support the economic viability of the central CBD and Stoke;

·      Trial the allocation of car pool spaces in high demand, high visibility locations in the city centre. Promote the trial with existing and potential users;

·      Work with a CBD focus group to implement schemes to encourage visitors in the quiet winter months and focus on alternative transport modes to the private motor vehicle;

·      Improve the layout and access to Strawbridge Square carpark;

·      Secure a pedestrian corridor between Beach Road and Tahunanui Drive to enable better use of the Beach Road carparks;

·      Provide better information for drivers to find parking areas such as improved signage from the CBD ring route to the parking squares.

4.7.     Value for Money Principles

Value for money means a culture of continually seeking better and smarter services and ways of operating the transport activity. This is a concept that is high on the agenda in the Draft Government Policy Statement on land transport funding which seeks to make better use of the land transport network. Improved network management and selective development is needed to lift the performance and capacity of the existing network and minimise the need for major investment in new infrastructure.

The following implementation package will ensure value for money:

·      Road maintenance procedures will be used in a way that will optimise the amount of benefit gained from the money spent.

·      Investigation of collaboration and shared services with Marlborough District Council and Tasman District Council.

·      Improved asset management to ensure renewals are optimised.

The public will base much of the perception of value for money on how the Council delivers road improvements. The Council operates a road improvement policy which is aligned with value for money principles. This means improvements shall provide a high level of public amenity within the road that reinforces the importance and value of roads as public places. Upgraded roads would enhance personal security, facilitate slow vehicle speeds in residential areas and accommodate people that are less able or vulnerable, such as those with mobility and visual disabilities. The minimum standards in the Land Development Manual 2010 will reinforce the quality and therefore perceived value of the works.

Table 4.17     Level of Service Relating to Public Satisfaction

Level of Service

Performance Indicator

Performance Target

Public Satisfaction.

Percentage of public satisfied and dissatisfied with the transport activity (based on Nelson City Council Annual Residents Survey).

More than 50% of respondents are either very satisfied or satisfied, and less than 10% are either dissatisfied or very dissatisfied.

Figure 4.10   Percentage of Public Dissatisfied with the Transport Activity

A key driver for public satisfaction in terms of value for money is provision of good communication to explain issues to public. Key issues that the Council convey or intend to convey to the public include:

·      Importance of the arterials.

·      Parking policy and no-stopping lines.

·      Issues around local road speeds.

·      The success public transport improvements.

·      Council’s strategic direction.

·      Key safety issues for Nelson.

·      Congestion explanations.

·      Conflict on shared paths.

·      Structures on road reserve.

·      Resurfacing policy.

·      Traffic calming measures and techniques.

·      Explaining how council develops its minor improvements and footpath and road upgrade programme.

Much of this information is provided within the policies on the Council Website and is included in Live Nelson when the topic is in focus. It is important for the public to understand the rationale of the Council’s decisions and processes. It is hoped that with increased public understanding the value of Council transport activities and projects will be perceived to be positive.

Recent projects and studies have used the consultation section of the Nelson City Council website to communicate with residents. The Council’s transport staff also participate in as many forums as practical to answer questions raised by the public and providing explanations on transport issues. Talking this approach supports the value for money principles by engaging with the public and making sure the opinion of the public is heard.

It is important that the community knows the Council is listening and addressing their concerns, which the Council is committed to doing.

The Council also responds to requests from the public in a timely manner which is managed by the service request system which will help to elevate the satisfaction levels of the public.

4.8.     Systems to Measure, Monitor and Report on Performance Indicators

4.8.1.   Local Roads, Walking, Cycling and Schools

Much of the performance of the local roads is contained within the Council Road Asset Maintenance Management database. The road roughness and rating is gathered through surveys over the entire network every two years and reported on in the Infrastructure Annual Reports. The latest computer software running the Road Asset Maintenance Management database allows any Road Asset Maintenance Management information to display spatially on maps so any areas that may fall below the performance indicator levels can be identified.

The footpath network undergoes an audit every three years for the quality and safety of the network. This not only enables the performance to be measured but also maintenance work to be programmed. The results of the audits can be found in the Footway Audit Report.

The rate of walking and cycling can be measured in two ways. Firstly the census results which are freely available from Statistics New Zealand contain information on the mode of travel people chose to get to work; including by cycle or by foot. This information is gathered every five years. The second method is through the Annual Residents Survey as it contains questions in relation to the surveyed persons choice a travel mode. These results are published in the Council Survey of Residents report.

The regular cycle counts at key screen lines in the cycle network reveal the trends in cycling and provide some insight into whether the targets for increased cycle use are heading in the right direction.

4.8.2.   Arterial Traffic

The Council owns a TRACKS strategic transport model that was built in 2006 for the Nelson to Brightwater Study and updated in 2009 for the Arterial Traffic Study using 2006 census data. The validated model shows the Level of Service in terms of congestion and intersection delay. The Council intended to update the model in 2014 with the latest census data. However there was not enough change from the 2009 update to justify the expense. The Level of Service for the Waimea Road and SH6 Arterial routes can be checked and compared to the performance indicators and reported in the model reports.

The Waimea Road arterial route is of significant importance to the Council because it is not a state highway and therefore the sole responsibility of the Council. The Council assesses this route more frequently through monitoring travel times every quarter and volumes monthly.

From 2015 travel time surveys will be undertaken using wireless detection methods. This will provide a much larger sample than the current car following method.

4.8.3.   Safety

The statistics for accidents involving motorists, cyclists and pedestrians are a good indicator on how safely the transport network is operating. These statistics are gathered by the New Zealand Police and processed by the NZ Transport Agency using their Crash Accident Database. The accidents within the City of Nelson are extracted yearly so that the accident rates can be compared with the peer group average from around New Zealand. This also enables the progress of road safety to be monitored.

Additional cycle crash data is collected via the 0800 Cycle Crash hotline. This hotline is a joint initiative with TDC, NZ Transport Agency and ACC and designed to capture all of the crashes and near misses involving cyclists that do not typically make it into the NZ Transport Agency database.

The data is reported with internal annual road safety reports.

4.8.4.   Public Transport

Each quarter the key metrics of patronage and fare revenue by route, by zone and by ticket type are collated and reviewed to monitor the performance of the Public Transport system. At the end of each financial year the Council undertakes a financial analysis of the public transport service. This enables the revenue from the farebox to be compared to the operating cost of the public transport network.

These values are reported in the annual plan and therefore the performance of the public transport network can be monitored over time.

4.8.5.   Parking

The Council undertakes a midweek parking survey each year in December which measures the occupancy of the short stay parking spaces within the central core area. A survey of five sample areas in the fringe area is also surveyed in order to measure commuter parking demands. The peak occupancy is recorded and this can be compared to the performance target occupancy rate. The results are reported within the annual plan.

Every 4-5 years more comprehensive data is collected for the CBD and the fringe areas bordering the CBD. The surveys collect occupancy data for the whole area and duration of stay data for sample areas around the CBD. These surveys are undertaken on a Thursday and Saturday in the first week of December. The report summarising the last data collected can be found in A789874.

4.8.6.   Value for Money Principles

Every year the Council commissions a residents survey to seek feedback on their services and facilities as well as other information to assist them with planning, management and accountability.

The survey contains a specific section on the residents view on whether the Nelson City Council services and facilities are good value for money.

The results of the survey are published in the Council Survey of Residents report.


Transport

Asset Management Plan

2015 - 25

Part 2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


N-logotype-black-wide

 

 


5.       Technical Performance measures/Asset management Systems/lifecycle

This section details the broad strategies and work programmes required to achieve the goals and standards outlined within section 4 of the Asset Management Plan.

It presents the lifecycle management plan for the transport assets, and includes:

·      A brief description of the assets;

·      Expenditure trends;

·      Key issues and strategies for managing these issues;

·      Operations, maintenance, and renewal and development strategies;

·      Financial forecasts.

The transport assets are split as follows:

·      Roads;

·      Road structures;

·      Pedestrian network;

·      Cycle network;

·      Passenger Transport Network;

·      Traffic control and equipment, street lighting, signs and markings;

·      Safety;

·      Parking;

·      Central Business District.

An overview of asset lifecycles is provided below which details the key stages in the asset lifecycle and asset failure. A brief description for the activities and projects outlined in the Level of Service section and this section is provided in Appendix K.

5.1.     Asset Lifecycle

Assets have a lifecycle as they move from initial concept to final disposal. Depending on the type of asset, its lifecycle varies from 1 year to over 100 years. Key stages in the asset lifecycle are described in Table 5.1.

Table 5.1       Key Stages in the Asset Lifecycle

Asset planning

The new asset is designed - decisions made at this time influence the cost of operating the asset and the lifespan of the asset. Other, non-asset solutions, must also be considered

Asset creation or acquisition

The asset is purchased - constructed or vested to Council. Capital cost, design and construction standards, commissioning the asset, and guarantees by suppliers influence the cost of operating the asset and the lifespan of the asset

Asset operations and maintenance

The asset is operated and maintained - operation relates to a number of elements including efficiency, power costs and throughput. Maintenance relates to preventative maintenance where minor work is carried out to prevent more expensive work in the future and reactive maintenance where a failure is fixed

Asset condition and performance monitoring

The asset is examined and checked to ascertain the remaining life of the asset - what corrective action is required including maintenance, rehabilitation or renewal and within what timescale

Asset rehabilitation and renewal

The asset is restored or replaced to ensure that the required level of service can continue to be delivered

Asset disposal and rationalisation

A failed or redundant asset is sold off, put to another use, or abandoned

5.2.     Asset Failure Modes

Generally it is assumed that physical failure is the critical failure mode for many assets. However the asset management process recognises that other modes are relevant and are often critical to effective delivery of services.

Table 5.2       Range of Asset Failure Modes

Structural

The physical condition of the asset is the measure of deterioration, service potential and remaining life

Capacity

The level of under or over capacity of the asset is measured against the required level of service to establish the remaining life

Level of Service Failure

Reliability of the asset or performance targets are not achieved

Obsolescence

Technical change or lack of replacement parts can render assets uneconomic to operate or maintain

Cost of Economic

Impact

The cost to maintain or operate an asset is greater than the economic return

Operator Error

The available skill level to operate an asset could impact on asset performance and service delivery

5.3.     Roads

The service level statement for roads is “Roads are safe to use and provide a comfortable and reliable means of travel.”

The last valuation of the roading network was undertaken in June 2014.

Table 5.3       Road Surface Valuation

 

June 2012

June 2014

Quantity

2,089,091 m2

2,140,850 m2

Replacement value

$ 24,992,982

26,649,423

Depreciated replacement value

$ 14,545,019

14,612,127

Annual depreciation

$ 1,051,059

1,113,452

Table 5.4       Road Basecourse Valuation

 

June 2012

June 2014

Quantity

2,295,969 m2

2,274,622 m2

Replacement value

$ 33,519,591

$ 33,429,410

Depreciated replacement value

$ 18,766,406

$ 15,777,764

Annual depreciation

$ 313,380

$ 364,686

The road network is managed in two ways. Firstly an ongoing maintenance programme addresses road defects through either planned or responsive maintenance and secondly roads are renewed or resealed based on a prioritised forward work programme (repairing those in the worst condition).


 

Expenditure Level (from 2012 to 2015)

·      Sealed pavement maintenance costs, approx $469,000/annum. (Reduction from 2009-12 of $94,000/annum.)

·      Sealed road resurfacing $1,600,000/annum. (Increase from 2009-12 of $650,000/annum.)

·      Sealed road pavement rehabilitation $0/annum. (Decrease from 2009-12 by $236,000/annum.)

·      Unsealed pavement maintenance costs, approx $34,000/annum.

·      Unsealed road metaling approx $65,000/annum.

·      Costs for general management and control of the road network and management of road asset, approx $481,000/annum.

·      Costs for other associated improvements and maintenance and renewals of drainage, approx $157,000/annum.

·      Depreciation approx $1,426,000/annum.

The Key Issues for Roads

·      The major focus of road maintenance is to prevent water getting into the road base.

·      Moisture will soften road base material. We must ensure use of correct surfacing materials in each road section to optimise the surface life.

·      The quality of road reinstatement work by utility operators.

·      Historically resurfacing has occurred without major dig outs to fix road base issues.

·      Increasing frequency of emergency events with the potential reduction in NZ Transport Agency co-investment for the recovery and re-instatement costs.

Strategies for Managing These Issues

·      Ensure both timely resurfacing and good drainage of the road surface so that it provides an adequate wearing and waterproofing course to prevent water getting into the road base.

·      Develop and adopt a surfacing selection guideline; regarding placement of asphalt or chipseal, including bus and cycle lanes with robust site validation processes through visual and experienced based road asset maintenance assessments.

·      An allowance of $200,000 per annum for the recovery of small scale emergency events has been allowed for under the environmental maintenance category.

 

·      In response to NZTA changing their initial advice on the way emergency events would be funded, the emergency works budget has been reduced to $100,000 per year cumulating.

5.3.1.   Asset Condition and Performance

Every formed Council owned road is recorded in the Road Asset Maintenance Management database. This database records pavement and surfacing construction, and maintenance history, inspection data and traffic volumes.

Road Asset Maintenance Management surveys are done every second year to assess the condition of the road pavement and surfacing. Assessments are carried out over a 50m stretch of every road. Long roads are split into sections. The pavement condition rating assesses rutting, cracking, potholes and shoving. The surfacing assessment considers flushing, bleeding, scabbing, ravelling and delaminating of chipseals, asphaltic concrete and slurry surfaces.

The road asset condition has been well documented in Section 4.2, 4.3 and 4.4. The average road roughness across the road hierarchy is below the level of service standard. The Surface Condition Index shows that the surface condition of roads has been improving since 2008.

There is a large section of road network that will exceed the expected life of the pavement over the next three years. There is also a significant length of the network that is older than the expected life which might be contributing to a higher Surface Condition Index than previously experienced.

Table 5.5       Road Surface Data Reliability Analysis

Data Attribute

Very Uncertain

Uncertain

Reliable

Highly reliable

Asset quantity

 

 

 

 

Asset age

 

 

 

 

Condition

 

 

 

 

Performance

 

 

 

 

Table 5.6       Road Base Data Reliability Analysis

Data Attribute

Very Uncertain

Uncertain

Reliable

Highly reliable

Asset quantity

 

 

 

 

Asset age

 

 

 

 

Condition

 

 

 

 

Performance

 

 

 

 

The Council regularly records traffic counts across the city. The counts are recorded monthly or annually depending on their location. The monthly counts consist of five sites on the arterial network. Count data is entered into the Road Asset Maintenance Management database to provide an overall picture of the network’s traffic use.

5.3.2.   Maintenance Strategy

The operation and maintenance of Council’s Transport infrastructure is managed by the Infrastructure Group. The roading maintenance contract was awarded to Downer EDI Works Ltd in 2010. The contract runs for 3 plus 1 + 1 + 1 years thus is due for renewal in 2016. The contract allows for the provision of all road maintenance and includes street and car park cleaning, road markings and signage.

All maintenance costs and traffic count data is recorded and inputted into the Road Asset Maintenance Management database monthly.

A three year forward works programme has been formulated, based on identified works contained within the Road Asset Maintenance Management, "all faults register" and is in the order of $500,000/year for pavement repairs, present repairs and maintenance. The budget is to cover these works and unidentified future failures. (Note: Any unidentified future failures will be prioritised against identified works contained within the all faults register, meaning not all identified works will be completed within the 3 year funding programme.) This is an increase of $31,000 over the 2012-15 level to make allowance for the likely increase in costs from the tender of a new maintenance contract.

The Council will formulate a resealing policy for urban roads. This policy will provide guidance on the type of seal to be used whether it is asphalt or road chip weighing up the whole of life costs of each type of seal.

5.3.3.   Pavement Rehabilitation

Where Road Asset Maintenance Management data and local observation indicates that poor pavement structure is critical then generally this is renewed as a standalone project. A review in 2014 (A1192250) highlighted the following priorities for the 2015-18 period:

·      Quarantine Road (SH6 to Nayland Road);

·      Maitai Valley Road (4500-4900);

·      Wildman Avenue Turning Head;

·      Cable Bay Road (1950-2900).

5.3.4.   New Roads

It is unlikely that any new roads will be built by the Council. New roads in Nelson will come from new subdivisions and the Council will adopt these roads after the subdivision developer has installed them.

5.3.5.   Reseals

Refer section 4.2.4.

5.4.     Road Structures

The service level statement for road structures including bridges and retaining walls is “road structures are considered to be designed and maintained to provide safe access across the network”.

The last valuation of the roading network was undertaken in June 2014.

Table 5.7       Bridges Valuation

 

June 2012

June 2014

Quantity

 44

44

Replacement value

$ 26,414,919

$27,199,741

Depreciated replacement value

$ 17,241,787

$ 17,649,524

Annual depreciation

$ 280,607

$ 288,947

Table 5.8       Retaining Wall Valuation

 

June 2012

June 2014

Quantity

28,111 m2

30,852 m2

Replacement value

$ 44,850,330

$ 51,422,169

Depreciated replacement value

$ 29,735,112

$ 37,426,908

Annual depreciation

$ 658,467

$616,972

Structures on the road network are generally managed by undertaking regular inspections to identify a forward maintenance programme to address defects. New structures are also built to cater for growth. These are generally built by developers as part of new subdivisions.

Structures are classified as a roading asset where they provide support for roads.

 

Expenditure Trends (from 2012-2015)

·      Preventative retaining wall maintenance costs, approx $64,000.

·      Maintenance on structures approx $72,000/annum.

·      Depreciation approx $770,000/annum.

The Key Issues for Structures

·      Ownership of retaining walls.

·      Structures approaching the end of useful life.

·      Premature failure.

·      Seismic capacity for all but lifeline routes not well understood.

Strategies for Managing These Issues

·      Develop ownership guidelines and investigate as part of retaining wall condition survey (found assets).

·      Continually keep track of structure condition and maintain as required. Replacing or retrofitting structures as useful life diminishes.

5.4.1.   Asset Condition and Performance

The condition of both bridges and retaining walls is recorded in detailed inspection surveys every six years. Every two years those structures that are in poor condition or at risk then put on a two year inspection cycle.

The surveys were last surveyed in 2007 by Tonkin and Taylor. The survey rates each wall- and bridges general condition on a scale from 1-5 with 1 being of good general condition and 5 being of poor general condition. A risk assessment of the likelihood of failure and the expected life expectancy are also estimated. The last survey was undertaken by Tonkin and Taylor in 2007.

The average assessed remaining total asset life of the roading retaining walls is 39 years and those walls on cycleways/walkways is 34 years. Eight walls were identified in the survey as requiring replacement. The spread of remaining asset life for walls is shown in Figure 5.1.

Figure 5.1     Remaining Asset Life of Retaining Walls

The detailed survey of bridges are undertaken approximately every 6 years and was last undertaken over the 2010/2011 summer period by Aurecon. The survey report details specific defects found during the survey. It also provides a recommendation for maintenance work and a forward work priority programme. A seismic review was undertaken on six key structures which were identified in the previous report as likely to suffer significant damage in the event of a magnitude 7.5 earthquake. The details of the conditions recorded in the survey are contained in a Road Asset Maintenance Management database held with the Council.

The key structures have a remaining design life of between 25 and 61 years and four of the seven bridges were identified as requiring earthquake strengthening. It was found that 22 bridge structures required maintenance work valued at greater than $5,000.

Table 5.9       Road Structure Data Reliability Analysis

Data Attribute

Very Uncertain

Uncertain

Reliable

Highly reliable

Asset quantity

 

 

 

 

Asset age

 

 

 

 

Condition

 

 

 

 

Performance

 

 

 

 

5.4.2.   Maintenance Strategy

Repairs and maintenance of structures are identified through the survey inspection reports as detailed in Section 5.4.1 or routine inspections undertaken by the Contractor or Councils contract supervisors. Maintenance is therefore mostly reactionary to defects identified in surveys rather than preventative maintenance.

The current road maintenance contract (to September 2013, with an optional extension for a further 3 years) specifies the response times for different repair types, the roles of the Engineer and Contractor, performance requirements and the basis of payment.

5.4.3.   Renewal Strategy

Renewal of road structure assets will be implemented to maintain a level of service of an asset by intervening prior to either the end of the useful life of the asset, or the condition of the asset falling below an agreed level.

The renewals programme is developed using the recommendations of the bridge and retaining wall survey reports.

5.4.4.   New Structures/Capital Works

It is proposed that seismic strengthening of bridges on lifeline transport routes be funded to provide greater resilience in the event of emergencies. The high risk bridges proposed to be addressed in the next three years are:

Gibbs and Poleford Bridge - seismic strengthening, Security of these lifeline bridges to ensure access to city water supply pipeline up the Maitai Valley in case of earthquake, design and construction in one year under the Minor Improvement work category.

New structures will only be undertaken where new roads are required. New roads are most likely to be associated with new development so it will be expected that any structures required will be installed by the developer prior to the council adopting the roads and structures.

5.4.5.   Emergency Works

Structures are susceptible to damage during natural disasters, in particular flooding and earthquakes. The recent storm events in the Nelson region highlighted the risk that exists for the area. Failure of or damage to a bridge or retaining wall during one of these events would result in emergency works to initially make the asset useable and also to secure the long term future for the asset.

The Council can obtain emergency works funding and insurance for events. The Financial Assistance Rate rates for funding of emergency works has not been announced yet but Council will still need to provide partial emergency works funding. The Financial Assistance Rate funding is not always covered for replacement of damaged retaining walls, even if they are a Council asset. Only if the walls are supporting the road is there an opportunity to seek funding.

5.5.     Pedestrian Network

The service level statement for footpaths is “the footpaths network is considered to be suitable, accessible, safe and well maintained”.

The last valuation of the roading network was undertaken in June 2014.

Table 5.10     Footpaths Valuation

 

June 2012

June 2014

Quantity

494,845 m2

481,443 m2

Replacement value

$ 28,324,783

$ 30,043,243

Depreciated replacement value

$ 8,742,590

$ 9,406,454

Annual depreciation

$ 273,298

$ 337,466

Table 5.11     Walkways Valuation

 

June 2012

June 2014

Quantity

23,067 m2

23,067 m2

Replacement value

$ 3,669,888

$ 3,806,273

Depreciated replacement value

$ 2,619,867

$ 2,627,768

Annual depreciation

$ 38,129

$ 40,104

The footpath network is managed in three ways. Firstly an ongoing maintenance programme addresses footpath defects through either planned or responsive maintenance. Secondly footpaths are renewed based on a prioritised forward work programme (repairing those in the worst condition), and thirdly, new footpaths are built because of health and safety issues, accessibility requirements, or in response to public requests meeting certain engineering, environmental and community criteria. These new footpaths are service level improvements and not growth related. New footpaths are also built to cater for growth. These are generally built by developers as part of new subdivisions.

Walkways are classified as a roading asset where they connect roads, are on legal road and serve for the purpose of providing a route for pedestrians/cyclists with limited recreational value. There is a register of these which has been agreed with Parks and Community Facilities.


 

Expenditure Level (from 2012 to 2015)

·      Maintenance costs, approx $206,000/annum.

·      Renewals budget $550,000/annum.

·      Capital costs for new footpaths to improve the level of service vary from $150,000 to $1,000,000/annum depending on scheduled roading projects.

·      New/upgrade walkways $100,000/annum.

·      Capital cost for new walkways to improve the level of service $100,000/annum

·      Depreciation approx $280,000/annum.

The Key Issues for Footpaths

·      Demand for footpaths and walkways where previous development has occurred below the current standards.

·      Conflict at crossings between providing a smooth level surface for mobility scooters and a suitable vehicular access.

·      Demand for new and improved footpaths and walkways due to ageing population.

·      Demand for improved lighting of footpaths and walkways.

·      Demand for improved connectivity between footpaths, and safer road crossings, especially around schools and across the busy arterials.

·      The high cost of providing new footpaths on hillside and rural streets, and the compromises that are made should a lower standard be proposed (usually at the detriment of on-street parking, slower vehicle speeds and the perception of pedestrian safety.

·      Improvement in quality of footpath between the Central Business District and Tahunanui Beach.

5.5.1.   Asset Condition and Performance

Road Asset Maintenance Management records footpath and walkway condition assessments. The Council undertakes regular footpath condition assessments which inform the footpath renewal forward work programme. The most recent footpath condition assessment has been undertaken by L&M Price for the entire city in 2014. A summary of the data collected in this assessment is contained in Table 4.3 in section 4.2.1.

Table 5.12     Footway Data Reliability Analysis

Data Attribute

Very Certain

Uncertain

Reliable

Highly reliable

Asset quantity

 

 

 

 

Asset age

 

 

 

 

Condition

 

 

 

 

Performance

 

 

 

 

Pedestrian counts are undertaken every 6 months in 5 locations throughout the city and comparisons can be made with the 5 year comprehensive survey undertaken in 2010. Reporting of the pedestrian surveys is provided in the Regional Land Transport Programme and Regional Land Transport Strategy Annual report.

5.5.2.   Maintenance Strategy

Footpath and walkway repairs are identified through customer notification or routine inspections undertaken by the Contractor or Councils contract supervisors.

The current road maintenance contract (to September 2013, with an optional extension for a further 2 years) specifies the response times for different repair types, the roles of the Engineer and Contractor, performance requirements and the basis of payment.

Considerations which drive the maintenance works include:

·      Planned and unplanned work depending upon the urgency of the response required.

·      Footpath and kerb replacement required as a result of street tree roots.

5.5.3.   Renewal Strategy

The function of the renewal budget is to maintain a level of service of an asset by intervening prior to either the end of the useful life of the asset, or the condition of the asset falling below an agreed level.

The main driver for a renewals programme is Council’s responsibility, as the custodian of the footpath network to effectively maintain and manage the lifecycle of the network, on behalf of the ratepayers who own it, for the least cost over the useful life of that network. The renewals programme shown in Appendix N has been developed by network services staff using the criteria outlined below:

·      Road Asset Maintenance Management and area wide survey condition ratings - including an assessment of safety and risk-of-failure, in other words, a footpath condition-rating scale.

·      Use and location - Areas of high pedestrian use (for example main bus routes, commercial centres), and those with a high public profile will be one criterion for priority upgrade. Areas that fall into this category comprise commercial centres (including the Central Business District); areas around schools; major walkways and cycleways for example.

·      Under-grounding or other utility works - The ability to coordinate footpath upgrade works with under-grounding or other utility projects offers significant advantages. Mapping of forward programmes may result in advantages for cost and programming e.g. these include main street programmes, road renewals, large events such as Central Business District upgrades and other utilities work programmes.

·      Optimisation – alignment with other roading works to minimise inconvenience to the public (whole of street approach).

All renewal works aim to comply with the Land Development Manual 2010 footpath standards, although in some instances, such as hill side streets, or where crossings are steep, this is not always possible. Staff endeavour at all times to implement the objectives of the Land Development Manual when renewing footpaths.

The footpath renewals contract is included in the road maintenance contract.

5.5.4.   New Footpaths and Walkways

Since 2012, Council has taken a new direction on the planning of future new footpaths and signs and changing the focus to slowing traffic speeds and making the local roads safer for all users especially in the hillside areas where it is very costly to provide footpaths.

New footpaths and walkways will be constructed from a priority list of missing footpaths with an annual budget of $200,000. The new footpath schedule can be found in Appendix M with the live priority matrix in document A777631.

5.6.     Cycle Network

The service level statement for the cycle network is “the cycle network is considered to be suitable, accessible, safe and well maintained”.

There are approximately 20 kilometre of off-road cycleways and 34 kilometres of on-road cycleways. Part of this network is integrated with footpaths and carriageways.

‘Cycle lanes’ is the term used to describe dedicated routes on roads. Shared walk/cycleways describe off road routes separated from road traffic by either a kerb or verge, either on road reserve or other Council or NZ Transport Agency owned land that is identified as a shared utility in the Parking and Vehicle Control Bylaw schedules. Generally shared walk/cycle paths are 3 metres wide. Off-road cycleways are generally defined as those outside of the road reserve and are addressed in the Parks and Reserves Asset Management Plan.

The last valuation of the roading network was undertaken in June 2014.

Table 5.13     Cycleways Valuation

 

June 2012

June 2014

Quantity

65,707 m2

71,192 m2

Replacement value

$ 3,735,966

$ 4,682,764

Depreciated replacement value

$ 3,371,443

$ 4,000,467

Annual depreciation

$ 46,296

$ 71,973

The cycleway network is managed in a similar way as the pedestrian network, identified in 5.5 above.

Expenditure Level (from 2012 to 2015)

·      Maintenance costs approx $65,000/annum since the completion of the Atawhai cycleway.

·      Budgeted capital costs for new cycleways to improve the level of service vary with significant expenditure over the last three years implementing the walk cycle schools package of works. This package has received NZ Transport Agency co-investment from Regional Funds.

·      The key issues for shared walk/cycle paths and on road cycle lanes are:

·      Demand to extend and improve cycle linkages (the current network with planned improvements is shown in Figure 5.2 below.

·      Conflict at crossings between cyclists and vehicles and on shared paths between cyclists, pedestrians and dogs.

·      Demand for new and wider shared paths and cycleways.

·      Demand for improved lighting and markings on shared paths and cycleways.

·      Broken glass on the shared paths and cycle lanes.

·      Removal of cycle facilities during roadworks.


 

Figure 5.2     Existing and Proposed Cycle Network


 

5.6.1.   Asset Condition and Performance

Road Asset Maintenance Management records shared walk cycleways, although as all the paths are relatively young (less than 13 years) there has been no condition assessments carried out to date. Over the last couple of years it is evident that some older cycleways require some renewal, specifically the coastal route and the airport bridge. The condition of the on road cycle lanes is managed with the carriageway infrastructure and line markings and are considered in section 4.2.3.

Table 5.14     Cycle Infrastructure Data Reliability Analysis

Data Attribute

Very Uncertain

Uncertain

Reliable

Highly reliable

Asset quantity

 

 

 

 

Asset age

 

 

 

 

Condition

 

 

 

 

Performance

 

 

 

 

Cycle counts are undertaken every 6 months in 5 locations throughout the city and comparisons can be made with the 5 year comprehensive survey undertaken in 2010. Reporting on the cycle surveys are provided in the Regional Land Transport Plan (RLTP) and RLTP Annual Report.

5.6.2.   Maintenance Strategy

Cycle path repairs and glass removal are identified through customer notification or routine inspections undertaken by the Contractor or Councils contract supervisors.

Cycleways routine maintenance provides for the normal care and attention of the asset to maintain its integrity and to be fit for purpose. It is a combination of planned maintenance such as sweeping and reactive maintenance such as patching and repairing cycleways when complaints by the public are received.

The current road maintenance contract (to September 2013, with an optional extension for a further three years) specifies the response times for different repair types.

Considerations which drive the maintenance works include:

·      Planned and unplanned work depending upon the urgency of the response required.

·      Scheduled improvements planned works.

Cycle network maintenance costs have historically been $65,000/annum (maintenance - $35k, sweeping - $15k and Atawhai shared path $15k). However the network has just been extended significantly by the R funding walk, cycle schoolpackage (6.1km shared path) in the 2012-15 period with a corresponding increase in maintenance required. Cycle network maintenance of $80,000 is now necessary to maintain the level of service.

5.6.3.   Renewal Strategy

Renewal expenditure is major work, which does not increase the assets’ design capacity but restores, rehabilitates, replaces or renews an existing asset to its original capacity. Cycleways renewal is undertaken when all or part of a cycleway has reached the end of its economic life. The required level of replacement/rehabilitation will depend on age, condition, the level of ongoing maintenance and useful lives of the materials used.

Renewals of the following are programmed in the next three years:

·      Airport Bridge;

·      1.65km of the coastal path.

5.6.4.   New Shared Walk / Cycleways and Cycle Lanes

A package of walking and cycling projects ‘R’ is included. An overview of these projects is identified in the Regional Land Transport Plan and further detail is provided in Appendix K under the walk/cycle package.

5.7.     Public Transport

Nelson currently operates two public transport services. They include;

The NBus including The Late Late Bus[3] (subsidised by Council and NZ Transport Agency);

The Total Mobility scheme – door to door passenger service for the mobility impaired (subsidised by Council and NZ Transport Agency).

The Council also offers a Super Gold Card scheme for pensioners where they get to travel for free during off peak periods on the NBus. This scheme is fully funded by central government.

Figure 5.3     Zone Structure and Bus Routes

Transport Map Only.jpg

Contract Structure

The contract for the NBus and the Late Late Bus services was awarded in March 2012 to SBL Limited. The contract was for 6 years with two two-year extensions if performance indicators are met. In May 2013, the contract changed from a gross contract price to a net contract with all fare revenue retained by the operator. The net contract sum is $535,000 in 2013/14 and is adjusted for inflation each year. The current contract also allows for the contract price to be renegotiated if changes in service levels are required.


Key Issues for Public Transport

·      Accessibility to local services / facilities / places of employment;

·      Frequency of bus services, particularly between Nelson and Richmond;

·      Equitable funding from various sources (fares, rates parking revenue, NZ Transport Agency, Tasman District Council).

·      Ageing population resulting in increasing demand for the total mobility service.

Financial

In addition to funding from ratepayers and the NZ Transport Agency, a proportion of the costs are contributed by the user through fares. In 2012/13 63% of the cost of the NBus and Late Late Bus services was recovered through fares. The usual funding arrangement for public transport in New Zealand is that the net cost is funded in equal proportions by the local council(s) and the NZ Transport Agency. However when the improved NBus service was introduced in 2012, the NZ Transport Agency indicated that it would not be able to increase its co investment and the funding gap was met using a portion of Council’s parking revenue. Now that the service has proven itself, the NZ Transport Agency has confirmed indicated that Nelson is in a strong position to get matched co investment in the 2015-18 NLTP. The NZ Transport Agencies preference would be for this increase to fund a significant improvement to the service, so that Council’s contribution remains the same. This 2015-25 AMP has no contribution from the parking account to public transport with the local share now being fully funded from rates.

Table 5.15     Fares as at July 2014

5.7.1.   Improvement Strategy

The following priorities for public transport have been identified in the 2013 review of the NBus service[4] in order to increase patronage:

·      Lower fares to increase patronage and then review fare structure every two years.

·      Increase the frequency of the bus service on arterial routes between Nelson and Richmond and to encourage an increase in patronage.

·      Continue marketing and promotion of new, improved, or altered services.

·      Review the provision of bus stops and shelters and prioritise infrastructure improvements.

·      Conduct user and non-user surveys every 2 years and use feedback to improve services.

·      Construct additional infrastructure on hail and ride rates to increase visibility of service.

·      Improve coverage of bus service in Stoke.

In 2014 Council carried out a business case assessment in order to obtain additional funding from NZ Transport Agency to implement the improved coverage in Stoke and to inform the Regional Public Transport Plan. The outcomes of the business case will be determined by NZ Transport Agency during the RLTP moderation process.  The Business Case successfully obtained co-investment from NZ Transport Agency for increased bus coverage in Stoke.

The following priorities for total mobility have been identified:

·      Increase funding at 6% per annum for the 2015-2025 period to meet the demand caused by the ageing population for the service.

5.7.2.   Future Public Transport Study

A public transport review is planned to occur every five years with the next review scheduled in 2019/20.

The full scope of the review is yet to be established but it is likely this will entail assessing the suitability of the public transport network and whether changes should be made to bus routes and if new routes are required.

5.8.     Traffic Control and Equipment, Street Lighting, Signs and Markings

The service level statement for the transport assets in this section are:

·      Traffic signals are designed and maintained to optimise traffic flow in the roading network.

·      Street lighting is provided and maintained to enable safe and easy night driving on all urban streets and to outdoor public spaces were night time pedestrians movements dominate e.g. Central Business District areas.

·      Appropriate signage is maintained to enable safe and efficient way finding across the transport network.

·      Road markings are maintained to provide clear delineation and direction for roads, parking, and cycle and bus lanes at all times.

The last valuation of the roading network was undertaken in June 2014.

Table 5.16     Street Signs Valuation

 

June 2012

June 2014

Quantity

 2,882

2,882

Replacement value

$ 1,590,864

$ 1,809,896

Depreciated replacement value

$ 795,432

$ 904,948

Annual depreciation

$ 106,058

$ 120,660

 


 

Table 5.17     Line Marking Valuation

 

June 2012

June 2014

Quantity

 

 

Replacement value

$ 120,000

$ 120,000

Depreciated replacement value

$ 120,000

$ 120,000

Annual depreciation

$120,000

$120,000

Table 5.18     Streetlights Valuation

 

June 2012

June 2014

Quantity

4,291

4,433

Replacement value

$ 20,237,614

$ 34,648,552

Depreciated replacement value

$ 10,685,803

$ 17,226,538

Annual depreciation

$ 556,932

$ 796,011

Table 5.19     Traffic Signals Valuation

 

June 2012

June 2014

Quantity

12

13

Replacement value

$ 1,858,069

$ 3,513,748

Depreciated replacement value

$ 821,884

$ 1,959,584

Annual depreciation

$91,115

$ 139,368

These roading assets are an important activity for the Council to manage as they provide important information and direction to all road users. The Council seeks to ensure that this is done so that the transport network is safe, legible and efficient.

Expenditure Trends (from 2012 to 2015)

·      Maintenance costs of signs, markings and street lighting and furniture, approx $930,000/annum.

·      Renewal costs of signs, markings, street lighting and furniture and traffic signals, approx $130,000/annum.

·      Operation and maintenance of traffic signals, approx $78,000/annum.

·      Depreciation approx $930,000/annum.

The Key Issues

·      Lack of road sign asset knowledge.

·      Street lighting poles that are in a poor condition and luminaries that have reached the end of their serviceable life.

Strategies for Managing These Issues

·      Develop inventory for street signs.

·      Use pole testing results to target replacement of at risk poles.

·      Replace poor performing luminaries with LED’s.

5.8.1.   Asset Condition and Performance

The Council requires a sign inventory to be undertaken so that the location and condition of all signs and supports are recorded into Road Asset Maintenance Management. It is estimated that this will cost $50,000.

The traffic signal asset is in a very good condition with recent controller and LED upgrades.

Sign condition is monitored by the road maintenance contractor and signs that fall below standard are programmed to be replaced.

There are still a considerable number of Mercury Vapour/Fluorescent lights all over the city. These should be replaced wherever possible with LED technology to improve light output and reduce energy consumption. Lighting poles are in the process of being inspected for structural integrity. Refer to document A1224555

5.8.2.   Renewal Strategy

There are no planned renewals for the traffic signal asset in the first three years.

The streetlight renewal budget of $200,000/annum will be used to improve street lighting, focussing on:

·      Safety of all users;

·      Renewal of aged mercury vapour and fluorescent luminaries;

·      Improving the energy efficiency of the streetlight network by installing LED’s;

·      Replacing rusty pole bases;

·      Reducing light pollution with the Dark Sky policy.

The Council has a “Dark Sky” policy when it comes to new or improved street lighting. This policy has been adopted to limit the amount of light pollution emitted directly up from street lights.

5.8.3.   New Assets

There are no new traffic signals planned in the next five years.

Along with street lighting renewal to improve lighting levels there will be new street lighting also incorporated into the following upgrade projects.

·      Rocks Road walking and cycling;

·      Milton, and Halifax upgrades.

5.9.     Safety

The service level statement for safety is:

“To work towards a safe road system increasingly free of death and serious injury.”

The following objectives relate to the NZ Transport Agency work category (432) on road safety in particular promotion, education and advertising. This work category provides for the development and implementation of activities that address the safe use of the land transport network.


 

Objectives

·      Advancing the priorities and initiatives identified in the Safer Journeys Strategy and its action plan (www.saferjourneys.govt.nz).

·      Achieving safer outcomes by working with communities to identify and deliver local land transport safety issues.

·      Developing and motivating national, regional and local land transport safety partnerships to ensure an integrated approach to safety outcomes.

Strategic Fit To the Nelson Region

The 2014 NZ Transport Agency Communities at Risk Register;

·      shows Nelson City to have low individual risk for cyclists;

·      shows older drivers in Nelson are at below average individual risk for a crash;

·      shows Nelson to have medium individual risk for pedestrians;

·      shows young drivers to be at low individual risk in Nelson City but are a high priority nationally;

·      Safer Speeds is also identified as a high priority in the Safer Journeys strategy.

Current Road Safety Performance

The analysis in Section 4.4 indicates that road safety has improved markedly from the period covered by the previous AMP. The target for road safety performance has been changed to move away from statistics that compare Nelson with the peer group average and instead towards a fixed baseline. This will allow a direct measure of the improvement in Nelson alone without a particularly good or bad year in the other centres influencing whether the targets have been met locally.

In order to achieve the gains in road safety that have been realised in the last three to five years the Council has run a variety of initiatives and campaigns that are summarised by transport mode below. In the 2012-2015 period $147,000 per annum was budgeted.

Cycling

The initiatives for improving cycle safety are Nelson’s RIDE ON Strategy, 0800 CYCLECRASH and Be Bright on a Bike. Key outcomes are to improve community cycle skills, encourage more cycle use, drawing attention to cycle presence on the road and a reduction in crashes involving cyclists.

Motorcycling

The initiative for improving motorcycle safety is the “Top of the South Motorcycle Safety Programme. Key parts to the strategy are motorcycle training courses together with information publicised on licence requirements and safety gear as two closest neighbours Tasman and Marlborough District Council have medium casualty risk rating for motorcycles.

Older Drivers

The initiatives for improving safety with Nelson’s older drivers are the Staying Safe, Car Fit and Mobility Scooter Training schemes. Key parts to achieve this are classroom based learning on staying safe and one to one mobility scooter training and support. A Car Fit package helps older drivers recognise what their vehicle’s safety features are and assists in correctly adjusting them to their personal needs.


 

Speeds and Driving to the Conditions

The initiatives for reducing driver speeds will focus on driver education and awareness in particular to driving within residential streets. It is hoped that a greater ownership of streets and public space by residents can be achieved by investigation and implementation of a community development model to reduce speeds in residential streets.

Walking

The initiatives for improving safety while walking focuses on young pedestrians and parents of child pedestrians. The work will involve walking school buses and Feet First and Walk to School promotions. Other events and activities designed to promote and encourage using active transport as a mode of travel to and from school will be utilised.

Younger Drivers

The initiatives for improving safety amongst young drivers are Rotary Young Driver Awareness (RYDA), Students Against Dangerous Driving (SADD) and the training of teachers in delivering road safety across the school curriculum. Key outcomes are to provide increased awareness in the target group of young drivers and their parents about elevated risk levels and steps that can be taken to reduce that risk.

Road Safety Action Plan

The Council has a joint road safety action plan with the Tasman District Council. This plan is a critical component in the delivery of a Road Safety programme across the Nelson/Tasman district. The two councils through resolution have agreed to a cluster arrangement for the purpose of delivering a road safety programme across their respective districts. For management purposes a Joint Road Safety Action Plan Committee has been appointed with representatives from key stakeholder groups.

The Road Safety Action Plan Committee is tasked with the management of all road safety activities. To enable this, a supporting structure has been developed which includes:

·      Three times a year council led and chaired Road Safety Action meetings, which include formal agendas and stakeholder reporting lines and minutes.

·      Operational meetings for professional key staff as and when required with meeting recordings made.

·      Planning processes and operational calendars and works schedules as attached.

The goal of the plan is to contribute to the Governments Safer Journey initiatives which aim to reduce road user crash risks and consequences. The plan acknowledges the Governments Safer Journeys initiatives and that even a responsible driver may make mistakes on our local roads. It is the goal of this plan to better manage our road networks, our vehicles, our users and crash forces to deliver a safe system across the Nelson/Tasman sub region.

To achieve the goals of the plan the Road Safety Action Plan aims to:

·      Fully understand crash risk on our road networks.

·      Redesign our high risk road infrastructures to be predictable, forgiving of mistakes and self explaining.

·      Manage our local roads to ensure that the travel speeds suit the function and safety level for the road environment and conditions.

·      Manage local vehicles to ensure they are safe and road worthy.

·      Ensure that all road users are skilled, competent, alert, unimpaired, comply with the road rules and take steps to improve their safety.

The improvements in road safety that have resulted in all of Nelson previously medium to high risk user groups dropping to low risk on the High Risk Communities Register have been as a result, in part to the programmes and initiatives detailed above. In order to maintain this safety improvement and make further gains Council needs to continue to be proactive with road safety campaigns and initiatives that include speed reduction measures.

5.10.   Parking

The service level statement for parking is “Parking is easy to use, and is rationed fairly and equitably”.

The last valuation of the roading network was undertaken in June 2014.

Table 5.20     Car Parking Valuation

 

June 2012

June 2014

Quantity

36,207m2

33,892 m2

Replacement value

$ 2,600,849

$ 2,777,088

Depreciated replacement value

$ 831,756

$ 660,919

Annual depreciation

$ 32,985

$ 32,280

Council has eight car parks, two in Stoke (237 parks) and six in the Central Business District (871 parks). The number of spaces in each park is identified in Table 5.25.

Table 5.21     Car Parking Spaces in Nelson and Stoke

ID

Location

Number of spaces

Parking Type

1

Strawbridge Square (Stoke)

180

time restricted

2

Putaitai Street/Fire Station Car Park (Stoke)

57

time restricted

3

Tahaki Street (Nelson Library)

59

time restricted

4

Millers Acre

92

metered

5

Wakatu Square

173

metered

6

Buxton Square

229

metered

7

Montgomery Square

268

metered

8

Betts Car Park

52

leased to individual users

9

Bridge Street Car Park

 

leased to individual users

 

Total

1108

 

 


 

Table 5.22     Car Parking Data Reliability Analysis

Data Attribute

Very Uncertain

Uncertain

Reliable

Highly reliable

Asset quantity

 

 

 

 

Asset age

 

 

 

 

Condition

 

 

 

 

Performance

 

 

 

 

Parking and public transport are intrinsically linked. Changes to the parking charge may affect the use of public transport. Free parking would discourage use of public transport, requiring increased enforcement or increases in the commercial rate to ensure funds were available to operate, maintain and improve the Central Business District.

In Nelson there is a lack of long term parking spaces within the Central Business District and the Council does not plan to add any more long term parking capacity. Along with parking charge rates the Council wish to maintain a central city parking regime that is incentivised for people to use public transport and active modes.

Expenditure Trends (from 2012 to 2015)

·      Carpark maintenance costs approx $266,000/annum;

·      Carpark lease costs $167,600/annum;

·      Carpark rate costs $324,000/annum.

The Key Issues for Car Parking

·      Maximum Parking occupancy exceeding the desired level of service at 85% in the surveyed first week of December in the Central Business District core.

·      Perception of heavy handed enforcement.

·      Long-stay commuters occupy a significant proportion of the short stay inner city parking.

·      Condition monitoring and rating, maintenance and replacement of signage and marking affect the effectiveness of parking restriction enforcement.

·      Frequent requests for no-stopping lines.

·      Payment methods out of date with current technologies.

Strategies for Managing These Issues

·      Optimise time limits to reflect car parking demand.

·      Replace parking meters in 2017/18 with a more flexible payment facility.

·      Trial different parking regimes in order to determine best fit for the Nelson CBD users.

·     

5.10.1. Asset Condition and Performance

Off-street car parks have been incorporated and included into the Road Asset Maintenance Management database.

Car parking meters were renewed in 2006 to ensure compliance with the new currency and will be coming to their end of life in 2017/18. The maintenance costs for the meters have not increased significantly as their end of life has approached however the need to introduce more convenient ways to pay such using credit and debit cards including Pay Wave will drive the replacement date.


 

Summary of 2008 and 2012 Car Parking Data Collection Reports

·      815 parks are available in the four Central Business District squares – approximately 25% used by all day commuters;

·      There is enough short-stay capacity if the long-stayers stopped using the short stay spaces;

·      Short stay parking should be of sufficient capacity, carefully costed, well-located and accessible;

·      Long Stay parking should not compete with short stay capacity, and should align with the wider transport policy.

Potential Methods to Manage Parking Square Enforcement

·      Continue existing pay and display system (note: tickets can only be issued if money is paid);

·      Install barrier arms and new meters (cost estimate $300,000 per square) for a “pay as you exit system”;

·      Change bylaw to more clearly limit the length of time allowed in a parking square per day.

Parking Revenue

·      In 2012/13 $428k was received from on-street meters and $712k from off-street meters. It ahs been estimated that under the current one hour free then $1.50/hr that the total revenue from the meters will be in the order of $460K pa.

·      Infringement recoveries ($838k received in 2012/13) fund parking regulation enforcement.

Implementation Plan for Parking

·      Renew pay and display meters with units that enable payment by credit card and integration with smart phone apps to extend the stay, $470,000 in 2017/18 and $470,000 in 2018/19.

·      Install signage directing users to the parking squares from the CBD ring route, $200,000 in 2015/16 and $100,000 in 2016/17.

·      Reconfigure the traffic signals on Main Road Stoke at the Putaitai intersection to allow the right turn out to prevent unnecessary movements through Strawbridge Square carpark, $40,000 in 2015/16.

·      Modify the tree planters in Strawbridge Square carpark to minimse damage, $30,000 in 2015/16.

·      Allocate a small number of campervan and motor home spaces within the CBD, $20,000 in 2016/17.

 


6.       Valuation

Roading Asset Valuation

 

 

 

 

Asset Category

June 2014

Quantity

Units

RV ($)

DRV ($)

Depr ($)

Pavement Layers

Formation

2,943,138

m3

105,952,978

105,952,978

 

Sub-base

385,000

m3

40,810,048

40,810,048

 

Basecourse

2,274,622

m2

33,429,410

15,777,764

364,686

Surfacing

2,140,850

m2

26,649,423

14,612,127

1,113,452

Drainage

Intakes

57

units

287,215

213,791

3,590

Outfalls

37

units

141,229

91,719

2,026

Sumps

6,185

units

14,445,169

9,548,638

160,449

Stormwater pipes

74,456

m

31,254,587

18,344,137

365,090

Culverts

3,578

m

3,070,782

1,492,914

34,714

Kerb and Channel

339,426

m

21,527,541

10,991,856

282,476

Kerb Only

13,480

m

899,166

569,484

12,920

Dished Channels

26,751

m

2,360,180

334,096

40,377

Regulatory

Signs

2,882

units

1,809,896

904,948

120,660

Electronic Signs

30

units

262,920

237,018

21,910

Posts

1,758

units

153,913

76,956

10,261

Handrails/Sight Rails

6,443

m

836,134

418,067

27,871

Guardrails

1,219

m

915,311

457,655

18,306

Edge Marker Posts

441

units

9,993

4,997

1,999

Speed Tables

36

units

936,000

633,100

23,400

Road Humps

20

units

29,640

14,820

1,186

Raised Pavement Markers

1,531

units

26,808

13,404

2,234

Road Markings

 

 

120,000

120,000

 

Traffic Signals

 

 

3,513,748

1,959,584

139,368

Streetlights

Streetlights

4,433

units

34,648,552

17,226,538

796,011

Structures

Bridges

44

units

27,199,741

17,649,524

288,947

Retaining Walls

30,852

m2

51,422,169

37,426,908

616,972

Fords

3

units

84,781

57,798

848

Footbridges

28

units

1,250,597

862,480

12,506

Other

Land for Legal Road

 

 

256,096,995

256,096,995

 

Footpaths

481,443

m2

30,043,243

9,406,454

337,466

Walkways

23,067

m2

3,806,273

2,627,768

40,104

Cycleways

71,192

m2

4,682,764

4,000,467

71,973

Carparks

33,892

m2

2,777,088

660,919

32,280

CCTV

18

units

101,250

67,693

20,250

Misc Street Furniture

635

 

1,508,363

657,563

53,682

TOTAL

 

 

 

703,063,905

570,321,205

5,018,012


7.       Financial Forecasts and Development Contributions

Expenditure on assets can be categorised into the following main areas which are discussed below.

Operations and Maintenance

Operation and Maintenance expenditure is required for the day-to-day operation of the network whilst maintaining the current level of service.

Maintenance costs are generally subdivided into:

·      Routine – ongoing day to day maintenance;

·      Planned – Non day to day maintenance that is planned in advance;

·      Reactive – Maintenance that is unexpected.

Renewals

Renewal expenditure includes rehabilitation and replacement of assets to restore an asset to its original level of service.

Capital

Capital works involves the creation of new assets, or works, which upgrade or improve an existing asset beyond its current capacity or performance.

The forecasted subsidised annual expenditure for the next three years is shown in
Table 7.1.

Asset Management Assumptions

·      The forecast are based on current NZ Transport Agency funding thresholds and co-investment levels.

·      Maintenance and operations allocations are largely based on maintaining current level of service.

·      Do not allow for fuel prices or inflation escalation.

·      Staff resources will be available to commission all the actions required.

Table 7.1       Forecasted Subsidised Annual Expenditure

Activity Class

2015/16

2016/17

2017/18

Transport planning

$45,000

$70,000

$105,000

Road safety promotion

$90,000

$90,000

$90,000

Walking and cycling facilities

$280,000

$605,100

$570,000

Public transport services

$1,293,300

$1,281,800

$1,332,200

Public transport infrastructure

$69,300

$131,900

$36,000

Maintenance and operation of local roads

$3,135,900

$3,148,600

$3,161,500

Renewal of local roads

$2,691,800

$2,394,800

$2,538,100

New & improved infrastructure for local roads

$650,000

$650,000

$700,000

Total Forecasted Expenditure

$8,255,300

$8,372,200

$8,532,800


Other Significant Sources of Council Funding

·      Rates – in addition to funding from rate payers.  Inner city and Stoke CBD ratepayers pay a higher differential to cover provision of special services in the CBD’s.

·      Parking charges and enforcement.

·      Property rents and land leases.

·      Development Contributions – see below.

·      Borrowing – the Council raises loans to fund capital works only.

·      Depreciation – the Council depreciates its assets according to the replacement value method in order to fund renewal projects and repay Council debt.

Development Contribution

In addressing actual and potential adverse effects from Developments, the Council may seek financial contributions.

This will go towards the necessary land and works to construct, widen or upgrade any new or existing road, where:

·      roads are not available; or

·      existing roads are of inadequate width or construction to cater for increase usage caused by the subdivision or development; or

·      alterations or works to existing roads are required for traffic safety or efficiency as a consequence of the subdivision or development.

Furthermore, a financial contribution may be sought when the full number of on-site parking spaces is not provided as per the Resource Management Plan.

The LTP shows a programme of expected works for the ten years to 2025. This includes yearly financial forecasts of income and expenditure on transport activity operations and renewals and new capital expenditure. The LTP is included in Appendix L. Please note that these figures in this AMP are based on 2015 estimates and do not include inflation. The LTP figures differ beyond year 1 as they do include an allowance for inflation.

 


8.       Risk management

Background

Risk management is the systematic application of management policies and procedures to identify, analysis, evaluate, treat and monitor risk so that injury to people, damage to the environment, financial loss, disruption to infrastructural assets and services and legal obligation failures are controlled and mitigated as far as practicable.

Analysis of Risks

Council’s risk management framework is consistent with the joint Australian New Zealand Standard (AS/NZ IS4360:2004), to ensure that risks are managed on a consistent basis.

Risk, likelihood and consequence are defined as:

·      Risk is a function of the likelihood and consequence of an event occurring;

·      Likelihood is the probability or frequency of an event occurring;

·      Consequence is the outcome of an event including a loss, injury, disadvantage or gain.

For each event the likelihood score (Table 8.1) is multiplied by the consequence score (Table 8.2) for each area of impact. These multiples are then totalled to produce the risk priority rating for the event (Table 8.3), which provides an assessment of the level of risk associated with the event.

Table 8.1       Likelihood Ratings (Semi Qualitative Measure)

Rating

Description

Score

A

Almost Certain

Likely to occur frequently, i.e. several times a year.

0.9

B

Likely

Likely to occur more than once during the life of the project.

0.7

C

Moderate

Likely to occur during the life of the project.

0.4

D

Unlikely

Might occur once in 100 years.

0.2

E

Rare

Might occur once in 100+ years.

0.01

Table 8.2       Semi-Quantitative Measures of Consequence and Areas of Impact

Areas of Impact

Consequence

Negligible (10)

Minor (30)

Moderate (50)

Major (70)

Catastrophic (100)

Health and Safety

Minor injury possible.

Serious injury to one person.

Serious injury to multiple members of staff, contractors or public.

Single fatality of staff, contractor or public.

Multiple fatalities of staff, contractors or public.

Public Health

Temporary but non-serious health impacts.

Localised serious health impact on one person.

Localised serious health impact on more than 20 people.

Localised or widespread serious health impact on more than 100 people.

Localised or widespread serious health impact on more than 1,000 people.

Asset Performance

Asset failure impacting on one or more persons.

Asset failure impacting on more than four people

Asset failure impacting on more than 40 people

Asset failure impacting on more than 400 people

Asset failure impacting on more than 4000 people

Environment and Legal Compliance

Short term and Temporary impact requiring no remedial action.

Medium term environmental impact with negligible effects on environment or community.

Measurable environmental harm to an internationally or nationally significant site. Loss of public access or conservation value of the site.

Major environmental damage requiring long-term recovery investment. High profile legal challenge. Loss of public access or conservation value of a significant environment.

Permanent environmental damage to an internationally or nationally significant site. Large scale class action.

Historical or Cultural

Loss of important records about a site. Work required restoring them.

Unsympathetic development compromising the integrity of a registered historical, cultural or archaeological site.

Damage to a registered historical, cultural or archaeological site, but capable of restoration.

Loss or permanent damage to a registered historical, cultural or archaeological site.

Permanent loss of national icon.

Financial

Capital cost/ loss <$100k.

Capital cost/loss $100k - $500k.

Capital cost/loss $500k - $1million.

Capital cost/loss $1million- $5million.

Capital cost/loss > $5 million.

Customer Perception

Service Request.

Minor complaint.

Justifiable complaint / information request.

Ministerial questions /third party investigations.

Public or ministerial enquiry.

Table 8.3       Risk Priority Rating (Semi Quantitative)

Rating

Level of Risk

Score

> 200

Extreme

Awareness of the event to be highlighted to Council.

150 - 200

High

Risk treatment required. Risk to be eliminated or mitigated by 30 June 2009 to comply with Infrastructural Assets Business Plan.

100 - 150

Moderate

Risk treatment required.

0 - 100

Low

Manage by routine procedures.

The potential risks to Transport assets and services include:

·      Legislative;

·      Operational;

·      Organisational;

·      Public health and safety.

A simplified summary with proposed mitigation actions has been provided in Table 8.4 and Table 8.5.


Table 8.4       Business Risk Schedule

No.

Risk Event

Consequence or Outcome

Mitigation Strategies

Gross Risk

Action Plan

Residual Risk

1.

High level policies, procedures and controls

1.1

Resource Consent Conditions on road reserve not in accordance with Councils planning

Infrastructure developed through Resource Consent not in accordance with Land Development Manual, Policy or in alignment with councils future transport planning

All staff to ensure future RC conditions are non-binding on road reserve.

High

None

High

1.2

Inaccurate growth information

Inappropriate decision made about future infrastructure and services

Growth monitoring to be frequent and trends related to national/international data where possible

Mod

Monitoring regime now established

Low

1.3

Increasing standards

Public expectations of Transport safety, quality and environmental standards are increasing

 

Mod

The implications of increased levels of service, resulting in increased expenditure are fully recognised by Councillors

Low

2.

Financials

2.1

Poor financial forecasting

Reflects on Council as poor planning

Ensure assumption to project cost estimates are fully understood and refine estimates before each Annual Plan is developed

Mod

Ensure robust project management practices are followed

Mod

2.2

Desired NZ Transport Agency funding not obtained

Additional costs to Council or implementation of projects delayed, or maintenance deferred

Monitor NZ Transport Agency funding procedures and manuals and submit application in a timely manner

Mod

Ensure politicians are fully informed

Mod

2.3

Non-compliance with NZ Transport Agency funding agreement

Reduction or refund of NZ Transport Agency contributions

Annually report on compliance requirements

Mod

Implement measures to address any non-compliance

Low

3.0

Organisation Management

3.1

Failure to act on identified risk

Potential legal action against Council

 

Mod

Identified risk improvements implemented

Low

3.2

Lifelines plan not completed, updated or implemented

Lifeline asset failure reducing effectiveness of Nelson Tasman Emergency Management Group Plan 2005. Failure to comply with Civil Defence Emergency Management Act

 

High

Complete and update Lifelines implementation plan

Low

3.3

Asset Management Plan improvement plan not undertaken

Future forecasting not accurate. Decision making not optimised.

Annually report on improvement plan

Low

 

Low

4.0

Health and Safety

4.1

Safety Management Strategy and System for roads not implemented

Safety levels of service perceived not to have been achieved (although in reality works being undertaken but without the overarching structure)

 

Mod

Continue to monitor crash rates and set interventions via the TAMP

Mod

4.2

No agreed procedure with Police for road closure or traffic light failure event

Reduced safety leading to increased accident risk

Establish a Police traffic emergency procedures process as identified in OFI 6 of SMS

High

Establish a Police traffic emergency procedures process as identified in OFI 6 of SMS

Low

5.0

Transport Asset Management

5.1

Asset Management Plan not fully implemented

LTP, RLTP and Annual Plan not fully implemented resulting in recognition of poor Council performance and public dissatisfaction

Ensure robust project management practices are followed

High

Ensure robust project management practices are followed

High

5.2

Performance monitoring of levels of service not completed

Levels of service not met resulting in public dissatisfaction

Establish and implement monitoring programme

Low

Review every three years

Low

5.3

Non compliance with Land Development Manual for constructed/adopted assets

Substandard works requiring greater maintenance or earlier renewals

Project Scope and plan and site check procedures to be sufficiently resourced and implemented

High

Project Scope and plan and site check procedures to be sufficiently resourced and implemented

Mod

5.4

Unauthorised construction on road reserve

Public liability risk to Council. Risk of underground service damage

 

High

Establish and implement monitoring programme to ensure all approvals (including street opening notices and Traffic Management Plans) are obtained

Mod

5.5

Network modelling and condition assessments not applied

Capital and renewals works programme not optimised. Future forecasting not accurate

Road Asset Maintenance Management database and traffic models regularly updated and assessed

High

Road Asset Maintenance Management database and traffic models are regularly updated and assessed

Low

5.6

Lack of funding available to cover recovery cost triggered by a natural event

Additional rates burden

Increase insurance

High

Budget an increased internal contingency fund and investigate insurance costs to cover the unsubsidised portion of any emergency events

Low

5.7

Significant Natural Event

Resources reapportioned as necessary which might compromise Asset Management Plan implementation. Potential public claims from a lack of understanding of the risks

Delay implementation of this plan and reviewed modify as necessary when resources re-established

High

Preliminary risk maps of areas particular susceptible to flooding, liquefaction, tsunami, slips and fault lines to be mapped and published

Low

 


Table 8.5       Asset Risk Schedule

 

No.

Risk Event

Consequence or Outcome

Mitigation Strategies

Gross Risk

Action Plan

Residual Risk

1.0

Road pavements (including footpaths, cycleways and car parks)

1.1

Structural failure/blockage due to earthquake or landslide

Pavement failure and road closure

Maintenance contractor has 24 hour call out facility

Low

 

 

1.3

Vehicle crash damage

Road closure and chemical/load spill clean up. Pollution of watercourse

Maintenance contractor has 24 hour call out facility. Establish a pollution emergency response plan and make ready for implementation

Low

 

 

1.4

Inadequate maintenance

Road failure

Maintenance programme implemented

Low

 

 

1.5

Inadequate Traffic Management Plan for high volume roads

Reduced safety leading to increased crash risk

Update TMP guidelines as identified in OFI 8 of Safety Management System

Low

 

 

1.6

Inadequate on-road residential parking

Unsafe parking or installation of no-parking lines leading to public dissatisfaction

 

Mod

Consider when designing local road upgrades

Low

2.0

Road bridges (including footbridges and cycleway underpasses)

2.1

Structural failure due to earthquake

Catastrophic damage to bridge structure. Prolonged road closure

Arterial and Lifeline bridges designed and constructed to earthquake loading standards

High

Implement recommendations from seismic strengthening of lifeline bridges

Low

2.2

Flooding greater than bridge capacity

Damage to bridge structure

All bridges constructed to Q50 or Q15 standard (depending on location). Structural inspections every five years and maintenance inspections annually

Low

 

 

2.3

Flooding that closes cycleway underpasses

Inconvenience to cyclists and pedestrians

Suitable warning signage

Low

 

 

3.0

Road retaining walls

3.1

Structural failure due to earthquake or landslide

Catastrophic damage to several retaining walls. Road closure

Arterial and lifeline bridges designed and constructed to earthquake loading standards

Low

 

 

3.2

Inadequate design

Damage to retaining wall

Design to comply with Building Control Act requirements

Low

 

 

3.3

Inadequate maintenance

Retaining wall failure

Structural inspections every six years. Worst walls to occur every two years.

Low

 

 

4.0

Roading drainage (sumps, pipework and culverts)

4.1

Inadequate road drainage

Downstream flooding, pavement damage and increased maintenance costs

Upgrade road drainage where secondary flow paths are inadequate and historically private property flooding occurs

Low

 

 

4.2

Inadequate design or no kerb, channels and sumps

Downstream flooding, pavement damage increased maintenance costs

All road upgrades include drainage in accordance with Land Development Manual

Low

 

 

4.3

Inadequate maintenance

Downstream flooding, pavement damage, increased maintenance costs, increased risk of storm water pollution

Maintenance programme implemented

Low

 

 

5.0

Streetlights

5.1

Inadequate streetlights that do not comply with Land Development Manual

Non-compliance with level of service requirement

 

Mod

Implementation programme established

Low

5.2

Energy inefficient streetlights

Additional power consumption

 

Mod

Renewal programme established using LED

Low

5.3

Inadequate maintenance

Streetlights or streetlight column failure

Maintenance programme implemented

Low

 

 

6.0

Traffic Signals

6.1

Power failure or damage

Lights inoperable

 

Mod

Manage as uncontrolled intersection and install appropriate signs except at critical asset intersections in peak hour where Police appointed as Pointsmen until standby generators are installed.

Low

6.2

Inadequate maintenance

Lights inoperable or column failure

Maintenance programme implemented. Where signals are disconnected install temporary priority give way signs

Low

 

 

7.0

Safety Barriers

7.1

Inadequate barriers not complying with Land Development Manual

Non-compliance with SMS

 

Mod

Review safety barriers and develop upgrade and maintenance programme as identified in OFI 10 of SMS

Low

 


9.       Performance Monitoring and Improvement Plan

The primary focus of this improvement plan is to improve our asset management practices and process that will assist in achieving the least whole of life cost in maintaining the transport assets and bring improvements to the services provided.

 

Priority Areas

Improvement Action

Commentary

Timeline

Estimated cost

Data collection, analysis and monitoring

Improve data collection methodology of delay and travel time data.

Current sample is very small using the following car method. Potential to improve sample size by improving survey method.

2015

Within existing data collection budget

Improve data availability to enable more effective tracking of compliance with Levels of service.

A large amount of data is currently collected but is difficult to access and relies on a single person to analyse. Wider availability is essential to ensuring the data is monitored at least quarterly rather than every 1-3 years as currently is the case. GIS integration is needed.

2015-2016

Included in staff cost budgets

Improve data collection and reporting for Nbus punctuality, trips and passenger data.

Current data collected does not allow evaluation of demand at different points along routes. No punctuality data is collected or reported on with the supplier expected to self monitor. This is unlikely to be accepted by NZ Transport Agency as a performance monitoring method in the next contract. Integrated electronic monitoring system is due in 2016.

2016

$61,000 in total over the next three years

Increase coverage and frequency of pedestrian and cycle data collection.

Currently, comprehensive cycle and walking data is collected every five years. The availability and cost of other third party data sets (e.g. Strava) will be investigated to widen the data set. This will allow closer monitoring of changes in use of these transport modes.

2017

Unknown (Further investigation needed)

Develop parking demand model based on meter data.

Comprehensive parking demand data is collected manually every 4-5 years on average. In order to have a more 'live' data set data the meters can be used to give an indication of trends. This will still need to be validated using the manually collected data. This will not be possible should Council choose to remove the charges for parking.

2016

Included in staff cost budgets

Reduce reliance on RAMM for strategic asset management other than maintenance and renewals

The current focus of RAMM is not on what isn't there or where levels of service are lacking but instead on managing what we already have. Improved in-house GIS development is needed to allow a higher level of data customisation than is available through RAMM.

2017-2018

Included in staff cost budgets

Programming

Develop polices to encourage officers to reject/accept potential projects

Currently, a large number of potential projects make it to the network deficiencies lists that are unlikely to ever be considered any further for investigation or construction. There will be an increased focus on dealing with these immediately and informing the party that raised the issue that the particular project will not be proceeding any further.

2015

Included in staff cost budgets

Investigate pavement condition testing and analysis regime

Current practice is to be reactive rather than predicting when failures are likely to occur in road pavement structures. A testing programme to allow prioritisation prior to failure will be investigated in the next three years and recommended in the next AMP.

2015-2018

Included in staff cost budgets

Develop expertise in-house for benefit/cost analysis of pavement maintenance versus rehabilitation

This work is currently contracted out. Council holds all of the available data. Performing this work in-house will allow a higher level of flexibility in when and how often it is used in evaluating the value for money of maintenance works.

2018

Included in staff cost budgets

Asset Strategies

Develop strategy for planning for sea level rise

Sea level rise is expected to result in inundation of the current level of the key coastal arterials around 2050. Early planning is necessary to understand impacts.

2017-2018

Included in staff cost budgets

Redefine Nelson road hierarchy to align with NZ Transport Agency One Network Road Classification

NZ Transport Agency have finalised the One Network Road Classification (ONRC) that they are expecting RCAs to implement in the next 1-2 years. This classification will directly influence the levels of funding that NCC receive from NZ Transport Agency.

2015-2016

$50,000

Develop Council Policy

Private Access on Road Reserve;

Land slips on and above Road Reserves;

Speed complaints procedure;

Speed Hump Policy;

Signage Policy;

Power and Telecom Undergrounding;

Road Reserve maintenance limitations;

Fatal Accident Site Marking;

Resident Parking Zones.

2018

Included in staff cost budgets


Appendix A           Relevant transport legislation

The overall framework for planning, funding and managing the land transport system includes the following Acts, Regulations and Rules. Bills and Rules under development have been provided as they are likely to become legislation in the short term:

Resource Management Amendment Act (2003)

·      Local Government Act 1974, Local Government Act 2002;

·      Land Transport Act 1998, Land Transport Management Act 2003, Land Transport Management Amendment Act 2008, Land Transport Management Amendment Act 2013, Land Transport (Enforcement Powers) Amendment Act 2009, Land Transport Amendment Act 2009, Land Transport (Road Safety and other matters) Amendments Act 2011, Land Transport (Road Safety and other Matters) Amendment Act 2011, Government Roading powers Act 1989;

·      Resource Management Act 1991, Resource Management (simplifying and streamlining) Amendment Act 2009, Resource Management Amendment Act 2013, Building Act 2004, Building Amendment Act 2012, Building Amendment Act 2013, Health Act 1956;

·      Requirements of the Auditor General (refer Appendix J for improvement measures specific to the Transport Activity).

Bills

·      Local Government Act 2002 Amendment Bill (No.3).

Regulations

·      Heavy Motor Vehicle Regulations 1974;

·      Land Transport (Infringement and Reminder Notices) Regulations 1998 and 2012, Land Transport (Offences and Penalties) Regulations 1999, Land Transport (Ordering a Vehicle off the Road) Notice 1999 Land Transport (Requirements for Storage and Towage of Impounded Vehicles) Regulations 1999;

·      Land Transport (Storage and Towage fees for Impounded Vehicles) Regulations 1999, Transport Services Licensing Regulations 1989, Traffic Regulations 1976.

All Land Transport Rules, including

·      Operator Licensing 2007, Passenger Service Vehicles 1999, Road User Rule 2004, Setting of Speed Limits 2003, Traffic Control Devices 2004, Vehicle Dimensions and Mass 2002, Vehicle Lighting, Driver Licensing.

Bylaws

·      Parking and Vehicle Control Bylaw 207 (2011) and 2012 Amendment;

·      Speed Limits Bylaw 210 (2011) and associated Amendment 1 (2013).

 


Appendix B           Nelson’s Strategies and Policies

NELSON CITY COUNCIL LONG TERM PLAN

The last Long Term Council Community Plan was adopted in July 2012. It is a requirement of the Local Government Act 2002 to have such a plan to manage the Council’s activities and budgeting. Details in the plan forms the basis for the Council’s annual planning process. The plan must have a focus on social, cultural, economic and environmental outcomes. The next LTP 2015 -2025 will be adopted by Council in June 2015.

NELSON REGIONAL POLICY STATEMENT 1997

This document is at the top of the hierarchy of resource management considerations. It is prepared under the Resource Management Act and has statutory force.

Its purpose is to identify regional issues in terms of natural and physical resources and to outline objectives, policies and methods to achieve integrated management of the natural and physical resources of the whole region, including cross-boundary issues with other regions.

Other plans prepared under the Resource Management Act must now “give effect” to the provisions of the relevant regional policy statement for a region or district (changes to the Resource Management Act in 2005 have increased the importance of the Regional Policy Statement).

Nelson’s Regional Policy Statement was made operative in 1997.

Amongst the regional cross-boundary issues identified are:

·      “consistent management of transport nodes (including the port and airport), their adverse effects and equality of access (Nelson City/Tasman District)”; and

·      “a consistent approach to roading (Marlborough District/Nelson City/Tasman District).”

Key Chapters of the Regional Policy Statement in relation to the arterial study are Chapter 8, The Coast; and Chapter 14, Infrastructure. In general terms, Chapter 6, Development and Hazards, anticipates an increasingly compact urban form for the city, for efficiency reasons but also to protect and retain the rural setting of the city and to avoid natural hazards which are perceived as significant in areas adjacent to urban areas in the future (including climate change and sea level rise).

NELSON RESOURCE MANAGEMENT PLAN

This document is an integrated district and regional plan for the management of all the region’s natural and physical resources under the Resource Management Act (with the exception of air quality, for which there is a separate regional plan). The Plan was made operative in 2004 and has full statutory weight.

While much of the Plan and its policy framework is organised to apply to individual zones (e.g. residential, commercial, industrial) there is a set of District wide objectives and policies which apply across the whole region. Amongst them is a significant section on land transport, DO10.

REGIONAL LAND TRANSPORT PLAN 2015-2025

RLTPs are six-year documents with a ten year horizon that provide strategic context and direction for each regional programme. Key considerations include:

·      developing a significance policy to prioritise significant activities;

·      developing the front end strategic case using business case approach principles;

·      having a programme of activities, not just projects, with clear linkages between all activities and agreed outcomes, e.g. relationship between investing in different modes and activities funded outside the National Land Transport Fund;

·      setting out land transport objectives, policies and measures for at least 10 financial years;

·      considering the infrastructure implications and/or public transport service improvements that are needed to support growth areas;

·      considering the feasibility and affordability of alternative regional land transport objectives;

·      identifying performance measures that will be used to monitor activities.

The Regional Land Transport Plan is under development at the time of writing this Asset Management Plan. It will be adopted by Council in April 2015.

REGIONAL PUBLIC TRANSPORT PLAN 2015

The purpose of the regional public transport plan is to provide:

·      A means for encouraging councils and operators to work together in developing public transport services and infrastructure.

·      An instrument for engaging with the public in the region on the design and operation of the public transport network.

·      A statement of:

o    The public transport services that are integral to the public transport network.

o    The policies and procedures that apply to those services.

o    The information and infrastructure that supports those services.

The Regional Public Transport Plan is under development at the time of writing this Asset Management Plan. It will be adopted by 30 April 2015.

ARTERIAL TRAFFIC STUDY 2011

The Arterial Traffic Study was a key initiative in order to achieve the Community Outcomes 2009/19 Nelson Community Plan.

The objective of the Arterial Traffic Study was to determine the best transport system configuration between Annesbrook and the Queen Elizabeth II/Haven Road roundabouts that will improve the city as a whole in the long term. Refer to section 2.1 for more details on the outcomes of the study.

SOCIAL WELLBEING POLICY 2010

The Counci’s vision for this policy is that Nelson has a happy, healthy community where people have access to necessary services and facilities and feel connected to each other and to the city.

Council will ensure that social wellbeing issues are considered when planning and delivering new services, facilities and activities.

Areas where Council has a key responsibility or role include the physical environment, leisure and recreation, social connectedness, cultural identity, civil and political rights and safety (particularly relating to safety in public spaces). With limited resources available Council needs to focus on areas where it can have a significant impact and rely on partners to take the lead in other areas.

Council has chosen to focus on particular issues surrounding older people, youth and affordable housing in this policy. These three areas relate to key trends affecting Nelson and have been raised as particular concerns by the community.

Over and above initiatives that directly aim to improve social wellbeing, most Council activities (such as economic development, transport, water supply, waste collection, environmental planning, parks and community facilities) impact on the wellbeing of the community.

Council’s social wellbeing role includes:

·      Leading by example - looking at Council activities through a social wellbeing “lens” to improve social wellbeing outcomes for the community;

·      Partnering, collaborating and facilitating – with central government, community organisations and other stakeholders to target initiatives effectively;

·      Delivery – of services and activities (including through grants to community groups) within wellbeing areas where Council has responsibility;

·      Advocacy – at regional and national levels;

·      Planning – ensuring that the development of facilities and services contributes to enhancing wellbeing in the future.

PEDESTRIAN STRATEGY (2005) AND CYCLING STRATEGY (2006)

These two strategies are well-developed documents, which link back to the Regional Policy Statement for statutory policy and to the LTP for community outcomes and a budget. They are complementary to the Regional Transport Plan.

HEART OF NELSON – CENTRAL CITY STRATEGY

This was a special study, carried out in 2009, focused at the Council’s interest in achieving various community outcomes in the LTP. The Mayor’s Foreword states that the Council “wants to maintain a vibrant and vital heart of the city” for locals and visitors, and to encourage economic development. It is intended “to manage growth in a coordinated manner and to maintain and enhance the successfulness of the City Centre and surrounding area”.

The Strategy consists of an overall vision supported by numerous specific suggestions and proposals to enhance the function, usability and vitality of the city centre over time.

TAHUNANUI STRUCTURE PLAN

This structure plan is dated 2004 and had its genesis in the Tahunanui Enhancement Study 2002, which looked at improvements needed in the City’s popular beach recreational area arising from expressed concerns about the “existing condition of Tahunanui”.

The achievement of the Structure Plan relies primarily on public expenditure to achieve street layout and access changes, and changes to the Nelson Resource Management Plan to enable intensification and cohesion around the traditional commercial heart of Tahunanui. The structure plan has no statutory force.


OTHER KEY PLANS & STRATEGIES RELATING TO TRANSPORT

·      Nelson Urban Growth Strategy 2005

o    Road Reserve Management Policies and Procedures (pending)
Objective is to provide for a consistent approach to road reserve asset and activity management and to demonstrate to the community that Council recognises the critical importance of managing the road reserve asset and activities in an effective and sustainable manner;

o    Council will manage the city’s assets and activities on the road reserve in a cost effective, sustainable, well planned and coordinated manner to provide agreed levels of service. Council will use the various policies and procedures referenced in Road Reserve Management Policy as the means to fulfil its ownership responsibilities under the Local Government Act 2002.

·      Land Development Manual 2010;

·      Safety Management Strategy 2007;

·      Road Safety Action Plan.

 


Appendix C           Strategic documents, studies and models providing demand data

Demand Driver

Document Name

Date

Source reference

Notes

Sustainability

Sustainability Stock take

April 2011

A293617

 

Population

Population projections

2015

A1322277

 

All

Arterial Traffic Study

2010-2011

A371678 - Stage 1

A362768 - Stage 1B

A431870 – Stage 3

A618888 - Stage 4

Includes consideration of fuel price rises, sea level rises etc.

Update on several key demand drivers

Regional Land Transport Strategy & Regional Land Transport Programme Annual Monitoring report

September 2010

 

 

 

 

November 2013

A378027

 

 

 

 

 

A478601

Includes journey to work, main means of travel, traffic volume, travel times on arterials, vkt’s, cycle and ped counts, comprehensive cycle count data, pt patronage, safety data.

Traffic growth

Nelson Tasman Transport Model TRACKS model building report

2009-2010

A673715-model building report

1089224-model data

945050,945051-turning movement data

945048-level of service

Includes data on future transport demands.

Population, demographic, household car ownership, journey to work, freight, air connections and employment data

Regional Land Transport Strategy

June 2009

RAD 696474

Also provides future travel demand and future journey to work predictions, along with Council’s long term passenger transport aspirations.

Central City strategic direction

Heart of Nelson Strategy

Aug 2009

RAD 845339

 

Population, freight, car parking, future land use and residential growth areas

TRACKS models input data

May 2009

781450

813236

 

Traffic flow along Waimea Road

Waimea Rd Microscopic Traffic Simulation Model

July 2009

798279, 798280, 813239, 797883

Includes various intersection scenarios.

Car Parking

2009 Central Business District Parking assessments and district ratio analysis

2009

800221, 800227, 800228

 

Sea-level rise

Review of Nelson City minimum ground level requirements in relation to coastal inundation and sea level rise

August 2009

RAD 825295

 

Population and employment growth to 2016, journey to work patterns and discussion of travel patterns

Passenger Transport Network Review

October 2008

RAD 701862

 

Traffic flow

Signalised intersection design data

 

796898

 

Road safety data

Crash Accident Study

1995

1998

2001

2008

799187

342066

799203

742399

 

Car Parking

Parking Studies

2005

2008

682309

788326

 

Traffic flow and parking data

Nelson Central Business District Microscopic Traffic Simulation Model

2012

5/2005

A789874

789948

 


Appendix D          Growth indicators

Congestion –Traffic Flow Data on the Main Arterials – ATS

Peak hour traffic count information has been obtained for three locations on the arterial routes and are summarised below. The data was obtained during February 2014.

Table D.1      Peak Hour Volumes

Car Trips –Traffic Flow Data on the Main Arterials

The following graph shows the 7-day average daily traffic volumes for selected roads over time.


Figure D.1     Nelson Arterial Traffic Volumes

The following graphs show the peak hour traffic volumes on the arterial routes by direction. The data has been presented from 2009 to the latest data available for 2014. This data range is for the period that the current traffic counting contractor has been working for Nelson City Council. Data prior to this does not contain enough detail to present graphs such as those following and as a result it has been excluded.

Figure D.2     Waimea-AM Peak Hour Ending 0900

Traffic volumes on Waimea Road in the AM peak hour have been reducing slightly in the northbound direction and have remained static in the southbound direction.


 

Figure D.3     Waimea – Peak Hour Ending 1700

 

Traffic volumes on Waimea Road in the PM peak hour have been reducing in the southbound direction and increasing in the northbound direction.


 

Figure D.4     Waimea – Midday Peak Hour Ending 1300

Traffic volumes on Waimea Road in the midday peak hour have been reducing in the southbound direction and have remained static in the northbound direction.


 

Figure D.5     Waimea – Weekday AM Peak Hour Ending 0900

Traffic volumes on Waimea Road, with weekend data removed, in the AM peak hour have been remained static in the southbound direction and have decreased in the northbound direction.


 

Figure D.6     Waimea – Weekday PM Peak Hour Ending 1700

Traffic volumes on Waimea Road, with weekend data removed, in the PM peak hour have reduced in the southbound direction and have increased in the northbound direction.


 

Figure D.7     Waimea – Weekday Midday Peak Hour Ending 1300

 

Traffic volumes on Waimea Road, with weekend data removed, in the midday peak hour have been reducing in the southbound direction and have remained static in the northbound direction.


 

Figure D.8     Rocks Road -AM Peak Hour Ending 0900

 

Traffic volumes on Rocks Road in the AM peak hour have remained static in the northbound direction and have reduced in the southbound direction.


 

Figure D.9     Rocks Road– PM Peak Hour Ending 1700

 

Traffic volumes on Rocks Road in the PM peak hour have remained static in the northbound direction and have reduced in the southbound direction.


 

Figure D.10   Rocks Road– Midday Peak Hour Ending 1300

 

Traffic volumes on Rocks Road in the midday peak hour have remained static in the northbound direction and have reduced in the southbound direction.


 

Figure D.11   Rocks Road – Weekday AM Peak Hour Ending 0900

 

Traffic volumes on Rocks Road in the AM peak hour, with weekend data removed, have increased in the northbound direction and have reduced in the southbound direction.


 

Figure D.12   Rocks Road– Weekday PM Peak Hour Ending 1700

 

Traffic volumes on Rocks Road in the PM peak hour, with weekend data removed, have remained static in the northbound direction and have reduced in the southbound direction.


 

Figure D.13   Rocks Road – Weekday Midday Peak Hour Ending 1300

 

Traffic volumes on Rocks Road in the weekday peak hour, with weekend data removed, have increased slightly in the northbound direction and have reduced in the southbound direction.


 

Figure D.14   Main Road Stoke –AM Peak Hour Ending 0900

 

Traffic volumes on Main Road Stoke in the AM peak hour have reduced in both the northbound and southbound directions.


 

Figure D.15   Main Road Stoke – PM Peak Hour Ending 1700

 

Traffic volumes on Main Road Stoke in the PM peak hour have remained static in the northbound direction and reduced in the southbound direction.


 

Figure D.16   Main Road Stoke – Midday Peak Hour Ending 1300

 

Traffic volumes on Main Road Stoke in the PM peak hour have increased in the northbound direction and reduced in the southbound direction.


 

Figure D.17   Main Road Stoke – Weekday AM Peak Hour Ending 0900

 

Traffic volumes on Main Road Stoke in the AM peak hour, with weekend data removed, have remained static in the northbound direction and reduced in the southbound direction.


 

Figure D.18   Main Road Stoke – Weekday PM Peak Hour Ending 1700

 

Traffic volumes on Main Road Stoke in the PM peak hour, with weekend data removed, have remained static in the northbound direction and reduced in the southbound direction.


 

Figure D.19   Main Road Stoke– Weekday Midday Peak Hour Ending 1300

 

Traffic volumes on Main Road Stoke in the midday peak hour, with weekend data removed, have increased in the northbound direction and reduced in the southbound direction.

 


 

The following graphs show the total traffic using Waimea Road and Rocks Road. Note that these are composite peak hour volumes due to the surveys for both arterials being done at different times. The numbers presented show the totals for each weekday per month surveyed but are offset by up to three weeks.

Figure D.20   Waimea – Rocks Road - AM Peak Hour Ending 0900 - Screenline

 

The AM peak has remained essentially static from 2009 to date. The weekend data is included in this graph and is shown by the band of data points well below the main concentration of data associated with the weekdays.


 

Figure D.21   Waimea – Rocks Road - PM Peak Hour Ending 1700 - Screenline

 

The PM peak data does not show the same range as the AM data with weekends operating at a level much closer to the main weekday data set. The traffic in the northbound direction has remained essentially static. Southbound PM peak flows have trended downwards over the period presented above.


 

Figure D.22   Waimea – Rocks Road - Midday Peak Hour Ending 1300 - Screenline

 

Data for the midday peak show that northbound traffic has remained static and southbound traffic has deceased.


 

Figure D.23   Waimea – Rocks Road – Weekday AM Peak Hour Ending 0900 - Screenline

 

When the weekend data is removed the trend does not change with traffic volumes in the AM peak remaining essentially static from 2009 to date but with a very slight reduction in northbound traffic.


 

Figure D.24   Waimea – Rocks Road – Weekday PM Peak Hour Ending 1700 - Screenline

 

Once the weekend data is removed the northbound PM peak traffic shows a slight increase. The decreasing trend in the southbound traffic volumes remains.


 

Figure D.25   Waimea – Rocks Road – Weekday Midday Peak Hour Ending 1300 - Screenline

 

 

The trends in the midday peak remain unchanged by removal of the weekend data. The southbound traffic volumes have been decreasing and the northbound volumes remaining static.


Walking –Historic Pedestrian Counts

The following graphs show the time series data for pedestrian counts extrapolated out to 24 hours. Counts were started in 2001 and counted regularly every 6 months from 2005 onwards. Two additional sites were added in 2010, the Whakatu Drive and Atawhai Drive shared paths. The seasonal difference in number of pedestrians is clearly visible.

Figure D.26   Pedestrian Counts


Figure D.27   Pedestrian – 7 hr Count Total


Figure D.28   2010 Comprehensive Cyclist and Pedestrian Count

Note: These surveys are to be repeated at five yearly intervals with the next due in 2015.

Cycling –Historic Pedestrian Counts (Regional Land Transport Strategy Annual Report)

The following graphs show the actual number of cyclists counted over a 7 hour period. Counts are taken at the same sites and times as the pedestrian counts.

Figure D.29   Cyclists – 24 hrs Estimates


Figure D.30   Cyclists – 24 hrs Estimates (All Routes Above)


Figure D.31   2010 Comprehensive Cyclist and Pedestrian Count

Note: These surveys are to be repeated at five yearly intervals with the next due in 2015.

Nelson Projections

Table D.2      Population projections, 2015-2045

Figure D.33   Nelson - Projected population, 2015-2045

 

 


KEY TRENDS

·      Population and household numbers increasing but at a slower rate;

·      Ageing population;

·      Smaller households;

·      Growth in Stoke.

 

Nelson – population trends

·      Nelson’s population is expected to grow by 3,600 residents over the next ten years, to 53,320 in 2025, at an average annual growth rate of 0.7 percent

·      Half the growth between 2015 and 2025 is driven by an increase in Stoke’s population and the populations in Nelson Central, Nelson North and Tahuna are also expected to increase

·      Population growth is expected to slow down over time, based on the assumption that deaths will increase while births stay constant, and that migration rates also remain constant

·      Nelson’s population is likely to grow by a further 2,700 over the 20 years between 2025 and 2045, to 56,000 in 2045, at an average annual growth rate of 0.2 percent

·      Most of the growth in these later years is again driven by an increasing population in Stoke and, to a lesser extent, in Nelson North

·      Nelson’s population is ageing and the median age is projected to increase from 43 in 2015 to 50 in 2045

·      The proportion of the population aged 65 years and over will increase from 18% in 2015 to 25% in 2025 and is likely to make up a third of the population in 2045

·      The proportion of the population aged under 15 years will decrease after 2018, from 18% to 16% in 2025 and to 15% by 2045

Figure D.34:  Population projections by age groups, Nelson


 

Nelson – households TRends

·      The number of households in Nelson is projected to increase by about 1,800 in the ten years between 2015 and 2025, to 22,310

·      As with the population growth, about half the increase between 2015 and 2025 in the number of households is driven by growth in Stoke and a quarter is by Nelson Central

·      The number of households in Nelson is projected to increase by another 1,800 in the twenty years between 2025 and 2045, to 24,150, with over half of the increase driven by an increasing number of households in Stoke

·      Overall there is a trend towards smaller households with an increase in one-person households

Method

·      Annual population projections which align with Nelson City Council Long Term Plan and Infrastructure Strategy reference years (2015-2025-2045) have been calculated using linear interpolation. Annual household projections have been calculated using ratios between population and households suggested by Rationale Ltd in their 2014 peer review and confirmed in February 2015 as still being valid. These numbers are indicative until Statistics New Zealand release 2013-based household projections on 8 December 2015. Projections for different areas within Nelson (Stoke, Tahuna, Central and North) are based on 2013-based area unit projections which were published on 9 July 2015.

·      Projections are not predictions and should be used as an indication of the overall trend, rather than as exact forecasts.

 


Appendix E           How the focus areas link with the government’s, NZ Transport Agency’s and Council’ s strategic documents

Focus Area Safety

Government’s long-term outcomes:

·      To drive improved performance from the land transport system by focussing on:

o    Economic growth and productivity;

o    Road safety;

o    Value for money.

Government’s Forward Plan for Transport:

·      Implement the Safer Journeys road safety strategy and its Safe System approach, so there is a sustained reduction in deaths and serious injuries on the roads over time.

Government Policy Statement 2015 objective:

·      Free of death and serious injury.

Regional Land Transport Plan:

·      Aligns with GPS.

Nelson Community Plan outcomes:

·      People-friendly places - We build healthy, accessible and attractive places and live in a sustainable region;

·      Kind, Healthy People – We are part of a welcoming, safe, inclusive and healthy community.

Nelson City Council Pedestrian Strategy goals:

·      Provide a safe network;

·      Provide a user friendly network.

Nelson City Council Cycling Strategy outcomes:

·      A culture that acknowledges cycling as a part of everyday life, where people support cycling and see it as a safe transport choice;

·      A safe, convenient and continuous cycle route network linking all parts of the City, incorporating best practice design and engineering standards.

Focus Areas: Local Roads, Walking, Cycling and Schools, and Public Transport

Draft Government Policy Statement 2015 objective:

·      A land transport system that provides appropriate transport choices.

Government Policy Statement 2015 long term result:

·      Improved returns on investment in public transport.

·      Enable access to social and economic opportunities, particularly for people with limited access to a private vehicle.

·      Increased safe cycling through improvement of the cycle lane network.

Regional Land Transport Plan:

·      Aligns with GPS.

Nelson Community Plan outcomes:

·      Healthy land, sea, air and water – We protect the environment;

·      People-friendly places – We build healthy, accessible and attractive places and live in a sustainable region;

·      A strong economy – We all benefit from a sustainable, innovative and diversified economy;

·      Kind, Healthy People – We are part of a welcoming, safe, inclusive and healthy community.

Nelson City Council Pedestrian Strategy goals:

·      Develop a linked network;

·      Recognise walking as an important physical activity.

·      The LTP included an action to develop an active transport and active recreation policy which will supersede the pedestrian strategy in 2015.

Nelson City Council Cycling Strategy outcomes:

·      A culture that acknowledges cycling as a part of everyday life, where people support cycling and see it as a safe transport choice.

·      The LTP included an action to develop an active transport and active recreation policy which will supersede the pedestrian strategy in 2015.

Focus Areas: Arterial Traffic, Parking and Value for Money Principle

Draft Government Policy Statement 2015 Objective:

·      A land transport system that is reliable and resilient.

·      A land transport system that addresses current and future demand.

·      A land transport system that provides appropriate transport choices.

·      A land transport system that appropriately mitigates the effects of land transport on the environment.

Government Policy Statement 2015 long term result:

·      Support economic growth and productivity through provision of better access to markets, employment and business areas;

·      Improved returns from investment in road maintenance;

·      Support economic growth of regional New Zealand through providing better access to markets;

·      Improved network resilience and reliability at the most critical points;

·      Understand the costs associated with environmental mitigation.

Regional Land Transport Plan:

·      Aligns with GPS.

Nelson Community Plan outcomes:

·      People-friendly places – We build healthy, accessible and attractive places and live in a sustainable region;

·      Kind, Healthy People – We are part of a welcoming, safe, inclusive and healthy community.

 


Appendix F           Definition of Levels of Service

Table F.1       Definition of Levels of Service

RAD_n817181_v1_Nelson_South_Modelling_outputs_Page_26

 


Figure F.1     Nelson-Tasman Transportation Model Link LoS Criteria

RAD_n817181_v1_Nelson_South_Modelling_outputs_Page_27

 


Table F.2       Nelson Arterial Traffic Study Network Performance Summary Statistics

RAD_n1008669_v1_Appendix_C_-_Model_Outputs 4

Table F.3       Nelson Arterial Traffic Study Network Performance Summary Statistics

RAD_n1008669_v1_Appendix_C_-_Model_Outputs 1

 


APPENDIX G          STREETS WITHOUT FOOTPATHS

 


Appendix H          Annual Peak travel time delays on Rocks Road and Waimea Road

Figure H.1     Annual Average Morning Peak Travel Times – Waimea Road

Figure H.2     Annual Average Evening Peak Travel Times – Waimea Road

Figure H.3     Annual Average Morning Peak Travel Times – Rocks Road

Figure H.4     Annual Average Evening Peak Travel Times – Rocks Road

It is noted that the size of the sample is very small at around 36 surveys in total per year. As a result there is more variability in the sample then would be expected from a larger sample and indeed within the population. As a result, it is proposed to change the survey to increase the sample size.


Appendix I           Previous LEVEL OF SERVICE and why they have changed

Service

Previous Level of Service

Proposed Level of Service

Reason for change

Safety

Nelson City Council cyclist causalities are below the peer group average.

The social and economic costs of crashes on the transport network are minimised

Nelson City Council crash rates are below the peer group average.

Total social cost of urban crashes at the worst 10 intersection, is below the previous 5 year average.

The personal risk for each year reduces at least 2% per year from a base of 2007.

The collective risk for each year reduces by at least 4% per year from a base of 2007.

The total social cost for all intersections each year reduces by t least 4% per year from a base of 2007.

Nelson City Council pedestrian casualties are below the peer group average.

The previous performance targets are difficult to quantify.

The number of crashes including pedestrians each year reduces by at least 4% per year from a base of 2007.

Nelson City cycle crashes do not increase from these in the base year of 2007.

Public Transport

Public transport services that meet the transport needs of the community with an equitable sharing of costs.

Using the farebox recovery ratio 30-35% increase to approx 50% between 2015/16 and 2018/19.

Farebox recovery ratio to be greater than 50%.

New levels of service reflects actual improvement in performance to date more accurately.

Parking

Availability of long stay parking spaces in the interpeak as a percentage of the total long stay spaces within 20 min walk of the Central Business District, no less that 5%.

A reducing trend in occupancy of long-stay parking spaces between peak travel times at 9 sample locations within the Central Business District fringe.

The new level of service supports the balanced approach and the and is a better measure of the parking performance to assist with creating modal shift from single occupancy vehicles.


Appendix J           SUMMARY activity descriptions

This section contains summary descriptions of key work proposed.

Subsidised Maintenance

Network and Asset Management 151

·      Maintenance of RAMM database ($130.000/year)

o    Assumes roughness and rating measurements and database updated annually.

o    Includes $10,000/year for improving retaining wall and bridge data.

·      Bridge inspections ($20,000/year)

·      Retaining wall inspections ($31,000 in year 1 and increasing 2% per year, every year for years 2-10)

o    Assumes that there will be a 2% annual growth in retaining walls due to the land remaining to be developed being predominantly on hillsides.

·      Staff time for operations and maintenance ($250,000/year)

·      Staff time for asset management ($60,000/year)

·      Corridor access requests ($30,000/year)

·      Network wide crash analysis ($10,000/year)

·      Pavement testing for informing renewals programme ($50,000/year)

o    Dtims, FWD and similar.

·      Promotion of car pooling and other travel demand measures ($57,000/year)

Transportation Model Update ($40,000)

·      Allows for an update of the regional transportation model once the 2018 census data is available in year 4. This work may be done as part of a southern arterial study.

·      $40,000 has been allocated in year 4 to review and update the model after the 2018 Census.

Subsidised CAPITAL EXPENDITURE

Sealed Road Resurfacing

·      1.33M/year for years 1-3 and then 1.4M for years 4-10

Pavement Rehabilitation

·      Year 1 - $450,000

·      Year 2 - $120,000

·      Year 3 - $180,000

·      Year 4 - $780,000

·      $300,000 per year there after

·      Reflects the need for the pavement rehabilitation on both Quarantine Road between SH6 and Nayland Road and Cable Bay Road in Year 1.

 

Drainage Renewals 213 ($100,000 in year 1 with 0.6% increase per year, every year for years 2-10)

·      This work has not previously been budgeted for however work under this category is essential to keep the pavement structure dry.

·      Allows for 0.6% growth in the network with new development.

Traffic Services Renewals 222

·      The single significant item in this work category is $200,000/year for streetlight renewals in years 1-3 then reducing to $130,000/year for years 4-10.

Structures Component Replacement 215

·      Average of $380,000pa for first 3 years then 250,000pa for years 4 to 10.

·      Provides for the renewal of bridge and retaining wall structures, or their major components

Minor Improvements ($650,000/year)

·      Under the current funding regime, minor improvement projects up to an individual value of $300,000 are permitted without robust economic justification up to 5% of the total annual transport expenditure. This allows projects to receive NZ Transport Agency co investment without the rigor of a full benefit cost analysis.

·      Historically Council has progressed minor safety projects under this budget. In this AMP we have included all projects that are eligible for NZ Transport Agency co investment.

·      The following projects will be completed in year 1:

o    Maori Road Retaining Wall

o    Home zone projects

o    Waimea Road/The Ridgeway Intersection improvements

o    Gibbs Bridge – Maitai valley Seismic Upgrade

o    Poleford Bridge - Maitai Valley Road seismic upgrade

Waimea Road/ Van Diemen Street Junction Improvements

·      Intersection is highly congested with delays induced on Waimea Road by drivers stopping to let vehicles into and out of Van Diemen Street.

·      $50,000 in year 8 for investigation, $100,000 in year 9 for detailed design and $1,2M in year 10 for construction.

·      Anticipated to be traffic signals at this stage but Central Business District West traffic study in year 3 will likely define form and timing.

·      Until the investigation work is done it is not possible to know whether the threshold for funding subsidies will be met. There is a chance that an appropriate BCR will not be achievable due to the increase in delay to Waimea Road traffic.

Waimea Road Retaining Wall at Snows Hill

·      $485,000 to secure the steep unsupported cut slope above Waimea Road at Snows Hill opposite the Girls College Playing Fields.

HPMV Upgrades – 50Max Maitai Valley Road

·      Upgrades to the bridges in the Maitai Valley to accommodate 50 Max HPMV vehicles. Three bridges to be improved; Smiths Ford, Jickells and Gibbs bridges.

Quarantine Road Nayland Road Intersection Upgrade

·      Modelling shows that the queues from the intersection will cause unstable flows as traffic volumes increase.

·      $2,75M planned over three years from year 7.

Rocks Road Walking and Cycling Facilities

·      Currently these are no cycle lanes running the full length of Rocks Road. The Rocks Road Walking and Cycling Study was undertaken in 2014 to determine the form of the walking and cycling facilities along this route. At the time of publishing this AMP no final decision has been made.

·      Nelson City Councils contribution is $3M in total spread out over years 1-3. NZ Transport Agency will contribute in the order of $14M.

·      Allows for an improved walking and cycling facility between Crop and Food Research and Tahunanui Drive.

Maitai Shared Path (Saltwater Creek Bridge)

·      $30,000 in year 1 for design and $345,123 in year 2 for construction.

·      Allows for replacement of the existing bridge adjacent to the Maitai River to allow two-way pedestrian and cycle use.

·      Funding for the Maitai Walkway to Rocks Road link was added during the LTP development.

Tahunanui Cycle Network

·      There is a significant gap in the cycle network between Rocks Road and Stoke. Vulnerable users are required to negotiate busy roads with no cycle facilities.

·      $100,000 for design in year 1 then $260,000 in year 2 and $500,000 in year 3 for construction.

·      Provides a link between the end of Rocks Road and Stoke. Option 4 in the Opus report for the project is preferred but yet to be confirmed.

UnSubsidised expenditure

Stoke Foothills Traffic Study ($100,000 in year 1)

·      Study to determine the likely effect of growth in the Marsden and Ngawhatu Valleys on the surrounding transport network.

·      The primary focus of the study will be to determine where future investment in the transport network should occur, particularly on the links to Main Road Stoke and Waimea Road and along the Ridgeway.

Atawhai Hills Traffic Study ($100,000 in year 2)

·      Study to determine the viability and likely route of a link road running the length of the Atawhai Hills.

·      The Study will include a high level geotechnical assessment along with a landscape assessment.

·      The final route will be included in the Nelson Plan as an indicative road.

Milton Street (Grove to Cambria)

·      This section of road currently has no kerb and channel. There is high demand for parking in this location so improving pedestrian safety with a full height kerb is priority.

·      $20,000 for design in year 5 with $500,000/year in years 6 and 7 for construction.

·      Allows for the construction of new kerb and channel, footpaths and carriageway surface and aligns with stormwater upgrade.

Halifax Street (Maitai River to Milton)

·      $10,000 in year 1 for investigation, $50,000 in year 2 for detailed design and $600,000 in year 3 for construction.

·      Allows for the construction of new kerb and channel and carriageway surface.

·      Aligns with timeline for stormwater upgrades.

Wigzell Area Speed Reduction

·      The primarily residential Wigzell area south of Nelson hospital has very wide streets with straight alignment. As a result, vehicle speeds in the area are higher than the ideal 30km/h for a residential zone.

·      $10,000 in year 2 for investigation, $40,000 in year 3 for design and $800,000 in year 4 for construction.

·      Allows for kerb and channel on Alfred Street and calming measures on other roads in the area. Stormwater on Alfred Street will be upgraded at the same time.

·      Project removed from budget and will be funded from Minor Improvements and footpaths renewals as budgets allow.

Todd Bush Road

·      There is currently no footpath along Todd Bush Road. There is a school bus stop at the intersection of Todd Bush Road and SH6 and relatively high demand for its services. A footpath is needed to improve safety for students walking to and from the bus stop.

·      $600,000 for construction in year 1.

·      Allows for construction of kerb and channel and a footpath on one side of Todd Bush Road between SH6 and Todd Reserve.

Main Road Stoke/Marsden Road

·      With access to Waimea Road from The Ridgeway difficult and unlikely to be improved due to the difficulties in providing additional capacity, it is important that alternative access to the arterial network is provided.

·      Traffic volumes on Main Road Stoke are significantly lower than on Waimea Road which may make improving side road access at this intersection more economically viable.

·      $30,000 in year 7 for initial investigation, $70,000 in year 8 for design and $900,000 in year 9 for construction.

·      Allows for a signalised intersection with minor kerb changes. No land purchase allowed for.

 

Lighting of Railway Reserve

·      The current standard of lighting on the Railway Reserve shared path is non-existent in sections and poor in other areas and does not provide an adequate level of safety or convenience for users.

·      $20,000 has been allocated to undertake a robust business case.

Muritai SH6 Including Pedestrian Crossing Across SH6

·      The alignment of Muritai Street as its intersection with SH6 encourages high speed through the left turn from Muritai in particular. Left turning drivers typically attempt to turn into marginal gaps in the SH6 traffic while maintaining high speed which is a safety concern. Crossing SH6 is unsafe for pedestrians unless they direct from their desired line to the nearby signals.

·      $40,000 in year 2 for design and $60,000 in year 5 for construction.

·      Allows for Muritai Street to be squared up to SH6 to lower vehicle speeds as well as for a pedestrian crossing facility on SH6 north of Muritai Street.

Tahunanui Car Park

·      NZ Transport Agency agreed to remove the clearway on the east side of Tahunanui Drive to give council four years to find an alternative location for parking for businesses that currently rely on the on-street parking. At the end of the four year period, the parking on the east side will be removed which is expected to increase the capacity of the Bisley Avenue/SH6 intersection by approximately 10%.

·      $50,000 in year 1 for design and $150,000 in year 2 for construction.

·      Allows for piping of the open drain adjacent to 23 Tahunanui Drive and construction of a shared parking and access resource over the old drain, existing chemist parking and right-of-way serving numbers 15, 17 and 19 Tahunanui Drive.

New Footpaths ($200,000/year)

·      There are a large number of streets in Nelson that do not have footpaths on both sides. While it is ideal to have footpaths on both sides of all roads, in some situations, like hillside sites, it is difficult to provide them. In other situations developers have chosen to only provide a single footpath, particularly on short cul-de-sacs.

·      With the limited resources we have available to us, it is important to prioritise footpath extension projects carefully. Footpath projects are typically prioritised on the basis of proximity to schools, whether there is a footpath on the opposite side of the road, the traffic volume, the zone served by the footpath and whether the project represents value for money. The priority matrix can be found in A777631, the programme is included in Appendix L.

·      The planned footpath extensions for the 2015/16 financial year are as follows:

o    Waimea Road between Chings Road and The Ridgeway.

o    Songer Street between Nayland Road and Durham Street.


 

Footpath Renewals ($300,000/year)

·          A programme of footpath renewals has been developed based on a City wide footpath condition inspection report. It prioritises footpaths in higher use areas, close to schools, shops and elderly centres. It seeks to address the condition of the footpaths to improve pedestrian safety, comfort and convenience whilst managing the condition of our footpaths with a timely and economic priority.

Marsden Valley-Ridgeway Upgrade

·      There is an existing road safety problem at this intersection with limited visibility available on some approaches and relatively high speeds on The Ridgeway. Minor road marking changes will be undertaken in the short term.

·      Marsden Valley is expected to be one of the largest sources of population growth in Nelson along with Ngawhatu Valley. All traffic generated in the valley will use this intersection.

·      A roundabout has previously been designed for this location although significant design changes will be needed.

·      $75,000 in year 3 for minor safety works, $120,000 in year 7 for design, $400,000 in year 8 for property purchase and $1,600,000 in year 9 for construction.

·      Allows for a single lane roundabout.

Marsden Valley Road

·      The current road cross-section and alignment has the feeling of a high speed rural road which is unsuitable for the residential activity that it will serve as development grows in the valley.

·      $50,000 in year 8 for investigation, $75,000 in year 9 for design and $1.2M in year 10 for construction.

·      Allows for localised traffic calming and alignment changes to reduce speed environment.

Main Road Stoke Marsden Valley Road

·      The Stoke Foothills Study will confirm the form of the intersection. In order to encourage traffic from that development onto the arterial network providing an efficient and safe link is necessary.

·      $2.0M budgeted over 3 years starting in year 7.

Lucas Terrace

·      Current carriageway needs to be upgraded to local residential standard to allow for the residential development of the greenfields site at the end of the current formation.

·      $150,000 budgeted over 2 years starting in year 6.

·      Removed from budgets. Upgrade will be funded by developer.

CBD Enhancement

·      This provides a budget to continue the work started under The Heart of Nelson initiative. Council will need to prioritise projects which are still relevant during the LTP development.

·      $100,000 in year 1 then $500,000 per year for the next 9 years has been provisionally budgeted.

·      CBD enhancement. Project budget cutback:

·      Year 1 $50,000 to develop programme of activities for future years 

·      Year 2 $250,000

·      Year 3 $250,000

·      Year 4 $300,000

Parking Strategy

·      The parking strategy, once finalised in 2014 will be reviewed every 8-10 years in order to ensure that the city’s parking resources are being used and managed in the most appropriate manner.

·      $20,000 in year 7 and $80,000 in year 8 for development of a new Parking Strategy.

Parking Strategy Implementation ($270,000 year 1 and $120,000 year2)

·      Install signage directing users to the parking squares from the CBD ring route, $200,000 in 2015/16 and $100,000 in 2016/17.

·      Reconfigure the traffic signals on Main Road Stoke at the Putaitai intersection to allow the right turn out to prevent unnecessary movements through Strawbridge Square carpark, $40,000 in 2015/16.

·      Modify the tree planters in Strawbridge Square carpark to minimse damage, $30,000 in 2015/16.

·      Allocate a small number of campervan and motor home spaces within the CBD, $20,000 in 2016/17.

Renewals: On- and Off -Street Parking Meters

·      The current parking meters are due for replacement in the 2015/16 financial year as they have come to the end of their design life. There has not been any increase in maintenance cost in the last few years approaching the retirement date so replacement has been deferred until the 2017/18 and 2018/19 financial years.

·      The renew would include a technology upgrade to enable payment by credit card and integration with smart phone apps to extend the stay.

·      $470,000/year in years 3 and 4.

Bus Services – (WC 511) Subsidised ($710,000/year)

·      Allows for wider route coverage of Stoke.

·      A large proportion (almost 100%) is expected to be funded by NZ Transport Agency with Councils costs remaining at a similar level to previous years.

Stoke Interchange (WC531)

·      It is expected that as Stoke grows that there will be an increase in bus trips starting and finishing in the Stoke town centre.

·      $20,000 in year 8 for design and $200,000 in year 9 for construction.

·      Allows for a small central interchange area within the Stoke town centre area. The location, timing and size will be guided, in part, by the outcomes of the 2014 Stoke Needs Study.

 

 

Integrated Ticketing (WC531)

·      Moving from the current manual ticketing system to an electronic one for the bus service is required as the current system is inefficient and nearing its end of life.

·      NZ Transport Agency are leading a joint procurement process in partnership with all of the participating Councils. This approach allows for the sharing of the up front capital costs based on the size of each councils service.

·      NZ Transport Agency are also subsidising the costs at a rate of 58%.

·      Nelson City Councils share of the total capital cost will be $61,000 spread over years 1 and 2 and the 2014/15 financial year.

Projects added

·      Stoke CBD enhancements: Year 1 $150,000; Year 3 $100,000; Year 4 $500,000

·      Toi Toi Street to upgrade the upper part of Toi Toi Street to sub collector road standard:  Year 4 $15,000; Year 5 $35,000; Year 6 $400,000.  Identified and adopted as part of Development Contributions Policy deliberations (LTP) to release further land for residential growth

·      Toi Toi Street / Vanguard Street to improve safety at this intersection: Year 4 $15,000; Year 5 $35,000; Year 6 $250,000. Identified and adopted as part of Development Contributions Policy deliberations (LTP) to release further land for residential growth

 

 

·     


Appendix K           Regional Land Transport Programme 2015-2021

Table 4 - Extract from Regional Land Transport Plan – Agreed Top of the South Significant Activities.

Nelson projects highlighted in the blue rows

 

Indicative

Ranking

Duration

Description

Organisation Responsible

Phase

Region

Contributes to Regional Objectives (refer Table 2 and Appendix 3 of monitoring performance measures)

Performance Monitoring Measure

Cost

Profile (based on 2012 GPS)

1

2015-18

SH1 Weld Pass realignment

NZTA

Design, Investigation, Planning and Construction

Marlborough

1, 2, 4

Crashes, resilience, travel time

 

HMM-3

2

2015-18

SH6 Rai Saddle Second Curve Realignment

NZTA

Planning and Construction

Nelson

1, 4

Crashes

$7,148,342

MHH - 2

3

2015-18

SH6 (Whakatu Drive) - Quarantine Road intersection upgrade

NZTA

Construction

Nelson

1, 2, 4

Travel time

$3,100,000

MMH - 4

4

2015-18

Walk Cycle Schools Package

 

 

 

 

 

 

 

MMM - 6

 

 

Rocks Road walking and cycling project

Nelson City Council

Design and construction

Nelson/NZTA

1,3

Cycle and pedestrian growth, cycle crashes

$14,250,000

 

 

 

Tahunanui cycle network

Nelson City Council

Design and construction

Nelson

1,3

Cycle and pedestrian growth, cycle crashes

$860,000

 

 

 

Rocks Road – Maitai path (Saltwater Creek bridge only)

 

Nelson City Council

Design and construction

Nelson

1,3

Cycle and pedestrian growth, cycle crashes

$375,100

 

 

5

2018-21

SH6 Aniseed Valley to Saxton Corridor Strategic Business Case

NZTA

Investigate, design and planning

Tasman/Nelson

1,2,4

Travel time

 

 

6

2018-21

SH6 Whangamoa South realignment Stage 1 (include Teal River bridge realignment and lower bends)

NZTA

Design and construction

Nelson

1, 2, 3,4

Crashes, travel time, resilience

 

 

7

2018-21

SH 6 Rai Saddle Section C Curve Realignment

NZTA

Investigate, design and construction

Marlborough

1, 4

Crashes

 

 

8

2018-21

SH6 Whangamoa South realignment Stage 2

NZTA

Design and construction

Nelson

1,2,3,4

Crashes, travel time, resilience

 

 

9

2018-21

SH6 Hope Saddle realignment

NZTA

Investigate, design, planning and construction

Tasman

1,4

Crashes, travel time, resilience

 

 

10

2018-21

SH60 Motueka River bridge widening

NZTA

Investigate, design and construct

Tasman

1,2,3,4

Travel time, resilience, safety

 

 

11

2015-18

Efficient freight and commuter route from Annesbrook to Haven e.g. Southern Arterial Investigations or existing route capacity improvements

NZTA/

Nelson City Council

Business Case

Nelson/

Tasman

1,2,4

Travel time, resilience

 

 

 

 

 

 

 

Table 6 - Extract from Regional Land Transport Plan - Activities proposed within Nelson City (Refer Table 4 for significant Nelson and inter-regional activities)

Duration

Activity

Organisation Responsible

Contributes to Objectives

Performance Monitoring Measure

Total Cost

NLTF Share

Assessment Framework

Priority

2015-18

SH Minor Improvements

NZTA

1,2,3,4,N4

Various

$900,000

$900,000

HMH - 2

1

2015-18

Public Transport Integrated Ticketing (WC531)

Nelson City Council

1,4,N1,N2,N3

Bus Patronage Growth

$129,200

$61,662

HHM - 2

2

2016-19

Rocks Rd to Maitai Path (Extension of Rocks Road shared path to Maitai path)

NZTA/Nelson City Council

1, N1,N3, N4

Cycle growth and cycle crashes

$1,800,000

$914,400

MMM - 6

3

2017-20

HPMV Upgrades - 50MAX Maitai Valley Road

Nelson City Council

1,3,4,N3

50 Max HPMV Route availability

$450,000

$226,500

MLH - 7

4

2015-18

Enhanced Network Resilience Nelson

NZTA

1,3,4

Unplanned closures

 

 

HLL - 8

5

2015-18

SH6 (Whakatu Drive) north-bound capacity improvements

NZTA

1,2,4

Travel Time

$2,500,000

$2,500,000

MLM - 8

6

2018-21

SH6 Cable Bay Road Intersection

 

NZTA

1,N4

Crashes

 

 

MLM - 8

7

2018-21

Weigh Facility Nelson

 

NZTA

4

Crashes

$3,740,000

$3,740,000

HML - 5

9

2018-21

Stoke Bus Interchange (WC531)

 

Nelson City Council

1,3,N1,N2,N3

Bus Patronage Growth

$320,000

$166,400

MMM - 6

10

Duration

Activity

Organisation Responsible

Contributes to Objectives

Performance Monitoring Measure

Total Cost

NLTF Share

Assessment Framework

Priority

2015-24

Quarantine/Nayland intersection upgrades

Nelson City Council

1,2,4,N3,N4

Travel time

$2,750,000

$1,430,000

MMM - 6

11

2021-24

Waimea Rd/Van Diemen Jct improvements

Nelson City Council

1,4,N4

Travel time delay

$1,350,000

$702,000

MLL - 10

12

2021-24

Parkers Road/SH6 intersection improvements

NZTA

1,2,4,N2

Travel time delay

$1,200,000

$1,200,000

 

13

 

 


APPENDIX l           10 YEAR LONG TERM PLAN – PROGRAMME

Account

Total
Budget
LTP
2015/16

Total
Budget
LTP
2016/17

Total
Budget
LTP
2017/18

Total
Budget
LTP
2018/19

Total
Budget
LTP
2019/20

Total
Budget
LTP
2020/21

Total
Budget
LTP
2021/22

Total
Budget
LTP
2022/23

Total
Budget
LTP
2023/24

Total
Budget
LTP
2024/25

Grand Total

15,363,194

13,283,425

17,922,419

13,142,840

13,287,435

13,037,735

12,430,881

12,593,009

16,977,287

14,284,655

 

 

 

 

 

 

 

 

 

 

 

5001 Subsidised Roading

7,676,970

6,518,455

8,307,096

6,598,612

6,528,547

5,943,151

5,998,435

6,139,056

8,590,025

7,146,357

     Base  Expenditure

3,039,100

3,056,380

3,103,771

3,118,310

3,137,221

3,185,719

3,159,890

3,179,392

3,229,234

3,204,434

          Base Service Provision Council Wide

90,000

89,994

90,045

90,000

90,000

90,000

90,000

90,000

90,000

90,000

               500123101221. WC 432 Road Safety Promotion

90,000

89,994

90,045

90,000

90,000

90,000

90,000

90,000

90,000

90,000

          Base Maintenance

2,934,100

2,946,355

2,958,688

3,013,310

3,027,221

3,040,719

3,054,890

3,069,392

3,084,234

3,099,434

               500120100117. WC 151 Network and Asset Management Expenses

581,000

581,591

582,237

582,897

583,555

584,227

584,911

585,609

586,321

587,048

               500120100118. WC 124 Cycle Path Maintenance

57,000

60,875

64,862

69,137

73,954

78,274

83,187

88,347

93,764

99,452

               500120100119. WC 111 Sealed Pavement Maintenance

500,000

503,029

506,024

509,054

512,108

515,181

518,272

521,382

524,510

527,657

               500120100120. WC 112 Unsealed Pavement Maintenance

45,000

45,242

45,499

45,815

46,090

46,366

46,645

46,924

47,206

47,489

               500120100121. WC 113 Routine Drainage Maintenance

135,900

136,799

137,547

138,408

139,238

140,074

140,914

141,760

142,610

143,466

               500120100122. WC 114 Structures Maintenance

170,000

170,999

172,077

173,078

174,117

175,162

176,213

177,270

178,333

179,403

               500120100123. WC 121 Pest control on road reserve

463,000

464,920

466,724

544,189

546,614

549,054

551,508

553,977

556,461

558,960

               500120100124. WC 122 Traffic Services Maintenance

908,900

909,615

910,461

880,932

881,745

882,581

883,440

884,323

885,229

886,159

               500120100125. WC 123 Operational Traffic Management

73,300

73,285

73,257

69,800

69,800

69,800

69,800

69,800

69,800

69,800

          Base General Operating Expense

15,000

20,031

55,038

15,000

20,000

55,000

15,000

20,000

55,000

15,000

               500126011475. Regional Land Tspt Programme

15,000

20,031

55,038

15,000

20,000

55,000

15,000

20,000

55,000

15,000

     Programmed Expenses

30,000

50,000

50,000

70,000

50,000

50,000

30,000

50,000

50,000

30,000

          Programmed Service Provision

30,000

50,000

50,000

70,000

50,000

50,000

30,000

50,000

50,000

30,000

               500143222163. WC 003 Activity Management Planning Improvement Expenses

10,000

30,000

30,000

10,000

30,000

30,000

10,000

30,000

30,000

10,000

               500143222164. Studies & Strategies

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

               500143722514. Transportation  model update

0

0

0

40,000

0

0

0

0

0

0

     Renewals

2,399,584

2,319,248

2,221,241

2,607,630

2,239,448

2,130,092

2,139,691

2,148,769

2,256,737

2,210,151

          Renewals: Infrastructure

2,399,584

2,319,248

2,221,241

2,607,630

2,239,448

2,130,092

2,139,691

2,148,769

2,256,737

2,210,151

               500173551539. WC 214 Sealed Road Pavement Rehabilitation

450,000

117,045

276,398

777,778

322,703

322,703

322,703

322,703

322,703

322,703

               500173551540. WC 212 Sealed Road Resurfacing

1,326,000

1,333,885

1,329,959

1,397,000

1,397,000

1,397,000

1,397,000

1,397,000

1,397,000

1,397,000

               500173551542. WC 211 Unsealed Road Metalling

58,000

57,986

58,014

58,000

58,000

58,000

58,000

58,000

58,000

58,000

               500173601538. WC 213 Drainage Renewals

100,000

100,575

101,216

101,811

102,422

103,036

103,654

104,276

104,902

105,531

               500173651537. Structures Component Replacement 215

307,021

507,825

317,416

250,000

250,000

250,000

250,000

250,000

250,000

250,000

               500173901541. WC 222 Traffic Service Renewals

405,000

425,495

365,935

266,449

266,937

267,429

267,924

268,421

268,922

269,425

     Capital Growth

134,845

0

0

0

0

0

0

0

0

0

          Capital Growth: Infrastructure

134,845

0

0

0

0

0

0

0

0

0

               500176752172. Railway Reserve/Princess Dr extension overbridge

104,000

0

0

0

0

0

0

0

0

0

               500176801212. Nile Street shared path (Brook Area extension)

40,000

0

0

0

0

0

0

0

0

0

     Capital Increased LOS

2,073,441

1,092,827

2,932,084

802,672

1,101,878

577,340

668,854

760,895

3,054,054

1,701,772

          Capital Increased LOS: Infrastructure

2,073,441

1,092,827

2,932,084

802,672

1,101,878

577,340

668,854

760,895

3,054,054

1,701,772

               500179551525. Minor Improvements 341

650,000

650,000

650,000

650,000

650,000

650,000

650,000

650,000

650,000

650,000

               500179552168. Waimea Rd/Van Diemen Jct improvements

0

0

0

0

0

0

0

50,000

100,000

1,200,000

               500179552934. Quarantine/Nayland intersection upgrades

0

0

0

0

0

0

100,000

150,000

2,500,000

0

               500179552935. HPMV Upgrades: 50MAX Maitai Valley Road

0

0

50,000

200,000

200,000

0

0

0

0

0

               500179752531. School frontage Nelson College

15,000

0

0

0

0

0

0

0

0

0

               500179801227. WC 452 Bishopdale to Ridgeway Shared Path

289,382

0

0

0

0

0

0

0

0

0

               500179801314. Maitai shared path (Saltwater Creek Bridge)

47,000

30,000

345,123

0

0

0

0

0

0

0

               500179802173. Maitai shared path (Collingwood St to Nile St)

600,000

0

0

0

0

0

0

0

0

0

               500179802199. Waimea Road Retaining Wall at Snows Hill

0

0

0

50,000

435,000

0

0

0

0

0

               500179802333. Tahunanui Cycle Network

100,000

260,000

500,000

0

0

0

0

0

0

0

               500179802568. Walk cycle Schools Package: Integrated Activities

150,000

0

0

0

0

0

0

0

0

0

               500179802695. Wood to Intermediate Part C,via Colleges

100,000

0

0

0

0

0

0

0

0

0

               500179802697. Whakatu Drive / Beatson Road

17,203

0

0

0

0

0

0

0

0

0

               500179802699. Railway Reserve to CBD (Stg II via St Vincent (Gloucester St

160,000

0

0

0

0

0

0

0

0

0

               500179802932. Rocks Rd to Maitai shared path

30,000

270,000

1,500,000

0

0

0

0

0

0

0

5002 Unsubsidised Roading

3,370,477

2,522,729

4,985,040

1,837,416

2,064,863

2,972,378

2,479,955

2,357,460

4,420,068

3,052,899

     Base  Expenditure

1,164,926

1,115,177

1,120,458

1,025,773

1,031,119

1,036,496

1,041,907

1,047,349

1,052,825

1,058,332

          Base Service Provision Council Wide

157,439

117,439

117,439

17,439

17,439

17,439

17,439

17,439

17,439

17,439

               500223100298. Provide Corridor Access Requests

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

               500223100435. Christmas/New Year Road Closures

7,439

7,439

7,439

7,439

7,439

7,439

7,439

7,439

7,439

7,439

               500223100728. Corridor Access Requests UFB

140,000

100,000

100,000

0

0

0

0

0

0

0

          Base Maintenance

898,105

888,356

893,637

898,952

904,298

909,675

915,086

920,528

926,004

931,511

               50022010. Road & Footpath Maintenance

273,000

274,638

276,286

277,944

279,611

281,289

282,977

284,674

286,383

288,101

               500220100409. Street and Sump Cleaning

177,000

178,374

179,756

181,147

182,546

183,953

185,369

186,793

188,226

189,667

               500220100448. Mtce: Rocks Rd Bollards

30,000

30,000

30,000

30,000

30,000

30,000

30,000

30,000

30,000

30,000

               500220100622. Artwork Maintenance

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

               50022016. Street Tree Maintenance

150,000

150,900

151,805

152,716

153,633

154,554

155,482

156,415

157,353

158,297

               500220160410. Street Garden Maintenance

223,105

224,444

225,790

227,145

228,508

229,879

231,258

232,646

234,042

235,446

               50022017. After Hours Duty Officer

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

               50022041. Footpath Maintenance

15,000

0

0

0

0

0

0

0

0

0

          Base General Operating Expense

60,882

60,882

60,882

60,882

60,882

60,882

60,882

60,882

60,882

60,882

               50022617. Electricity Non Sub

12,567

12,567

12,567

12,567

12,567

12,567

12,567

12,567

12,567

12,567

               500226200685. Rental: Maitai / Wakatu

6,667

6,667

6,667

6,667

6,667

6,667

6,667

6,667

6,667

6,667

               50022621. Rates

5,965

5,965

5,965

5,965

5,965

5,965

5,965

5,965

5,965

5,965

               50022625. Streetgarden water

8,223

8,223

8,223

8,223

8,223

8,223

8,223

8,223

8,223

8,223

               50022637. Insurance

20,460

20,460

20,460

20,460

20,460

20,460

20,460

20,460

20,460

20,460

               500226450692. Temporary Road closure expense

7,000

7,000

7,000

7,000

7,000

7,000

7,000

7,000

7,000

7,000

          Base Consultants

48,500

48,500

48,500

48,500

48,500

48,500

48,500

48,500

48,500

48,500

               50022710. Legal Fees

40,000

40,000

40,000

40,000

40,000

40,000

40,000

40,000

40,000

40,000

               50022720. Valuation Fees

8,500

8,500

8,500

8,500

8,500

8,500

8,500

8,500

8,500

8,500

     Unprogrammed Expenses

200,000

0

0

0

0

0

0

0

0

0

          Unprogrammed Maintenance

200,000

0

0

0

0

0

0

0

0

0

               500230911996. Emergency 2011 Response

200,000

0

0

0

0

0

0

0

0

0

     Programmed Expenses

318,000

158,000

158,000

58,000

58,000

58,000

58,000

58,000

58,000

58,000

          Programmed Service Provision

260,000

100,000

100,000

0

0

0

0

0

0

0

               500243222515. Southern Arterial Corridor Management Plan

50,000

0

0

0

0

0

0

0

0

0

               50024372. Prelim Capex - investigation, options, testing

10,000

0

0

0

0

0

0

0

0

0

               500243722936. Atawhai Hills Traffic Study

0

100,000

0

0

0

0

0

0

0

0

               500243722937. CBD West traffic study

0

0

100,000

0

0

0

0

0

0

0

               500243722939. Stoke Foothills Traffic Study

100,000

0

0

0

0

0

0

0

0

0

               500243722946. Railway Reserve Lighting feasibility

20,000

0

0

0

0

0

0

0

0

0

               500243722996. Stoke CBD study

80,000

0

0

0

0

0

0

0

0

0

          Programmed Maintenance

58,000

58,000

58,000

58,000

58,000

58,000

58,000

58,000

58,000

58,000

               50024041. Pest Control on Road Reserve

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

10,000

               500240701078. Replacement Planting

48,000

48,000

48,000

48,000

48,000

48,000

48,000

48,000

48,000

48,000

     Renewals

310,551

312,552

314,582

316,643

318,744

320,882

323,048

325,111

327,243

329,567

          Renewals General

5,551

5,752

5,971

6,211

6,479

6,773

7,085

7,282

7,537

7,973

               50027150. Renewals: Street/Garden Furniture

5,551

5,752

5,971

6,211

6,479

6,773

7,085

7,282

7,537

7,973

          Renewals: Infrastructure

305,000

306,800

308,611

310,432

312,265

314,109

315,963

317,829

319,706

321,594

               500273701504. Renewals: Street Lights on walkways

5,000

5,000

5,000

5,000

5,000

5,000

5,000

5,000

5,000

5,000

               500273751494. Renewals: Footpaths

300,000

301,800

303,611

305,432

307,265

309,109

310,963

312,829

314,706

316,594

     Capital Growth

700,000

100,000

175,000

100,000

100,000

100,000

250,000

620,000

2,675,000

1,300,000

          Capital Growth

100,000

100,000

100,000

100,000

100,000

100,000

100,000

100,000

100,000

100,000

               50027410. Sundry Land Purchases - Growth

100,000

100,000

100,000

100,000

100,000

100,000

100,000

100,000

100,000

100,000

          Capital Growth: Infrastructure

600,000

0

75,000

0

0

0

150,000

520,000

2,575,000

1,200,000

               500276551375. Marsden Valley Ridgeway Upgrade

0

0

75,000

0

0

0

120,000

400,000

1,600,000

0

               500276552193. Todd Bush Rd

600,000

0

0

0

0

0

0

0

0

0

               500276552200. Marsden Valley Road Upgrade

0

0

0

0

0

0

0

50,000

75,000

1,200,000

               500276552933. Main Rd Stoke/Marsden Rd

0

0

0

0

0

0

30,000

70,000

900,000

0

     Capital Increased LOS

677,000

837,000

3,217,000

337,000

557,000

1,457,000

807,000

307,000

307,000

307,000

          Capital Increased LOS

97,000

97,000

107,000

107,000

107,000

107,000

107,000

107,000

107,000

107,000

               50027710. Land Purchase - LOS

50,000

50,000

50,000

50,000

50,000

50,000

50,000

50,000

50,000

50,000

               500277701076. Road Frontage Planting Program

25,000

25,000

35,000

35,000

35,000

35,000

35,000

35,000

35,000

35,000

               500277701078. Street Garden Dev

7,000

7,000

7,000

7,000

7,000

7,000

7,000

7,000

7,000

7,000

               500277701079. Street Tree Dev

15,000

15,000

15,000

15,000

15,000

15,000

15,000

15,000

15,000

15,000

          Capital Increased LOS: Infrastructure

530,000

590,000

3,110,000

230,000

450,000

1,350,000

700,000

200,000

200,000

200,000

               500279552058. Tasman St (Nile to Bronte)

70,000

0

0

0

0

0

0

0

0

0

               500279552074. Milton St (Grove to Cambria)

0

0

0

0

20,000

500,000

500,000

0

0

0

               500279552075. Halifax (Maitai to Milton)

10,000

50,000

600,000

0

0

0

0

0

0

0

               500279552193. Todd Bush Rd

10,000

0

0

0

0

0

0

0

0

0

               500279552947. Muritai SH6 intersection (incl Ped crossing across SH6)

0

40,000

0

0

160,000

0

0

0

0

0

               500279553009. Toi Toi/Vanguard intersection upgrade

0

0

0

15,000

35,000

250,000

0

0

0

0

               500279553010. Toi Toi St upgrade

0

0

0

15,000

35,000

400,000

0

0

0

0

               500279752798. New Footpaths

50,000

200,000

200,000

200,000

200,000

200,000

200,000

200,000

200,000

200,000

               500279802213. Rocks Rd cycling and walking project

390,000

300,000

2,310,000

0

0

0

0

0

0

0

          Capital LOS: Other Property Improvements

50,000

150,000

0

0

0

0

0

0

0

0

               500278552948. Tahunanui car park

50,000

150,000

0

0

0

0

0

0

0

0

5505 Parking Regulation

570,192

570,192

570,192

570,192

570,192

570,192

570,192

570,192

570,192

570,192

     Base  Expenditure

570,192

570,192

570,192

570,192

570,192

570,192

570,192

570,192

570,192

570,192

          Base Service Provision Council Wide

560,692

560,692

560,692

560,692

560,692

560,692

560,692

560,692

560,692

560,692

               55052310. Providing Parking Reg Service

37,000

37,000

37,000

37,000

37,000

37,000

37,000

37,000

37,000

37,000

               550523100453. Vehicle Identification Fee/MOT

500

500

500

500

500

500

500

500

500

500

               550523100454. Court Processing

115,000

115,000

115,000

115,000

115,000

115,000

115,000

115,000

115,000

115,000

               550523100700. Providing service - EIL contract

408,192

408,192

408,192

408,192

408,192

408,192

408,192

408,192

408,192

408,192

          Base General Operating Expense

9,500

9,500

9,500

9,500

9,500

9,500

9,500

9,500

9,500

9,500

               55052650. Flea Market Towing

9,500

9,500

9,500

9,500

9,500

9,500

9,500

9,500

9,500

9,500

5510 Car Parking

2,373,498

2,248,821

2,682,191

2,688,510

2,294,160

1,801,537

1,858,932

1,971,340

1,808,762

1,846,200

     Base  Expenditure

1,741,130

1,743,453

1,745,791

1,748,142

1,763,792

1,766,169

1,768,564

1,770,972

1,773,394

1,775,832

          Base Service Provision Council Wide

211,934

212,099

212,265

212,432

212,600

212,769

212,939

213,110

213,282

213,455

               55102310. Provide: CBD Professional Serv

27,500

27,665

27,831

27,998

28,166

28,335

28,505

28,676

28,848

29,021

               551023100701. Provide: CCTV Operation

43,000

43,000

43,000

43,000

43,000

43,000

43,000

43,000

43,000

43,000

               55102342. Provide CBD Coordinator

141,434

141,434

141,434

141,434

141,434

141,434

141,434

141,434

141,434

141,434

          Base Maintenance

653,262

655,420

657,592

659,776

661,974

664,184

666,409

668,646

670,896

673,161

               551020100414. Mtce: Off Street Parking Meters

63,528

63,528

63,528

63,528

63,528

63,528

63,528

63,528

63,528

63,528

               551020100415. Mtce: On Street Parking Meters

130,000

130,000

130,000

130,000

130,000

130,000

130,000

130,000

130,000

130,000

               551020100457. Mtce: CBD Street Sweeping

95,000

95,570

96,143

96,720

97,301

97,884

98,472

99,063

99,657

100,255

               551020100458. Clean Asphalt Footpaths

137,000

137,822

138,649

139,481

140,318

141,160

142,007

142,859

143,716

144,578

               55102016. Mtce: Street Gardens

8,000

8,048

8,096

8,145

8,194

8,243

8,292

8,342

8,392

8,443

               551020160410. Mtce: Street Trees

20,000

20,120

20,241

20,362

20,484

20,607

20,731

20,855

20,980

21,106

               551020160416. Mtce: Blockwork Maintenance

80,000

80,480

80,963

81,449

81,937

82,429

82,924

83,421

83,922

84,425

               551020160417. Mtce: Carpark Maintenance

19,734

19,852

19,972

20,091

20,212

20,333

20,455

20,578

20,701

20,826

               551020161267. Hanging Baskets

80,000

80,000

80,000

80,000

80,000

80,000

80,000

80,000

80,000

80,000

               55102029. Mtce: CBD Seat Cleaning

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

20,000

          Base General Operating Expense

866,549

866,549

866,549

866,549

879,833

879,831

879,831

879,831

879,831

879,831

               55102608. CBD Wifi

44,000

44,000

44,000

44,000

44,000

44,000

44,000

44,000

44,000

44,000

               55102617. Electricity car parks

16,120

16,120

16,120

16,120

16,120

16,120

16,120

16,120

16,120

16,120

               55102620. Rent (Wakatu Leases)

201,274

201,274

201,274

201,274

201,274

201,274

201,274

201,274

201,274

201,274

               55102621. Rates

377,931

377,931

377,931

377,931

377,931

377,931

377,931

377,931

377,931

377,931

               55102625. Water By Meter

1,316

1,316

1,316

1,316

1,316

1,316

1,316

1,316

1,316

1,316

               55102627. Mtce: CBD Litter Collection

26,566

26,566

26,566

26,566

29,223

29,222

29,222

29,222

29,222

29,222

               551026270800. CBD rubbish bin collection

158,265

158,265

158,265

158,265

168,892

168,891

168,891

168,891

168,891

168,891

               55102637. Insurance

1,077

1,077

1,077

1,077

1,077

1,077

1,077

1,077

1,077

1,077

               55102650. Security / Cash Collections

40,000

40,000

40,000

40,000

40,000

40,000

40,000

40,000

40,000

40,000

          Base Consultants

9,385

9,385

9,385

9,385

9,385

9,385

9,385

9,385

9,385

9,385

               55102710. Legal Fees

5,000

5,000

5,000

5,000

5,000

5,000

5,000

5,000

5,000

5,000

               55102720. Valuations

4,385

4,385

4,385

4,385

4,385

4,385

4,385

4,385

4,385

4,385

     Programmed Expenses

115,000

10,000

15,000

50,000

10,000

15,000

70,000

90,000

15,000

50,000

          Programmed Service Provision

65,000

0

5,000

0

0

5,000

0

0

5,000

0

               55104312. Grant: Christmas Tree Decorations

0

0

5,000

0

0

5,000

0

0

5,000

0

               551043120707. Grant: Bank Lane Canopy

65,000

0

0

0

0

0

0

0

0

0

          Programmed Consultants

50,000

10,000

10,000

50,000

10,000

10,000

70,000

90,000

10,000

50,000

               551047302518. Parking Strategy

0

0

0

0

0

0

20,000

80,000

0

0

               55104760. Parking Surveys

50,000

10,000

10,000

50,000

10,000

10,000

50,000

10,000

10,000

50,000

     Renewals

290,368

140,368

671,400

490,368

20,368

20,368

20,368

110,368

20,368

20,368

          Renewals General

0

0

560,000

470,000

0

0

0

90,000

0

0

               551071401484. Renewals: On and Off St Parking Meter

0

0

470,000

470,000

0

0

0

0

0

0

               551071402942. Renewal: CCTV

0

0

90,000

0

0

0

0

90,000

0

0

          Renewals: Other Property Improvements

290,368

140,368

111,400

20,368

20,368

20,368

20,368

20,368

20,368

20,368

               551072252207. Renewal CBD Rubbish Bins

5,368

5,368

96,400

5,368

5,368

5,368

5,368

5,368

5,368

5,368

               551072552518. Parking Strategy implementation unspecified

270,000

120,000

0

0

0

0

0

0

0

0

               551072552943. Carpark Street Light Renewal

15,000

15,000

15,000

15,000

15,000

15,000

15,000

15,000

15,000

15,000

     Capital Increased LOS

227,000

355,000

250,000

400,000

500,000

0

0

0

0

0

          Capital Increased LOS: Infrastructure

227,000

355,000

250,000

400,000

500,000

0

0

0

0

0

               551079551840. Capital: Bridge St enhancement

132,000

0

0

0

0

0

0

0

0

0

               551079552994. Strawbridge Sq Layout & access improvement

45,000

15,000

0

0

0

0

0

0

0

0

               551079552995. Putaitai St/ Main Rd Stoke Right turn

0

40,000

0

0

0

0

0

0

0

0

               551079553000. CBD Enhancements

50,000

250,000

250,000

300,000

0

0

0

0

0

0

               551079752984. Stoke CBD enhancements

0

50,000

0

100,000

500,000

0

0

0

0

0

5560 Public Transport

991,821

1,063,293

976,902

1,048,340

1,408,879

1,250,052

1,061,898

1,074,449

1,087,759

1,151,865

     Base  Expenditure

922,473

931,424

940,872

992,310

1,002,850

1,014,022

1,025,868

1,038,419

1,051,729

1,065,835

          Base Service Provision Council Wide

877,473

886,378

895,850

947,310

957,850

969,022

980,868

993,419

1,006,729

1,020,835

               556023100391. Bus Services: 511 Subsidised

538,973

539,018

539,047

520,635

520,635

520,634

520,636

520,634

520,636

520,637

               556023102321. WC 514 Public Transport Facilities Ops

20,000

20,031

20,031

80,000

80,000

80,000

80,000

80,000

80,000

80,000

               556023102335. PT Minor Improvements Opex

171,000

171,000

171,000

171,000

171,000

171,000

171,000

171,000

171,000

171,000

               55602322. WC 522 SuperGold Card Concessions

147,500

156,329

165,772

175,675

186,215

197,388

209,232

221,785

235,093

249,198

          Base General Operating Expense

45,000

45,046

45,022

45,000

45,000

45,000

45,000

45,000

45,000

45,000

               556026452321. WC 524 PT Info Supply

45,000

45,046

45,022

45,000

45,000

45,000

45,000

45,000

45,000

45,000

     Programmed Expenses

0

0

0

0

50,000

0

0

0

0

50,000

          Programmed Service Provision

0

0

0

0

50,000

0

0

0

0

50,000

               556043222510. Passenger Transport service review

0

0

0

0

50,000

0

0

0

0

50,000

     Capital Growth

33,318

95,839

0

20,000

320,000

200,000

0

0

0

0

          Capital Growth: Other Property Improvements

33,318

95,839

0

20,000

320,000

200,000

0

0

0

0

               556075902218. Stoke interchange (WC531)

0

0

0

20,000

300,000

0

0

0

0

0

               556075902945. Integrated Ticketing (WC531)

33,318

95,839

0

0

0

0

0

0

0

0

               556075902997. CBD interchange

0

0

0

0

20,000

200,000

0

0

0

0

     Capital Increased LOS

36,030

36,030

36,030

36,030

36,029

36,030

36,030

36,030

36,030

36,030

          Capital Increased LOS: Infrastructure

36,030

36,030

36,030

36,030

36,029

36,030

36,030

36,030

36,030

36,030

               556079902335. PT Minor Improvements

36,030

36,030

36,030

36,030

36,029

36,030

36,030

36,030

36,030

36,030

5570 Total Mobility

380,236

359,935

400,998

399,770

420,794

500,425

461,469

480,512

500,481

517,142

     Base  Expenditure

380,236

359,935

400,998

399,770

420,794

500,425

461,469

480,512

500,481

517,142

          Base Service Provision Council Wide

380,236

359,935

400,998

399,770

420,794

500,425

461,469

480,512

500,481

517,142

               557023100460. WC 517 Total Mobility Operations

274,736

290,260

306,718

321,760

338,103

352,773

368,557

382,026

396,086

406,483

               557023220455. Wheelchair replacement 519

40,000

0

20,011

0

0

60,000

0

0

0

0

               557023220801. Wheelchair hoist use (WC521)

65,500

69,675

74,269

78,010

82,691

87,652

92,912

98,486

104,395

110,659

 

 

 

 

 

 


Appendix M          minor improvement and footpaths Priority List

Minor Improvements Projects

Original description

Road

Location

Comments

Construction estimate

Maori Road retaining wall

Maori Road

Retaining wall is failing and needs immediate attention.

$300,000

Homezone Area project

Prioritised based on Homezone spreadsheet.

$100,000pa

Waimea Road/The Ridgeway - Safety improvements

Waimea Road/The Ridgeway

Intersection of Waimea Road and The Ridgeway

Tighten the radius of the kerb for vehicles turning left into The Ridgeway to reduce speeds. Relies on the speed limit being reduced to 50km/h on Waimea Road.

$200,000

Poleford Bridge Seismic Upgrade

Maitai Valley Road

Poleford Bridge

Life Line route to water supply with bridge with poor seismic and HPMV capacity

$35,000

Gibbs Bridge Seismic Upgrade

Maitai Valley Road

Gibbs Bridge

Life Line route to water supply with bridge with poor seismic and HPMV capacity

$60,000

Airport Bridge Replacement

Coastal Shared Path

Existing bridge reached end of serviceable life. Piles and main span decayed

$230,000

Neale Ave - Parking and safety improvements

Neale Avenue

Neale Ave adjacent to Neale Park

Parents park on Neale Ave at the back of Nayland School to pick up and drop off children, but speeding vehicles. Angle parking and traffic calming on the approaches are options.

$50,000

Atawhai Crescent - Bus stop relocation

Atawhai Crescent

Atawhai Crescent and intersections with Dodson Valley Road and Rainbow Drive

Bus stop has been relocated but pedestrian refuge/build outs still need to be designed and constructed to allow safer pedestrian access from all footpath approaches.

$50,000

Toi Toi Street/St Vincent Street safety improvements

Toi Toi Street/St Vincent Street intersection

Toi Toi Street/St Vincent Street intersection

High number of crashes at this intersection. Partially due to unbalanced sight distances. Need to improve pedestrian safety so allow for raised pedestrian tables on all four approaches.

$300,000

Wigzell Area wide traffic calming

Kawai Street South

All of Kawai Street South

re Neighbourhood Support letter, investigate. Has been transferred to Homezone/shared zone/traffic calming programme for area wide treatment.

$300,000

Alton St - Streetlights

Alton Street

Alton Street for 100m south of Hardy Street adjacent to planted central median

Very dark in places. Ped safety issue

$20,000

Strawbridge Square Car Park- Footpath narrowing

Strawbridge Carpark

Driveway from Songer Street is very narrow. Cost depends on solution chosen. At lower end remarking and signing the driveway for exit only would solve the issue.

$50,000

Polstead Rd - Pedestrian refuge

Polstead Road

Polstead Road/Nikau Street Intersection

By the shops. Safe Journey to School, project in 2011/12. Couldn't get agreement to project.

$70,000

Grove St

Grove Street

Between Collingwood Street and Tasman Street

Long straight section with few cars parked encourages higher speeds. Kindergarten on this section. Allows for build-outs or chicane.

$20,000

State Highway 6 Pedestrian Crossing - Muritai Street

State Highway 6

North of Muritai Street

Difficult to for pedestrians to cross without a walking to the traffic signals. Central pedestrian refuge and kerb build-outs proposed.

$200,000

Trafalgar St South - Footpath and kerb repairs

Trafalgar Street South

Trafalgar Street South adjacent to Nelson Girls High

Safety improvements - fix footpath / low kerb by roundabout. Need to lift f/p and retain etc -cycle accident 3/09

$90,000

The Ridgeway/Arapiki Road - Pedestrian safety improvements

The Ridgeway/Arapiki Road

Intersection of Arapiki Road and The Ridgway

Children coming down Arapiki to cross Ridgeway have poor sightlines to north. Tighten left turn radius, construct pedestrian build-outs.

$50,000

Marsden Valley/The Ridgeway Intersection Upgrade

Marsden Valley/The Ridgeway intersection

Marsden Valley/The Ridgeway intersection

Sight distances are inadequate in at this intersection. Allows for minor kerb changes and calming to reduce speeds to match visibility.

$75,000

Vanguard Street - Right-turn bay safety improvements

Vanguard Street

Vanguard Street between Toi Toi Street and North Esk Street

Improve safety at the Vanguard / Toitoi intersection. The safety record of this intersection has improved since the change in give way rule so uncertain whether any further work is necessary.

$300,000

Quebec Rd - Speed reduction

Quebec Road

Quebec Road for 600m east of Prince Drive

Traffic calming required along straight connecting to Princes Dr. Straight section is out of character with the remainder of Quebec Road. Traffic calming will reduce speeds on this section to be similar to the rest of the route.

$50,000

Shakespeare Walk/Bridge

Shakespeare Walk

Pedestrian conflict - To be mitigated with pedestrian buildouts on both sides of the road.

$100,000

Karaka St - Traffic calming

Karaka Street

Karaka Street north of Orchard Street

Traffic calming by Council flats. Some has been done already but 200m between build-outs so an additional build-out needed.

$20,000

Examiner St - Speed humps

Examiner Street

Examiner Street 30m west of Trafalgar Street South

Speed humps too severe. They are likely to be achieving the objective of slowing vehicles down. The profile of the humps complies with the relevant design guidelines.

$10,000

Annesbrook Drive by Black Cat dairy with road remark

Annesbrook Drive

Opportunity to provide ped refuges adjacent to the Black Cat Dairy.

$100,000

Nile Street/Maitai Valley Road intersection upgrade

Nile Street/Maitai Valley Road intersection

Nile Street/Maitai Valley Road intersection

Poor safety record at this intersection caused by limited visibility and poor alignment. Allows for minor kerb changes and calming to reduce speeds and improve stop position.

$100,000

Arrow St/Quebec St intersection - Safety improvements

Arrow Street/Quebec Road

Intersection of Arrow Street and Quebec Road

Small flush roundabout to allow for safer right turn movements from down hill approach of Arrow Street.

$30,000

Vanguard St - Protection of shared path from parked cars

Vanguard Street

Need some sort of protection to prevent vehicles parking on Shared path. This is an enforcement issue.

$70,000

Stafford Ave/Annesbrook Drive one way section

Stafford Avenue

AJ worked with residents to agree a plan in 2012. Allows for minor changes to marking and islands to make turning in difficult from Main Road Stoke.

$30,000

Marybank Road - Roundabout improvements

Marybank Road

Intersection of Marybank Road and Noel Jones Drive

WALTER Ingram S/R 108823 (Larger trucks will struggle to track through intersection but this is uncommon and only really during construction. Tresillian Ave will be connected through in the next couple of years so an alternative route will be available.)

$30,000

Near misses with cyclists driving out of Marsden Cemetery

Marsden Valley Road

Conflict between cyclists on path and cars exiting cemetery driveway. Road marking and signage to inform drivers of cycle activity.

$50,000

 

NETWORK DEFICIENCIES - FOOTPATHS

Original description

Road/Walkway Name

Location

Notes

Construction estimate

Footpath in front of 413 Waimea Road

Waimea Road

Between Chings Road and The Ridgeway - South side

Evidence of high use by school children.

 $   33,750.00

Songer Street footpath, south side west of Nayland Rd 360m

Songer Street

Between Nayland Road and Durham Street - South side

Some levels issues, driveway, gardens on road reserve.

 $   85,500.00

Bronte Street footpath behind St Joseph's

Bronte Street

Between Scotland Street and Collingwood Street

No footpath along the back of St Josephs School. Trees and bank make construction more expensive.

 $   72,000.00

Centennial Road footpath

Centennial Road

Full length on south side.

Gap in footpath on south side, popular with school children.

 $   45,000.00

Kea Street footpath

Kea Street

Full length on north side.

Tracks on grass show desire lines, crossings at intersection with Kaka St lead you nowhere, just into middle of intersection

 $   29,250.00

Nikau Street footpath

Nikau Street

Full length on south side.

Full length to provide higher level of service for pedestrians accessing back of school in particular.

 $   69,750.00

Palm Avenue footpath

Palm Avenue

Between Nikau Street and Apple Lane.

 $   20,250.00

Manson Avenue footpath

Manson Avenue

Full length. Close to school.

 $  110,250.00

Stanley Crescent footpath

Stanley Crescent

From Beachville Crescent to end - South side

Some visibility issues over crests.

 $  108,000.00

Emano Street footpath (Lower section)

Emano Street

Piko Street to Orsman Crescent

Footpath on one side only. High proportion of children in the area walk to school.

 $  222,000.00

Emano Street (Upper section)

Emano Street

Orsman Crescent to end

No footpath. Part of walkway to the top of port hills.

 $  192,000.00

Arapiki Road footpath

Arapiki Road

South side west of crest

80m of footpath between No 24 and 32, south side to improve schoolchildren visibility to cross Arapiki Rd, avoids crossing at toe of hill(poor visibility) or at Ridgeway/Arapiki.

 $   64,000.00

Scotia Street footpath

Scotia Street

Anglia Street to 140m north

Visibility around corner difficult, new house on corner will complicate lack of footpath.

 $  168,000.00

Maire Street Footpath

Marie Street

50m at end

Involves sale of land. Links end of existing footpath to walkway at end of road.

 $   40,000.00

Maitai Path

Maitai Path

Adjacent to Whakatu land

Length of Maitai path to be upgraded once Whakatu redevelop the site at 16 Paru Paru Road. Agreements in place to allow widening once they establish café outdoor area on neighbouring park.

 $   35,000.00

Brougham Street footpath

Brougham Street

East of Collingwood Street

Footpath is missing on southern side. Very difficult to construct as all driveways would need to be regraded for a long way back into properties. No opportunity to join to the Scotland Street footpath as road gets too close to boundary.

 $  300,000.00

Dodson Valley Road footpath

Dodson Valley Road

South side between Winton Place and Atawhai Crescent

Hill in the way. Not feasible to provide footpath on this side of the road and still provide access to properties. Have added pedestrian build-outs to minor improvements list instead.

 $  372,000.00

Bledisloe Avenue footpath

Bledisloe Avenue

In front of numbers 2-16

Missing section in front of 2-16 leads to Bledisloe Reserve.

 $   29,250.00

Reeves Street footpath

Reeves Street

West side for 70 m north of Aldinga Avenue

Restricted visibility when crossing at end of footpath on north side.

 $   35,000.00

Montreal Road footpath

Montreal Road

South of Toi Toi Street

Footpath on one side only.

 $  252,000.00

Joyce Place footpath

Joyce Place

Full length

Footpath on one side only. Is a new subdivision and in a short cul-de-sac so not a priority.

 $   36,000.00

Washington Road footpath

Washington Road

East of Brittania Heights intersection

No footpath on residential side of road, 4 houses affected, steep bank and tight road alignment. Children have to cross road to reach footpath at bottom of bank. No feasible option for providing a footpath on the west side of the road and still being able to provide vehicle access to the properties affected.

 $  192,000.00

Rangiora Terrace footpath

Rangiora Terrace

Between end of existing footpath and Tamaki Steps

Rough surface from base of steps onto existing footpath, No footpath around Rangiora Tce intersection and over rise towards sea. Too dangerous and have to cross road. Rangiora Tce upgrade no longer in AMP. Rough surface to be dealt with by maintenance.

 $   12,000.00

The Ridgeway footpath

The Ridgeway

From Somerset Tce towards Kauri St on the east side

Footpath is in poor repair, when repaired can it be moved 1 metre back from traffic lanes, peds are very close to moving traffic lanes.

 $  210,000.00

Jellicoe Ave footpath

Jellicoe Avenue

Bledsloe Ave to Railway Reserve

Well worn path from Bledsloe Ave to Railway Reserve.

 $   27,000.00

Airlie Street footpath

Airlie Street

Full length

No footpath.

 $  336,000.00

Bridge on approach to the Airport/Quarantine Rd

Quarantine Road

Bridge on approach to Quarantine Rd/Bolt Rd roundabout on Quarantine has no footpath on south side. Some pedestrians to airport and general walkers.

 $  200,000.00

Douglas Rd to Observatory Hill walkway

Off Road

Off Road

Off road recreational route. Needs to be part of any development of the land above Douglas Road. Over private property.

 $  600,000.00

Observatory Hill to Emano St walkway

Off Road

Off Road

Off road recreational route. Needs to be part of any development of the land above Emano Street. Over private property.

 $  270,000.00

Stanley Crescent to Washington Rd walkway

Off Road

Off Road

Off road recreational and transport route. Over private property.

 $  240,000.00


Appendix N          Footpath Rehabilitation Sites

Proposed Footpath Rehabilitation sites - Draft Treatment Selection 2015/2018

 

Road Name

Start

End

Carriageway Start Name

Carriageway End Name

Side

Length

Year 1

 

 

 

 

 

 

BRIDGE STREET

7

48

RUTHERFORD STREET

TRAFALGAR STREET

LEFT

41

TASMAN STREET SOUTH

36

134

BRIDGE STREET

HARDY STREET

LEFT

98

NILE STREET EAST

SUSSEX STREET

COLLINGWOOD STREET

LEFT

80

TIPAHI STREET

470

500

FRANKLYN STREET

MOTUEKA STREET

LEFT

30

MARSDEN VALLEY ROAD

10

400

MAIN ROAD STOKE

TAUPATA STREET

LEFT

390

ANNESBROOK DRIVE

NO. 312 ANNESBROOK DRIVE

QUARANTINE ROAD

RIGHT

50

UFB COST SHARE SITES

VARIOUS

YEAR 2

 

 

 

 

 

 

MAIN ROAD STOKE

316

336

LOUISSON AVENUE

MAITLAND AVENUE

Left

20

MAIN ROAD STOKE

715

895

MARSDEN ROAD

ROAD WIDENS

Left

180

MOTUEKA STREET

287

297

TIPAHI STREET

WAIMEA ROAD

Right

10

VICKERMAN STREET

141

153

HAVEN RD

WILDMAN AVE

Right

12

WILDMAN AVENUE (EASTBOUND)

353

373

VICKERMAN STREET

LOW STREET

Right

20

BRIDGE STREET

863

873

HARLEY STREET

TASMAN ST BRIDGE

Right

10

BRIDGE STREET

262

505

TRAFALGAR ST

COLLINGWOOD STREET

Right

243

BRIDGE STREET

262

502

TRAFALGAR ST

COLLINGWOOD STREET

Left

240

CAR PARK MONTGOMERY SQUARE

286

359

ACCESS NW CORNER BY ROLLOS

RUTHERFORD ST KERB LINE

Left

73

CAR PARK MONTGOMERY SQUARE

50

168

EAST SIDE OF CARPARK (WHITCOULLS)

WEST SIDE OF CARPARK (RSA)

Right

118

CAR PARK MONTGOMERY SQUARE

168

286

WEST SIDE OF CARPARK (RSA)

WEST SDIE OF NOTHERN HALF CARPARK

Right

118

COLLINGWOOD STREET

1342

1407

NILE STREET

BRONTE STREET

Left

65

DURHAM STREET

5

100

SONGER ST

RUTLAND ST

Left

95

EXAMINER STREET

350

371

RUTHERFORD STREET

TRAFALGAR STREET

Left

21

EXAMINER STREET

176

225

RUTHERFORD STREET

TRAFALGAR STREET

Right

49

FRANKLYN STREET

300

320

TIPAHI ST

KAWAI ST

Left

20

FRANKLYN STREET

552

622

WAIMEA RD

END AT JUDDER BAR

Right

70

HALIFAX STREET

213

310

RUTHERFORD ST

TRAFALGAR ST

Left

97

YEAR 3

 

 

 

 

 

 

HALSTEAD STREET

7

42

HALIFAX ST

NEW ST

Left

35

HAVEN ROAD (ARTERIAL, NORTHBOUND)

194

264

HALIFAX STREET

QUEEN ELIZABETH II DRIVE

Left

70

HAVEN ROAD (ARTERIAL, NORTHBOUND)

72

177

HALIFAX STREET

QUEEN ELIZABETH II DRIVE

Left

105

HAVEN ROAD (ARTERIAL, NORTHBOUND)

267

391

HALIFAX STREET

QUEEN ELIZABETH II DRIVE

Left

124

MAIN ROAD STOKE

627

637

MAITLAND AVENUE

KEA STREET

Left

10

MAIN ROAD STOKE

637

681

KEA STREET

MARSDEN ROAD

Left

44

MAIN ROAD STOKE

1629

1688

LEMARI AVENUE

TAINUI STREET

Left

59

MAIN ROAD STOKE

1071

1170

PUTAITAI STREET

SONGER STREET

Left

99

MAIN ROAD STOKE

1509

1629

RANUI STREET

LEMARI AVENUE

Left

120

MAIN ROAD STOKE

4200

4505

ELMS STREET

SALISBURY ROAD

Left

305

SCOTLAND STREET

4

64

BRONTE STREET

SEYMOUR AVENUE

Right

60

SEAVIEW ROAD

176

186

ALLPORT PLACE

SEAVIEW LOOP ROAD

Left

10

SHELBOURNE STREET

98

112

NILE ST

EDUCATION BUILDING

Right

14

SONGER STREET

620

635

DERBY STREET

REEVES STREET

Left

15

SONGER STREET

410

435

SEAVIEW ROAD

DURHAM STREET

Left

25

THE RIDGEWAY (NORTH)

290

300

ROAD NARROWS

BAIGENT ROAD

Left

10

TRAFALGAR SQUARE (WEST SIDE)

87

97

ROAD NARROWS

NILE STREET WEST

Right

10

TRAFALGAR SQUARE (WEST SIDE)

55

68

ROAD NARROWS

NILE STREET WEST

Left

13

TRAFALGAR SQUARE (WEST SIDE)

108

312

NILE STREET WEST

TRAFALGAR STREET ROUNDABOUT (EXAMIN

Left

204

TRAFALGAR STREET (NORTH)

286

340

ROAD WIDENS

GROVE STREET

Left

54

TRAFALGAR STREET (NORTH)

759

814

HALIFAX STREET

BRIDGE ST

Right

55

TRAFALGAR STREET (NORTH)

726

814

HALIFAX STREET

BRIDGE ST

Left

88

YEAR 4 AND BEYOND

 

 

 

 

 

 

TRAFALGAR STREET (SOUTH)

219

246

ROAD WIDENS

BRONTE STREET (CENTRAL)

Left

27

TRAFALGAR STREET (SOUTH)

248

298

ROAD WIDENS

BRONTE STREET (CENTRAL)

Left

50

TRAFALGAR STREET (SOUTH)

162

217

ROAD WIDENS

BRONTE STREET (CENTRAL)

Left

55

TRAFALGAR STREET (SOUTH)

91

162

EXAMINER STREET

ROAD WIDENS

Left

71

VAN DIEMEN STREET

395

410

RUTHERFORD ST

TRAFALGAR ST

Right

15

VANGUARD STREET

29

39

RUTHERFORD STREET

HARDY STREET

Left

10

VANGUARD STREET

1987

2004

MOTUEKA STREET

END

Right

17

WAIMEA ROAD

1200

1215

FRANKLYN STREET

MOTUEKA STREET

Left

15

WAIMEA ROAD

478

490

VAN DIEMAN STREET

HAMPDEN STREET

Left

12

WAIMEA ROAD

4670

4708

QUARANTINE ROAD

ANNESBROOK DRIVE CENTRE ISLAND

Left

38

ANNESBROOK DRIVE

344

476

QUARANTINE ROAD EAST

MAPLE AVENUE

Left

132

BRONTE STREET (EAST)

0

63

CDS

BROOK ST

Left

63

CHAMBERLAIN STREET

207

219

RANGIORA

MAIRE ST

Right

12

CHAMBERLAIN STREET

109

152

TOSWILL ST

RANGIORA

Right

43

GREEN STREET

249

327

MURITAI ST

ROTO ST

Left

78

KONINI STREET

424

476

MOUNT ST

GLOUCESTER ST

Left

52

MAITLAND AVENUE

225

235

MAIN RD STOKE

KOROMIKO AVE

Right

10

MOTUEKA STREET

143

153

VANGUARD STREET

TIPAHI STREET

Right

10

MOTUEKA STREET

20

42

VANGUARD STREET

TIPAHI STREET

Right

22

NEALE AVENUE

95

115

BLEDISLOE AVE

KEA ST

Left

20

NGATITAMA STREET

35

45

RUTHERFORD ST

HAMPDEN ST

Right

10

NORTH ROAD

198

208

WEKA ST

START KERB LHS

Left

10

NORTH ROAD

453

463

START KERB LHS

END

Left

10

PARKERS ROAD

250

270

BULLEN STREET

MURITAI STREET

Left

20

PARKERS ROAD

850

930

OTTERSON STREET

GOLF ROAD

Left

80

PARKERS ROAD

725

806

PARKERS ROAD ROUNDABOUT (BOLT)

OTTERSON STREET

Left

81

QUARANTINE ROAD

505

515

BOLT ROAD

PASCOE STREET

Left

10

QUARANTINE ROAD

86

145

BOLT ROAD

PASCOE STREET

Left

59

SCOTLAND STREET

64

189

SEYMOUR AVENUE

BROUGHAM STREET

Right

125

SUFFOLK ROAD

490

502

KINGSFORD DRIVE

CLAIRMONT HEIGHTS

Left

12

SUFFOLK ROAD

815

957

KINGSFORD DRIVE

CLAIRMONT HEIGHTS

Left

142

THE RIDGEWAY (SOUTH)

520

560

KAURI STREET

SOMERSET TERRACE

Left

40

THE RIDGEWAY (SOUTH)

408

453

KAURI STREET

SOMERSET TERRACE

Left

45

THE RIDGEWAY (SOUTH)

620

680

KAURI STREET

SOMERSET TERRACE

Left

60

TRAFALGAR SQUARE (CUL DE SAC)

3

91

TRAFALGAR SQ (WEST SIDE)

END

Right

88

WAIMEA ROAD

4709

4784

QUARANTINE ROAD

ANNESBROOK DRIVE CENTRE ISLAND

Left

75

WASTNEY TERRACE

265

275

JACKSON ST

JOLLIE ST

Right

10

WESTBROOK TERRACE

56

218

SEYMOUR AVE

MIRO ST

Right

162

 

UFB YET TO BE INSTALLED *

BEACH ROAD

170

180

BISLEY WALK

WAIKARE STREET

Left

10

FRANKLYN STREET

40

68

VANGUARD ST

TIPAHI ST

Left

28

FRANKLYN STREET

110

130

VANGUARD ST

TIPAHI ST

Left

20

TUKUKA STREET

314

324

KAWAI ST

WAIMEA RD

Right

10

TUKUKA STREET

197

212

TIPAHI ST

KAWAI ST

Right

15

TUKUKA STREET

269

369

KAWAI ST

WAIMEA RD

Left

100

BAIGENT ROAD

50

120

THE RIDGEWAY

NEWMAN DR

Left

70

EMANO STREET

590

620

MURPHY ST

ORSMAN CRESENT

Left

30

JENNER ROAD

440

465

JENNER ROAD CUL-DE-SAC 1

JENNER ROAD CUL-DE-SAC 2

Left

25

JENNER ROAD

345

400

JENNER ROAD CUL-DE-SAC 1

JENNER ROAD CUL-DE-SAC 2

Left

55

KARAKA STREET

0

10

TITOKI ST

POLSTEAD RD

Right

10

KARAKA STREET

62

72

TITOKI ST

POLSTEAD RD

Right

10

KARAKA STREET

72

97

TITOKI ST

POLSTEAD RD

Left

25

MARSDEN ROAD

168

277

MAIN RD STOKE

THE RIDGEWAY

Left

109

MARSDEN ROAD

7

159

MAIN RD STOKE

THE RIDGEWAY

Left

152

NILE STREET (EAST)

1363

1383

MAITAI RD

CLEVELAND TCE

Right

20

SCOTIA STREET

815

825

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

10

SCOTIA STREET

884

895

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

11

SCOTIA STREET

775

790

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

15

SCOTIA STREET

260

290

BEATSON ROAD (NORTH END)

ULSTER STREET

Right

30

TOSSWILL ROAD

285

300

STATE HIGHWAY 6

CHAMBERLAIN STREET

Right

15

ALFRED STREET

220

230

VANGUARD STREET

TIPAHI STREET

Right

10

BEACH ROAD

365

385

BISLEY WALK

WAIKARE STREET

Left

20

COLLINGWOOD STREET

1535

1600

BRONTE STREET

BROUGHAM STREET

Left

65

MILTON STREET

380

464

GROVE ST

HALIFAX STREET EAST

Left

84

TIPAHI STREET

616

740

MOTUEKA ST

TUKUKA ST

Left

124

TUCKETT PLACE

6

95

WAIMEA RD

END

Left

89

TUKUKA STREET

0

20

START

TIPAHI ST

Right

20

TUKUKA STREET

0

50

START

TIPAHI ST

Left

50

WAIMEA ROAD

34

200

RUTHERFORD STREET

VAN DIEMAN STREET

Left

166

WAIMEA ROAD

345

395

RUTHERFORD STREET

VAN DIEMAN STREET

Left

50

WAIMEA ROAD

1950

1975

TUKUKA STREET

BOUNDARY ROAD

Left

25

WAIMEA ROAD

96

111

RUTHERFORD STREET

VAN DIEMAN STREET

Right

15

WAIMEA ROAD

1606

1625

TUKUKA STREET

BOUNDARY ROAD

Left

19

AKERSTEN STREET

218

228

WILDMAN AVENUE

MARINA CAR PARK

Left

10

ALFRED STREET

126

136

VANGUARD STREET

TIPAHI STREET

Right

10

ALFRED STREET

200

210

VANGUARD STREET

TIPAHI STREET

Right

10

ALFRED STREET

290

317

TIPAHI STREET

KAWAI STREET (NORTH)

Right

27

BISLEY AVENUE

580

630

CHAMPION TCE

MOANA AVE

Left

50

BOLT ROAD

310

345

PARKERS ROAD ROUNDABOUT (BOLT)

ROTHERHAM STREET

Left

35

BOUNDARY ROAD

6

116

WAIMEA RD

KAWAI ST SOUTH

Left

110

BROOK STREET

308

490

STORE

BLICK TERRACE

Left

182

JENNER ROAD

320

335

JENNER ROAD CUL-DE-SAC 1

JENNER ROAD CUL-DE-SAC 2

Left

15

JENNER ROAD

400

425

JENNER ROAD CUL-DE-SAC 1

JENNER ROAD CUL-DE-SAC 2

Left

25

JERNINGHAM STREET

0

112

TORLESSE ST

END

Left

112

KARAKA STREET

10

62

TITOKI ST

POLSTEAD RD

Right

52

KARAKA STREET

175

250

TITOKI ST

POLSTEAD RD

Right

75

KARAKA STREET

72

167

TITOKI ST

POLSTEAD RD

Right

95

KAWAI STREET (NORTH)

401

445

ALFRED ST

FRANKLYN ST

Left

44

KAWAI STREET (SOUTH)

667

690

TIPAHI ST

BOUNDRY RD

Left

23

KAWAI STREET (SOUTH)

160

200

MOTUEKA ST

TUKUKA ST

Left

40

KAWAI STREET (SOUTH)

615

664

TIPAHI ST

BOUNDRY RD

Left

49

MARSDEN ROAD

360

396

MAIN RD STOKE

THE RIDGEWAY

Left

36

MOANA AVENUE

185

205

BISLEY AVENUE

CENTRE MOANA AVENUE ROUNDABOUT (STA

Right

20

MOANA AVENUE

679

830

MONCRIEFF AVENUE (PAINTED CENTRELIN

PRINCES DRIVE ROUNDABOUT (MOANA)

Left

151

MURPHY STREET

190

202

EMANO ST

JENNER ROAD

Right

12

NILE STREET (EAST)

740

816

TASMAN ST

DOMETT ST

Left

76

NILE STREET (EAST)

1210

1258

DOMETT ST

MAITAI  RD

Left

48

PRINCES DRIVE

970

990

MOANA ROAD

ROAD NARROWS

Left

20

SCOTIA STREET

170

182

BEATSON ROAD (NORTH END)

ULSTER STREET

Right

12

SCOTIA STREET

729

749

ROAD NARROWS

ANGLIA STREET

Right

20

SCOTIA STREET

754

775

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

21

SCOTIA STREET

790

815

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

25

SCOTIA STREET

825

850

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

25

SCOTIA STREET

851

884

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

33

SCOTIA STREET

895

947

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Left

52

SCOTIA STREET

749

948

ANGLIA STREET

BEATSON ROAD (SOUTH END)

Right

199

STANSELL AVENUE

240

270

PADDYS KNOB ACCESS

CHANGE IN CARRIAGEWAY WIDTH

Right

30

STANSELL AVENUE

360

390

CHANGE IN CARRIAGEWAY WIDTH

TOSSWILL ROAD

Right

30

THE RIDGEWAY (NORTH)

981

1017

ARAPIKI ROAD

MARSDEN ROAD

Left

36

TIPAHI STREET

937

947

TUKUKA ST

KAWAI ST

Left

10

TORLESSE STREET

4

165

WATERHOUSE ST

START ONE WAY

Left

161

WAIMEA ROAD

3993

4083

BEATSONS ROAD (SOUTH END)

WATERHOUSE STREET

Left

90

WAIMEA ROAD

3898

3991

BEATSONS ROAD (SOUTH END)

WATERHOUSE STREET

Left

93

WASHINGTON ROAD

470

600

HASTINGS ST

PRINCES DR

Left

130

WATERHOUSE STREET

6

50

WAIMEA RD

COSTER

Right

44

WATERHOUSE STREET

6

111

WAIMEA RD

COSTER

Left

105

WESTBROOK TERRACE

265

325

MIRO ST

HINAU ST

Right

60

* Priority shown indicates the current condition of the footpath, however UFB schedule may be different.

                       



[1]  Specific, Measurable, Achievable, Realistic, Time bound

[2] Road roughness is measured by a system developed by the former National Association of Australian State Roading Authorities. Values are obtained by a special-purpose vehicle travelling down both outside lanes of the length of a road. The rougher the road, the higher the National Association of Australian State Roading Authorities counts per lane kilometre. A National Association of Australian State Roading Authorities count of greater than 150 typically indicates a road which is becoming a concern in terms of its roughness and the number of complaints likely to be generated.

[3] Tasman District Council contribute $10,000 a year towards the Late Late Bus.

[4] Refer A1119385