
Ordinary meeting of the
Works and Infrastructure Committee
Thursday 10 September 2015
Commencing at 9.00am
Council Chamber
Civic House
110 Trafalgar Street, Nelson
ATTACHMENTS UNDER SEPARATE
COVER
|
PAGE |
8 Transportation Asset Management Plan 2015-2025
1 A1156705 - Transport Asset
Management Plan 2015-2025 2
9 Water Supply, Wastewater, Stormwater/Flood Protection Asset
Management Plans 2015-2025
1 A824126 - Water Supply Asset
Management Plan 2015-25 186
2 A824068 - Wastewater Asset
Management Plan 2015-25 396
3 A824368 - Stormwater and
Flood Protection Asset Management Plan 2015-25 628
10 Solid Waste Asset Management Plan 2015-2025
Asset Management Plan
2015-2025
Quality
Assurance Statement
|
Version No. |
Date |
Description |
Prepared by |
Reviewed by |
Approved by |
|
1 |
10/12/13 |
Draft for Council workshop |
P Ruffell |
Councillors |
A Louverdis |
|
2 |
1/5/14 |
Draft approved by Council to inform LTP 2015-25 |
P Ruffell |
SLT |
A Louverdis |
|
3 |
10/9/15 |
Approved by Council W&I Committee |
Various |
Councillors |
Council |
Cover Photos:
375mm diameter
Butterfly Valve
Stoke High Level
Reservoir
Yellow highlighted text indicates changes to version 2
that incorporates LTP2015-25 decisions
Blue highlighted text indicates changes to version 2 as a result of
other factors

EXECUTIVE SUMMARY
Operations and Maintenance
1. INTRODUCTION
1.1 Background
1.2 Goals and Objectives of Water Supply Asset Ownership
1.3 BACKGROUND
1.4 Plan Framework
1.5 Asset Management Planning
1.6 Sustainable Development
2. LEVELS
OF SERVICE
2.1 Customer Research and Expectations
2.2 Water Quality
3.2 Reliability
3.3 Pressure
3.4 Flow Rate
3.5 Emergency Response
3.6 Environmental
4. FUTURE
DEMAND
4.1 Existing Situation
4.2 Demand Forecast
4.3 Demand Management
4.4 Supply Capacity
4.5 Extensions to the Area Supplied. 70
4.6 Future Growth
4.7 Action Plan
5. EMERGENCY
AND RISK MANAGEMENT
5.1 Background
5.2 Implementation
5.3 Risk Identification, Risk Analysis and Risk Priority
Rating
5.4 Risk Summary
5.5 Recovery
5.6 Action Plan
5.7 Review
5.8 Health and safety
6. LIFE-CYCLE
MANAGEMENT PLANS
6.1 Background Data
6.2 Asset Condition and Performance Assessments
7. FINANCIAL
7.1 Background
7.2 Asset Valuation and Depreciation. 106
7.3 Operations and maintenance plan. 117
7.4 Renewal Strategy
7.5 Capital Programme
7.6 Asset Disposal Plan
7.7 Long Term plan
7.8 Funding
8. ASSET
MANAGEMENT PRACTICES
8.1 Asset Management
8.2 Information Systems
8.3 Accounting/Financial Systems
8.4 Geographical Information System.. 133
8.5 Information Flow Requirements and Processes
8.6 Asset Management System
8.7 Network Model
8.8 Condition Model
8.9 SCADA Telemetry
9. PLAN
IMPROVEMENT AND MONITORING
9.1 Previous Action Plans
9.2 Performance Monitoring and Management
9.3 Improvement Programme
9.4 Monitoring And Review Procedures 138
10. ACTION
PLAN
10.1 Explanation
10.2 Annual Performance Monitoring
LIST OF TABLES
Table
ES3: Years 1-12 of the 2015/25 Long Term
Plan- Financial Summary
Table ES4: Renewals
Table ES5: Capital
Expenditure
Table
2.1 Asset
Performance
Table
2.2 Links Between
Levels of Service and Community Outcomes
Table
2.3 Ministry of
Health Grading Schedule
Table
2.4 Demerit Points
2008 – 2015 grading
Table
2.5 Urgent Maximum
Response Times
Table
2.6 Non Urgent
Maximum Response Times
Table
3.1 Nelson City
Population Projections 2011 – 2045. From Statistics New Zealand 2015 (A1393084)
Table 3.2 Nelson City Population Projections 2011 – 2045. From Statistics New Zealand 2015 (A13930………………………………………………………………………………………………………………………….
Table 3.3 Source of Raw Water
Table
3.4 Peak Daily Demand
Table
3.5 Total Daily Demand
Table
3.6 Water Demand
Projections (Peak Day 1 in 60 year Drought)
Table
3.7 Current
Reservoirs
Table
3.8 Proposed
Reservoirs
Table
4.1 Likelihood
Ratings (Semi Qualitative Measure)
Table
4.2 Semi-Quantitative
Measures of Consequence and Areas of Impact
Table
4.3 Risk Priority
Rating (Semi Quantitative)
Table
4.4 Risk Events
Ratings (Semi-Quantitative)
Table
4.5 Risk Treatment
Schedule and Plan - Water Supply
Table
5.1 Best Estimate
of Condition of Asbestos Cement Watermains
Table
5.2 Best Estimate
of Condition of Cast Iron Watermains
Table
5.3 Maitai
Pipeline Maintenance Schedule (over next five years)
Table
5.4 Reservoir Risk
Categories
Table
6.1 Water Supply
Asset Valuation - June 2014
Table
6.2 Nominal
Working Life of Water Assets (Years)
Table 6.3
Assumptions………………………………………………………………………………………………………………….113
Table
6.3.1 Water Supply Operation and
Maintenance Projections
Table
6.4 Water Supply
Renewals Projections
Table
6.5 Water Supply
Capital Expenditure Projections
Table
8.1 Previous
Action Plans Report Needs to be updated.
Table
9.1 Action Plan
Needs updating
Table
9.2 Annual
Performance Monitoring and Reporting
Table
A: Gap Analysis -
Water
Table B: Prioritisation Analysis of areas within the Services
Overlay for scheduling of expenditure on addressing servicing constraints
through the
Asset Management Plan’s and Long Term Plan
Table C: Services Overlay Infrastructure Upgrade Codes
Table
D: Water Supply Operation and Maintenance Projections 182
Table
E: Water Supply Renewals Projections
Table
F: Water Supply Capital Expenditure Projections
LIST OF FIGURES
Figure 2.1 Residents’ Satisfaction with Water Supply
Figure 2.3 Water Pressure Zones
Figure 3.1 Nelson
City Population Projections
Figure 3.2 Peak
Water Demand
Figure 3.3 Infrastructure Leakage Index for Nelson
Figure 3.4 World Bank Banding System for Infrastructure Leakage
Index
Figure 5.1 Sustainability Impact at Various Lifecycle Stages
Figure 5.2 Water Pipelines: Age/Material Distribution
Figure 5.3 Theoretical Life Expectancy/Material Distribution
Figure A Maitai Reservoir Level
Figure B The Water Balance Data for 2012/13 Financial Year
(latest available)
Figure C Sources of Water Losses
Figure D The Four Components of Managing Apparent Losses
Figure E The Four Components of Managing Real Losses
Figure F Plan of Infrastructure Planning for Growth in Services
Overlay Areas
LIST OF APPENDICES
Appendix A: Glossary
Of Terms
Appendix B: Water
Supply Conservation Strategy
Appendix C: Lifelines
Appendix D: Nelson
City Council Advanced Asset Management Gap Analysis - Water
Appendix E: Water
Losses Evaluation
Appendix F: Active
Leakage Control Plan
Appendix G: Pressure
Reduction Plan Needs To Be Upgraded.
Appendix H: Infrastructure
Planning Process For Growth Projects
Appendix I: 30 Year Infrastructure Strategy
Appendix J: Nelson
Water Treatment Plant Asset Management Plan (A1111654) (A717945)
Appendix K: Solutions
To Fire Flow Level Of Service (A706990)
EXECUTIVE SUMMARY Water Supply Asset Management Plan
2015-25
INTRODUCTION
This
Asset Management Plan is produced for the public water supply assets owned and
managed by the Nelson City Council and provides a 12 year outlook commencing
July 2015. The Plan identifies issues
that underpin expenditure and documents the features, risks and levels of
service associated with the effective, sustainable management of the water
supply assets.
Central
Government has signalled a likely requirement for Councils to develop an
infrastructure strategy covering the foreseeable issues associated with key
infrastructure for a 30 year future timeframe.
In
order to contribute to this strategy financial tables for the 30 year period
have been prepared for this asset management plan.
Assets included in this Plan
Nelson
City Council abstracts water from the Roding, Maitai South Branch and Maitai
North Branch Rivers for supply to approximately 20,000 customers throughout the City. A small number of
private schemes supply residents in the rural areas. The water is coarse
screened at the intakes and conveyed by raw water trunk mains to the Water
Treatment Plant at Tantragee Saddle which was commissioned in August 2004. Supply to the lower levels of Stoke and
Tahunanui is available in an emergency from Tasman District Council.
The water supply asset extends from the source
water intakes in the water catchments, to the point of supply at individual
customer’s property boundaries. It
includes dams, intake structures and screens, tunnels, a Water Treatment Plant,
trunk mains, secondary mains, rider mains, services, valves, hydrants,
non-return valves, pressure reducing valves, pumps, reservoirs, and water
meters.
The
replacement value (2014)
of the water supply infrastructural assets is $246.6million.
Goal of the Water Supply activity
To provide a water supply to Nelson City that
is capable of abstracting, treating and distributing potable water in an
efficient, safe, reliable and sustainable way whilst ensuring that the
ecological, recreational and cultural interests of the community in the water
sources are recognised and enhanced.
Rationale
for Council’s involvement
The
Nelson City Council is the predominant supplier of reticulated water in Nelson
City. The Councils role in this area has been established since the earliest
days of the city’s history.
Support
for Council continuing in this role comes from the following legislation.
Public Health and Safety:
Adequate potable water is essential for community well being - The Health Act
1956 places an obligation on Council to improve, promote and protect public
health within the District.
Legislative
requirements:
The
Nelson City Council is a local authority established under the Local Government
Act 2002 (the Act) with purpose and responsibilities set out in the Act. In
particular the purpose as it relates to infrastructure is as follows:
10 Purpose of local
government
(1) The purpose
of local government is—
a) to enable democratic local decision-making and action
by, and on behalf of, communities; and
b) to meet the current and future needs of
communities for good-quality local infrastructure, local public services, and
performance of regulatory functions in a way that is most cost-effective for
households and businesses.
(2) In this
Act, good-quality, in
relation to local infrastructure, local public services, and performance of
regulatory functions, means infrastructure, services, and performance that are—
(a) efficient;
and
(b) effective;
and
(c) appropriate
to present and anticipated future circumstances.
and the Act further defines core services to the community as:
11A Core services
to be considered in performing role
In performing its role, a
local authority must have particular regard to the contribution that the
following core services make to its communities:
(a) network
infrastructure:
(b) public
transport services:
(c) solid waste
collection and disposal:
(d) the
avoidance or mitigation of natural hazards:
(e) libraries, museums,
reserves, recreational facilities, and other community infrastructure.
Water supply is a network infrastructure (sec
197(2)) and a water service (sec 124).
Council
has specific obligations under section 130 of the Act to continue to provide
existing water services. These also recognise the requirement to take a
sustainable development approach, set out in section 14 of the Act, which takes
into account:
· the
social, economic and cultural interests of people and communities; and
· the
need to maintain and enhance the quality of the environment; and
· the
reasonably foreseeable needs of future generations
Reliable provision:
Human health, tourism and industry, in particular, rely on the reliable
provision of this service - The Local Government Act 1974 provides the
authority for the Council to own and operate the water supply service.
Water Supply Priorities for the
period 2015 to 2025
Council’s
priorities between 2015 and 2025 for the water supply activity will focus on
the following areas:
· Fire
Flows are lower than desired in many areas as a result of the 2008 NZ Fire
Service changes to how distances from hydrants are measured;
· Renewal
of the resource consents for water extraction from the Maitai and Roding rivers
by 2017;
· Te
Tau Ihu Settlement Legislation;
· Water
losses;
· Natural
Hazard Security of the network in light of the recent Canterbury Earthquakes
and storm events, including wider network hazards- Earthquake fault line,
liquefaction and climate change;
· Higher
than desirable pressures still exist in parts of the network resulting in
greater maintenance costs and water losses;
· Microbiological
and chemical Water Quality issues have been identified in previous water supply
grading exercises;
· Ongoing
risks of backflow contamination exist;
· Waimea
Water Augmentation Committee’s proposed dam on the Lee River at Brightwater;
· Integrating
supply with Tasman District Council;
· Renewals
Strategy;
· Recovery
works following extreme rainfall event in December 2011, expected to be
completed by July 2016;
· Condition
Assessment of older pipework;
· Supply
to elevated areas and future development areas;
· Existing
Maitai concrete pipeline between the treatment plant and the city;
· SCADA
(Supervisory Control And Data Acquisition). Review and upgrade of radio
telemetry;
· Additional
storage reservoir in Atawhai Area;
· Sustainable
Development;
· Water
Treatment Plant. Membrane replacement and move to using carbon dioxide for the
foreseeable future to moderate acidity of the raw water and improve the
effectiveness of treatment chemicals;
· 30
year Infrastructure Strategy signalled in the Local Government Act 2002
Amendment Act (2014).
Fire Flows
The
public supply is designed to provide an effective fire fighting network.
Hydrants are installed on all service mains in urban supply areas in accordance
with the New Zealand Fire Service Firefighting Water Supplies Code of Practice.
The
New Zealand Fire Service issued a revised Firefighting Water Code of Practice
in 2008 with the result that fire flows in the city are now lower than desired
in many areas largely as a result of the changes to how distances from hydrants
are measured.
The
required flow for single or multi-unit housing (but excluding multi-storey
apartment blocks) is 25 litres per second with a minimum of 12.5 litres per
second from a hydrant within 135 metres of the risk and a further minimum of
12.5 litres per second from another hydrant within 270 metres of the risk.
Previous
versions of this code of practice measured the distances from properties to
fire hydrants as a radius centred on the property, the current version now
measures the true “along the road” distance.
This has had the effect of now increasing the number of properties that
do not currently meet the distance requirement.
The exact number of
properties affected are expected to be confirmed in 2013/14. See Appendix K.
The
Fire Service Code of Practice confirms that where there is a reliably
calibrated and accepted system for computer modelling of flows in a reticulated
water system, the Fire Service may accept the outputs from such modelling in
place of testing certain fire hydrants.
$600,000
is included in the Renewals budget over the first six years of this plan i.e.
$100,000 per year from 2015/16-20/21, for upgrades to the water network in
areas where the fire flows are not being delivered. The areas to be upgraded
will be identified using the water network model.
Resource consents for water
extraction
Nelson
City draws its public water supply from three sources:
· A run
of river source from a weir on the Roding River;
· A run
of river source from a weir on the South Branch of the Maitai River;
· An
intake tower in a storage dam on the North Branch of the Maitai River;
Nelson
City Council has three Resource Consents for the water supply covering the abstraction of raw water from both the
Roding and Maitai rivers, the continued operation of the Maitai Dam on the
North Branch and intake weir on the South Branch of the Maitai River and the
Dam/ intake weir on the Roding River. The consents and expiry dates are as
follows:
· RM
960396 Maitai River expires 1/02/2017;
· RM
025151 Maitai River expires 1/02/2017;
· RM
975374 Roding River expires 1/10/2017.
A
single new resource consent application will need to be lodged in 2015/16 to
allow for a hearing and possible appeals, prior to the expiry of the existing
resource consents.
In
2013 Council approved the engagement of Cawthron Institute to provide
professional advice to Council through the resource consent process.
Professional planning advisers
and water engineers were engaged in 2013 to begin the preparation of the
consent application.
The
existing Maitai and Roding sources can provide sufficient water to meet the
City’s needs in a 1 in 60 year drought for the foreseeable future. Provision of
a rubber weir on top of the Maitai Dam spillway could increase the water
storage by 10,000m3 (if required), equivalent to 20 years demand
growth. Sufficient water of high quality
is therefore available for urban supply for the foreseeable future.
The
removal of gravel from behind the Roding dam and the possible enhancement of
lake storage have been identified by Council as areas to be investigated.
Te Tau Ihu Settlement Acts 2014
The Ngāti
Kōata, Ngāti Rārua, Ngāti Tama ki Te Tau Ihu, and Te
Ātiawa o Te Waka-a-Māui Claims Settlement Act 2014, Ngāti
Apa ki te Rā Tō, Ngāti Kuia, and Rangitāne o Wairau Claims
Settlement Act 2014 and the Ngati
Toa Rangatira Claims Settlement Act 2014 Te
Tau Ihu Claims Settlement Act (The Acts)
provides statutory obligations for Council in respect to general decision
making processes. The Acts are
the culmination of Central Government’s resolution of claims lodged by the
eight iwi for redress of past wrong’s and provides for Cultural, Relationship
and Financial redress.
Statutory acknowledgments may
impact works programmes within the Asset Management Plan and the eight iwi will
potentially be considered as affected parties under section 95E of the Resource
Management Act, which the settlement legislation provides for. The proposal to establish a Freshwater
Advisory Committee under the settlement legislation would be a potentially
effective tool for achieving a forum to involve the iwi of Te Tau Ihu in the
development of future asset management planning, infrastructure strategies and
Long Term Plans.
Water Losses
All
water reticulation networks are prone to leakage to some extent. Leakage occurs both from the public system
and from individual customer’s plumbing. Council estimates that the city
network has water losses of approximately 30% of the water that leaves the
treatment plant. This amounts to an average 2.4 million cubic metres per year.
The level of losses is arrived at by comparing the volume of water leaving the
treatment plant with the volume that is recorded by customer’s meters. Being
able to quantify this figure is very important and improving the accuracy of
records is currently a focus of the activity. A programme of repairing reported
leaks and proactive leak detection is included in the activity budgets. See appendix E.
Networks
also have other losses which include:
· Fire
fighting and hydrant flow testing;
· Overflows
at reservoirs and losses during cleaning;
· Mains
testing and flushing;
· Unknown
connections;
· Use
by contractors.
Collectively
this total water loss is referred to as Unaccounted for Water (UFW).
Controlling
UFW can significantly reduce demand. UFW
control also has an environmental benefit as it reduces the quantities of water
that are required to be abstracted from the river sources.
Natural Hazards
Because
the Maitai Water Supply Scheme (Dam and Pipeline) is a vulnerable asset, it was
designed to withstand 1 in 1000 year seismic and flood events without damage.
Key
structures are designed to withstand maximum credible earthquake and probable
maximum flood without collapse (but not without some damage, possibly requiring
decommissioning and major repair work).
Recent
work by Council has focussed on natural hazards that might impact on the city,
in particular:
· Direct
damage from Earthquake shaking;
· Damage
from liquefaction in susceptible areas;
· Damage
from Tsunami;
· Damage
from Flooding and major storm events;
· Impact
of potential climate change and sea level rise.
The
Maitai pipeline between the Dam and Brook Street has been identified as an
extreme risk from damage due to earthquake displacement, windfall trees or
slips.
The
pipeline supplies two thirds of Nelson’s water, is above ground, on a sidling
bench along the hillside.
Repair/replacement of, for example, a 5m length of damaged pipe would
take 24-48 hours depending on location (and has proved to be the case in 2008
when high winds brought down trees onto the pipeline). When full, city
reservoirs can hold sufficient water for approximately 24 hours average
consumption. The more usual capacity, allowing for filling time and continuing
use, is 8-10 hours of daytime demand.
Construction
of a new buried pipeline between the dam and the Water Treatment Plant was
completed in 2013/14.
Design
of a new pipeline between the Water Treatment Plant and Westbrook Terrace is scheduled for began in 2014/15 with
construction to begin
be completed in 2016/17.
The
Roding Water Scheme has low and moderate risks to structures, other than a 200m
length of pipe between the screenhouse and the chlorinator house. This pipe is suspended on piers along the
riverbank. A 30m section was washed out
in the large flood of January 1986.
Subsequently the pipes were more securely fixed and rock armouring was
constructed in front of the piers. There
is a possibility that a similar large flood could damage the pipe again. Reinstatement would take 2-3 days, during
which time the Maitai river and Tasman District Council would be the only
sources supplying the City. This risk is acceptable given the large storage
volume of the Maitai dam.
While
automatic chlorination exists at the water treatment plant, a stand-alone
portable chlorinator unit, run by a small petrol generator and using sodium
hypochlorite is also held there in case of emergency. This has the capacity of dosing 30l/h of
sodium hypochlorite, which is sufficient to treat the full Maitai flow of
37,000m3/day.
A
separate Emergency Management Plan has been developed covering Risks and
Actions specific to Water Treatment Plant.
A
portable chlorinator alternatively powered by either a petrol motor or an
electric motor is held at Princes Drive for emergency chlorination using High
Test Hypochlorite (HTH) powder. This has
a capacity of dosing 24kg of chlorine per hour.
This is sufficient to treat 12,000 m3/hour of water at 2 g/m3 (= 2ppm or
2mg per litre).
Risks
posed to the trunk mains range from low to high. The high risk is from earthquake and storm
events where sections of key mains could be damaged. Presently stocks of repair materials are held
to allow single repairs to each main.
Mutual
aid would be required from other water supply authorities to reinstate trunk
mains in the event of multiple major breaks.
Refer to section 4.5.2 for details of the Mutual Aid Plan.
The Clearwater, Stoke, Walters Bluff, and
Observatory Hill Reservoirs have been constructed to category 2. The large and small Thompson Terrace
Reservoirs have been strengthened to category 2 and category 3 respectively.
Note: Category 2 is a 1 in 1000 year earthquake
and category 3 is a 1 in 333 year earthquake.
All
large reservoirs have been fitted with automatic seismic shut off valves. When excess flow from the reservoir is
detected (such as from a broken outlet or damaged trunk main) the outlet valve
is automatically shut and an alarm sent to the Duty Officer via the SCADA
system. This acts to protect structures and ground adjacent any failure and
maximises the volume of water retained in reservoirs during emergencies.
As a
result of the Christchurch earthquakes Council is currently undertaking a
seismic review of the critical elements of the above ground network, starting
with the storage reservoirs and sections of the Maitai Dam to the treatment
plant trunk main looking at the direct impact of earthquake shaking. Future
work will focus on near fault proximity of the network, possible impacts of
liquefaction on existing and future infrastructure, impacts of flooding and the
long term planning required as a result of climate change.
Water Pressure
With
the exception of hillside development served by local storage tanks and
pressure pumps, provide a water supply of suitable pressure such that:
i) The maximum fluctuation between the
pressure at the lowest and highest draw times of the day at each property does
not exceed 35% from the mean value.
ii) The minimum working head at the ground
floor level of each property is not less than 300kpa (30m head) excluding
friction losses in the private pipework.
iii) The maximum static head at the ground
floor level of each property does not exceed 900kPa (90m head).
There
are parts of the network that do not meet these criteria. Higher pressures
cause premature failure of pipes and fittings while lower pressures can impact
on the use of modern appliances such as washing machines, dishwashers and mains
pressure hot water cylinders. Households affected by these issues currently
make their own arrangements by installing pressure reduction valves or small
pressure pumps.
Water Quality and Grading
Each
year the water supply and reticulation is able to be graded by the Ministry of
Health against the Drinking Water Standards for New Zealand 2008. The grading is voluntary and arrived at by
the review of the source, treatment and distribution against set criteria. Demerit points are awarded when the criteria
are not met.
The
Ministry of Health suggests that the minimum water supply grading for a
community size over 10,000 be:
· Source
and treatment B (satisfactory, very low level of risk when the water leaves the
treatment plant)
· Distribution
a (completely satisfactory, extremely low level of risk).
However,
it stresses that irrespective of size a community should aim for as high a
grade as possible. Nelson City Council
water supply was last graded in 2015 and was assessed as:
· Source
and treatment A (completely satisfactory, extremely low level of risk)
· Distribution
b (satisfactory, very low level of risk)
The
construction of the Water Treatment Plant achieved A for source/treatment, but
the present b for distribution is below the Ministry of Health suggested
standard.
The
grading assessment carried out in 2015 identified issues with the following areas of the
distribution network:
· Pipe
age and condition. 1 demerit.
· Leak
detection and water loss. 1 demerits.
· Backflow
prevention. 4 demerits.
· Supply
(high) pressure. 1 demerit.
· Free
available chlorine monitoring. 1
demerit.
· Microbiological
compliance. 4 demerits.
· Chemical
compliance. 2 demerits.
· Corrosion of materials. 1 demerit.
The
above issues highlight the emphasis placed on a secure reticulation network and
the need to keep the network at a good level of maintenance and condition.
In
addition to the water supply grading scheme the Ministry of Health monitors
networked water suppliers to ensure that their supply meets the Drinking Water
Standards under the Health Act 1956.
The
Nelson City Council supply is assessed by the Ministry of Health on an annual
basis for compliance with the drinking water standards.
Backflow Prevention
The
protection of the quality of the water supplied to customers is a vital
responsibility of any water supply authority.
While the quality of the water entering the system is known, chemical or
microbiological contamination can occur in some circumstances from water
re-entering the system from consumer’s premises should fittings be wrongly
connected or a temporary vacuum develop in the line. The risk from activities
such as undertakers, doctors and dentist surgeries are readily understood,
however similar issues can also arise in commercial kitchens where food is
prepared and cleaning chemicals are used.
Increased
emphasis has been placed on Risk Management by the Ministry of Health in recent
years. The 2007 amendments to the Health
Act require that water suppliers prepare Public Health Risk Management Plans
for their systems, and include the management of risk from backflow. Council’s
Public Health Risk Management Plan was completed in 2012.
Installation
of backflow prevention devices is programmed for the next ten years.
Lee River Dam (Tasman District
Council)
The
Waimea Water Augmentation Committee (WWAC) was formed to pursue an additional
water source for the Waimea Plains.
Nelson City Council is represented on WWAC and has provided
approximately $270,000
to support their work. In 2013 WWAC recommended the construction of a 14
million m3 detention dam on a site on the upper Lee River at
Brightwater. Water would be released from the dam and enter the underground
aquifer via the tributaries of the Waimea river. It would then be pumped from the aquifer by
users on the Waimea Plains. Bores for
the Waimea area of the Tasman District Council water supply are sited near the
Appleby Bridge and will benefit from a more secure volume of water in the
aquifer as a guard against salt water intrusion. Volumes required for urban
supply are small when compared with agriculture and horticulture irrigation
requirements, so the latter are likely to be responsible for funding the major
portion of the construction costs.
Tasman
District Council is in the process of considering submissions to a proposed
plan change that would make provision for the construction and operation of the
dam.
Nelson
City Council is yet to decide on whether or not to provide further monetary
support for the project. From a strict asset management point of view Nelson
City’s current raw water supply from the Maitai and Roding rivers is expected
to be able to supply the needs of the city for the foreseeable future. The
trend in water intensive processing industries in Nelson is also away from the
traditional areas of fin-fish and shellfish activities. Efficiency in water use
is also a feature of new processing facilities constructed in recent years. The
cost of Nelson City establishing separate water bores at the Appleby Bridge
well field and piping the water to Nelson for treatment has previously been
estimated at $14.7million (2008).
For
the city to need access to a further water source, demand would have to exceed
approximately 50,000m3 per day. This would be a considerable increase in the
2011/12 peak daily demand of 28,000m3.
The
removal of gravel from behind the Roding dam and the enhancement of lake
storage has been identified by Council as an additional source of water storage
for the city that may also provide benefits to Tasman District.
Integrating supply with Tasman
District Council
Historically
Nelson City and Tasman District have linked water supplies with Tasman District
supplying a small section of the southern part of Nelson City as well as the
Wakatu Industrial Estate. Nelson City supplies Richmond the lesser of 909m3 of
water/day or 1/15 of the Roding supply rate, arising from legislation covering
the construction of the Roding Dam.
Nelson
City Council and Tasman District Council have entered into an Engineering
Services Agreement (2005) formalising the above. This agreement combines the
other cross boundary infrastructural service of sewer reticulation to a small
number of properties adjacent Champion Road, but excludes the supply of water
to ENZA and the Alliance Group processing plant as separate agreements remain
in place between these industries and the Tasman District Council.
As of
March 2014 the agreement is being re-negotiated. Tasman District Council’s
preferred option is to become a bulk water supplier to Nelson City Council for
the residential areas with status quo continuing for the commercial/industrial
areas. In that capacity Tasman District Council would supply water to a metered
point and Nelson City Council would become responsible for the reticulation and
customer billing/enquiries.
This
approach would require some adjustment of the restrictions that are put in
place by Nelson City Council in times of water shortage (drought/emergency) in
order to reflect the different raw water supply source of the Tasman District
Council scheme.
The
current agreement remains in force until such time as a new agreement is
finalised.
Renewals Strategy
The
reticulation system has to reliably transport the required volumes of water
from the trunk mains and reservoirs to the consumers, at sufficient pressure
while maintaining quality. The water network is made up a range of materials
such as cast iron, asbestos cement, concrete, uPVC, polyethylene, concrete
lined steel and ductile iron. Currently Council’s renewal strategy is based on
replacing asbestos cement pipes that were installed in the 1950’s and are
showing higher than expected failure rates. Further investigation of the older
sections of the network are needed in order to confirm the condition of the
steel and iron pipes. As the current asbestos cement pipe renewal programme is
expected to continue for the next 8-10 years, enhanced condition assessment of
the other pipe types is expected to be part of the renewal strategy from years
5-8.
Recovery works post December
2011 and April 2013 storm events
As
with buildings and fittings Council insures items of infrastructure for damage
in these events. Infrastructure is insured through the LAPP (Local Authority
Protection Programme Disaster Fund) scheme. This is a mutual pool created by
local authorities in 1993 to cater for the replacement of infrastructure
following catastrophic damage by natural disaster. The recent earthquakes in
Christchurch coupled with the flooding events throughout the country have
reduced the funds ability to support Councils’ with their recovery works after
disasters.
December 2011
An
extreme rainfall event occurred throughout Nelson and Tasman in December 2011.
The event was notable for the total volume of rain that fell over a 48 hour
period, being the greatest for at least the past 220 years anywhere in the
urbanised areas of New Zealand. The long duration of relatively low intensity
rainfall led to hillsides becoming saturated, with multiple slips occurring
throughout the city.
The
water network itself generally coped very well with this event as flows in
rivers were even and at levels that did not threaten reticulation. The greatest
impact was on pipework from the Maitai dam to the treatment plant and a small
section of main at the Glen where slips came close to undermining sections of
pipe. Repair works at the Glen were completed in 2013. Repairs to the Maitai
pipeline at Poleford Bridge and the Arboretum adjacent the Maitai Camp are
ongoing in 2014.
April 2013
No
damage was sustained by water network during the April 2013 storm event.
Condition Assessment
Historically
asset monitoring to determine condition has been subjective based on local
knowledge and experience. Formal
procedures now exist to assess asset condition.
The
development and continued use of condition assessment data will support
preparation of predictive decay curves for particular asset types and hence
permit prediction of remaining life.
Consideration of economic influences and other factors will also be
required in the adopted life for the asset type.
By
considering the current condition point on an assumed decay curve, the profile
can predict the effective life (time) before failure. This failure time can be the physical end of
life, minimum level of acceptable service, or limit of capacity of the asset.
Supply to elevated areas and
future development areas
In
some of the more recent hill top developments above the reliable water supply
contour level of 110m, the issues of continuity of supply and pressure
fluctuations have been resolved by the installation of storage tanks and in
some cases pump stations (e.g. Observatory Hill, Austen Ward Heights, Panorama
Drive, Springlea, Wastney Terrace). To avoid the need for water towers and
allow maximum land development, the standards have been eased so that dwellings
with ground floor level less than 30m below the floor of the reservoir are
required to install a domestic pressure pump and tank to ensure adequate
pressures. Oversize service connections
are provided to minimise friction losses. The system works well as the presence
of the storage tank ensures continuity of supply.
Council
property database contains entries advising of these special circumstances.
A Map
of the areas zoned for growth but constrained by lack of services is attached
in Appendix I. Construction of services to these areas should be carried out in
line with Council’s prioritisation policy. Appendix I sets out a draft
“INFRASTRUCTURE PLANNING TOOL FOR GROWTH PROJECTS” that reflects infrastructure
prioritisation factors. In 2014 Council
is expected to consider a proposal to review the Nelson Resource Management
Plan and look at wider prioritisation criteria for future development areas.
Infrastructure planning will align with any new policy that is developed.
A
specific project has been identified to update desktop investigations, carried
out in the past, looking at servicing constraints to areas currently zoned for
residential development but restricted by a services overlay.
Existing Maitai concrete pipeline
The
Maitai pipeline between the Maitai Dam and the Water Treatment Plant transports
the majority of the water used in the City.
It has numerous small shrinkage cracks and is vulnerable to slips from
above and below the pipeline.
Council
completed the construction of a duplicate Maitai pipeline between the dam and
the Water Treatment Plant in 2014 but will continue to use and maintain the
existing pipeline, to reduce pumping costs, for as long as it is viable to do
so. The replacement of the section
between the Water Treatment Plant and Westbrook Terrace is shown in this Asset
Management Plan for construction in 2017/18.
Supervisory Control And Data
Acquisition (SCADA) Review and Upgrade
All
of the Nelson City Council’s strategic utility components are monitored
remotely, at Civic House or by duty staff using laptop computers at home,
utilising a telecommunication system called SCADA. SCADA has given Council the
ability to ascertain faults and instigate repairs without affecting the service
to the consumer and has significantly increased efficiency and reliability of
the utility schemes. This function has become critical to the operation of the
network and has been supported by Council’s in-house Information Management
team up to now. There is a need to upgrade this package and at the same time
consider how the technical requirements can be accommodated within the
essentially office based computer packages used by the majority of Council
staff.
Additional storage reservoir in
Atawhai Area
To maintain reasonable
security of supply Council has a network of larger water storage reservoirs
throughout the central city and Stoke. Currently there is approximately 21,000
m3 of storage throughout the city providing approximately 1m3 for every
property in the city. Current maximum one day demand for the city is
approximately 28,000m3. The Atawhai area has one large (2,500m3) reservoir at
Walters Bluff and a number of small tanks in the various valleys beyond. As
growth increases in the North of the city there is the need to install an
additional large reservoir further North to provide for future growth and
enhance the level of water stored close to urban areas in event of emergencies.
Construction of an additional reservoir is programmed for 2021-2023.
Sustainable Development (Nelson
2060)
Overview of Sustainability
The
Local Government Act 2002 requires that local authorities take a sustainable
development approach to everything they do.
The publication, Nelson 2060 (June 2013) was developed by Council
through an inclusive process called “Framing our Future” and sets out Nelson’s
sustainability strategy.
The framework and checklist outlined in this
document will be used to guide the management of the city’s infrastructure.
Infrastructure
is installed and maintained on the understanding that the assets are provided
in perpetuity for the benefit of future generations. Longevity of an asset is a prime
consideration when design and planning is undertaken for new or replacement
components in the network.
Actions for Future
Improvement
Further
action in promoting the sustainability of this activity is considered to centre
on the following areas:
· More
strategic monitoring of the condition and operation of the asset to identify
most appropriate renewal priorities;
· Enhanced
network modelling to aid prediction of performance and renewal strategies;
· Additional
effort to reduce water losses through renewal of pipelines, reduced water
pressures and proactive water loss detection;
· Duplication
of the trunk main from the treatment plant to the city centre;
· Renewal
of resource consents for the city water supply;
· Ongoing
monitoring of water quality in the Maitai and Roding rivers.
Water Treatment Plant. Membrane
replacement and changes to use of chemicals
Commissioned
in August 2004, the Water Treatment Plant is an ultra-filtration plant with
limited use of chemicals in the operation. Chlorine is used for residual
disinfection. Fluoride is not added to the Nelson water supply, but the
treatment plant could be retrofitted to accommodate this if any future Council
makes this decision.
The
plant was designed and constructed with the ability to install five filtration
“trains” to cope with future demand. The treatment plant can currently supply
approximately 41,000m3/day from the four trains that are in place.
Large
portions of the plant and individual components are computer monitored 24 hours
and alarms are raised if the process goes outside predetermined performance
limits. The filter manufacturer also monitors performance of the process from
Canada on a daily basis.
Water
Treatment Plant Filters – Renewal of the filters will be required between 2014/17. The filters have been in place
since 2004 and the 10 year guarantee period ended in August 2014. Installation
of the final fifth “train” is programmed for 2014/15. The installation of new filters for this train is
scheduled for 2015/16 and this will provide greater maintenance
flexibility within the plant and will extend the life of the existing
membranes.
Council
and the plant operators have
also been trialling the
use of carbon dioxide in 2013/14 as a means of adjusting the acidity of the
water in an effort to further reduce the use of chemicals. The treatment plant uses ferric
chloride to remove organic material from the raw water. Organic material is a
natural consequence of using run of river water sources and the component that
is held in solution can pass through the filters and add colour, odour and
taste to the water. Lowering the pH of the water improves the efficiency
of the chemicals used to remove
it, with a consequent reduction in the amount of chemical required in
the process. The pilot trial
has proven to be successful in reducing chemical use and the operational
contractor is currently making provision for a more permanent installation.
The
plant and water works reserve (includes the Maitai and Roding catchments) is
operated and maintained on behalf of Council, under contract, by Fulton Hogan
Ltd.
The
close control of the catchment and the water treatment plant are the primary
reasons that the city received an “A” grade from the Ministry of Health for the
water source.
30 year Infrastructure Strategy
The
requirement for an infrastructure strategy arose from advice provided by Better
Local Government programme advisory groups.
The strategy is intended to improve local authorities’ delivery of core
infrastructure and management of physical assets. It should identify strategic issues facing
the council and the future implications and is intended to add transparency for
residents and ratepayers about these issues and their consequences.
The
strategy is included in the LGA 2002 Amendment Act (2014) which is expected to be passed in its current
form in June 2014.
This
Asset Management Plan contains the information that would form the basis of the
water utility section of an integrated strategy. Detailed information relating
to the specific components of the strategy is set out in the appropriate
sections of this asset management plan and is either shown directly or as an
area that will require future work.
Appendix
H sets out the specific areas to be covered in a 30 year strategy, with the
reference to the appropriate sections of this asset management plan. The
appendix also contains the 30 year budget tables.
LEVELS
OF SERVICE
It is
Council’s responsibility to provide Nelson City with a water supply network
which meets public health and safety standards and is environmentally
sustainable. The Council’s objectives
are to:
· Provide
a water supply of acceptable quality, suitable pressure, flow and reliability,
with sufficient water to meet reasonable (in compliance with resource consent
conditions and Water Bylaw) peak demand through a 1 in 60-year drought.
· Ensure
that Nelson’s water supply is sustainably managed.
· To
provide water in a cost-effective manner.
The
levels of service are consulted on during the Long Term Plan submission process
and are reflected in this Asset Management Plan.
Table ES1: The Proposed levels of service 2015-25 are:
|
What Council will provide |
Performance Measures |
Targets |
Targets in Years 4-10 |
||
|
Year 1 |
Year 2 16/17 |
Year 3 17/18 |
|||
|
Good quality water |
Meeting Drinking Water Standards for NZ
2005/08 sampling and test standards Number of public complaints |
Maintain Ab grading “A”for source and “b” for
reticulation and ensure potable water supplied to customers No more than 100 justifiable complaints relating
to clarity, taste or odour in any year |
Maintain |
Maintain |
Maintain |
|
A reliable supply
of water |
Day to day continuity of
supply Water loss from the
network Water usage |
1 in 60 year drought security until at least
2035. Supply 99.5% available under normal operating
conditions. Max 24 hr outage under normal operating
conditions. Complete investigation to guide future work Compliance with resource consent abstraction
rates |
Maintain Maintain Maintain |
Maintain Maintain Maintain |
Maintain Maintain Maintain |
|
Acceptable
water pressure |
Percentage of customers
with acceptable pressure, defined as minimum 30m head, max 90m head and
maximum fluctuation <35% from the average
pressure received by each customer |
Computer model identifies 80% of properties
with acceptable pressure |
Maintain |
Maintain |
Maintain |
|
Adequate
flows of water |
Meet NZFire Service fire flows (and therefore domestic
and commercial/industrial flows) to all parts of the city |
Computer model identifies at least 95% of
properties served by the network with acceptable flows |
Maintain |
Maintain |
Computer model identifies at least 95% of
properties served by the network with acceptable flows and 99% by 2021/22 |
|
A
prompt response to reported network issues |
Meet response times
identified in the external works contract |
Contractor to meet maximum response times
under the contract |
Maintain |
Maintain |
Maintain |
|
A
network that protects the natural environment |
Comply with resource
consents RM025151 and RM975374 conditions for allowable water abstraction
rates, revegetation of stream banks and eel and fish passage requirements. |
100% compliance |
Maintain |
Maintain |
Maintain |
Water System Overview
Background
Historically,
the Nelson City Council has been the predominant water provider to the
residents of Nelson. The Council’s authority
to undertake water supply is contained in Section 12 of the Local Government
Act 2002. Under Section 25 of the Health
Act 1956, the Minister of Health may require a Council to provide sanitary
services, which includes waterworks.
Although it is discretionary whether or not it provides water, the
Council has a long term commitment to carrying out this activity.
Nelson
City Council does not operate separate rating areas for its water supply zones
as they are essentially operated as one large zone.
This
Asset Management Plan is written on the basis that water supply is an ongoing
core responsibility of Council.
The
replacement costs of the water supply assets are $246.6M (as shown in the 2014 valuations) detailed below.
Table ES2: Summary of Water
Services Assets (June 2014)
|
Asset Category |
Quantity |
Unit |
Replacement Value $,000s |
|
Reticulation High Pressure |
104.1 |
km |
32,399,508 |
|
Reticulation Low Pressure |
219.9 |
km |
61,301,794 |
|
Trunk Mains |
39.9 |
km |
18,455,112 |
|
Maitai Pipeline |
9.3 |
km |
17,666,517 |
|
Roding Pipeline |
3.9 |
km |
2,160,916 |
|
Maitai Water Supply Scheme |
|
|
20,670,500 |
|
Roding Dam |
|
|
2,859,900 |
|
Treatment Plant |
|
|
20,191,669 |
|
Tunnels |
3 |
No |
11,677,100 |
|
Reservoirs and Tanks |
37 |
No |
13,155,170 |
|
Pump Stations |
11 |
No |
2,544,228 |
|
Pressure Reducing Valves |
32 |
No |
383,922 |
|
Air & Non Return Valves |
136 |
No |
324,224 |
|
Gate Valves |
3,349 |
No |
7,273,282 |
|
Manholes |
94 |
No |
343,288 |
|
Hydrants |
2,481 |
No |
6,323,027 |
|
Meters |
20,252 |
No |
3,037,432 |
|
Customer Connections |
20,161 |
No |
25,913,634 |
|
Total |
|
|
246,681,222 |
Reticulation
The primary
purpose of the reticulation system is to distribute water to customers
throughout the city and provide a constant source of fire fighting water. In
many locations the need to meet minimum fire flows dictates the size of the
reticulation. Because Nelson has limited areas of flat land many of the
residential properties are established on the surrounding foothills. The
variation in height between the upper levels and sea level presents a real
issue for maintaining reasonable pressures in the reticulation. Council
endeavours to provide water to the city at the lowest practical pressure to
avoid damage to residential fittings and reduce losses. Pressures falling in the range between 30 and
90 metres of head have been adopted for the Level of Service.
Trunk Mains
Trunk
mains are typically larger diameter direct supply lines to the various water
reservoirs in the city. As these mains are critical parts of the network,
connections to them are limited in order to reduce the time when the water
supply has to be interrupted. The two major supply pipelines from the Maitai
and Roding Dams to the water treatment plant are separately identified.
Pump Stations
The
Nelson City Council operates 9 water pump stations throughout the city. The
majority of these are lift stations that supply water to reservoirs at higher
levels for storage as well as pressure enhancement. A small number are solely
pressure pumps that boost supply pressure to the reticulation. These are
generally used where the cost to install a reservoir would not be justified for
the small numbers of users affected.
Reservoirs and Tanks
There
are 37 reservoirs and tanks connected to the network. Seven of these hold
between 2,500m3 and 5,500m3 of water with the remaining
holding volumes ranging from 25m3 to 900m3.
All
but one of the seven larger tanks are constructed from pre-stressed or
reinforced concrete, with one tank being of bolted steel plate construction.
When
full the tanks will hold approximately one day’s supply of drinking water for
the city.
Currently
the larger tanks are positioned close to the central city area and Stoke. To
provide a better level of security for the north of the city a further larger
reservoir is proposed for the Bayview/Marybank area within the term of this
plan.
Within
the next 30 years it is anticipated that development will require additional
reservoirs for supply of potable water in emergencies at the Northern and
Southern ends of the city.
FINANCIAL
SUMMARY
The
projected operating and maintenance costs, renewals and capital expenditure for
the water supply system over the next twelve years are shown in the following
Tables.
Table ES3:
Years 1-12 of the
2015/25 Long Term Plan- Financial Summary
Note:
The figures are in 2015 dollars - the
Long Term Plan figures are adjusted for inflation
Operations and
Maintenance
|
Year |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
|
|
Long Term Plan |
2015/25 LTP |
2018/28 LTP |
2021/31 LTP |
2024/34 LTP |
|||||||||
|
O&M Expense |
2014/15 |
2015/16 |
2016/17 |
2017/18 |
2018/19 |
2019/20 |
2020/21 |
2021/22 |
2022/23 |
2023/24 |
2024/25 |
2025/26 |
2026/27 |
|
Administration |
1,650 |
2,109 |
1,694 |
1,659 |
1,649 |
1,679 |
1,649 |
1,650 |
1,649 |
1,660 |
2,830 |
2,830 |
|
|
Depreciation |
|
3,996 |
4,010 |
4,021 |
4,032 |
4,041 |
4,050 |
4,082 |
4,137 |
4,169 |
4,187 |
4,187 |
4,187 |
|
Electricity |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
|
|
Water Treatment |
1,600 |
1,600 |
1,600 |
1,600 |
1,600 |
1,800 |
1,800 |
1,800 |
1,800 |
1,800 |
1,800 |
1,800 |
|
|
WTP Lagoon
desludge |
|
|
|
|
|
|
|
|
|
|
100 |
|
|
|
Physical Works –
Programmed |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
|
|
Physical Works – Reactive |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,300 |
2,300 |
|
|
Headworks |
216 |
179 |
179 |
204 |
179 |
179 |
179 |
179 |
204 |
400 |
179 |
179 |
|
|
Roding Dam Gravel |
|
50 |
50 |
5 |
200 |
|
|
|
|
|
|
|
|
|
Fish Passage |
|
20 |
|
|
|
|
|
|
|
|
|
|
|
|
PHRMP |
|
30 |
|
|
|
|
|
|
|
|
|
|
|
|
Network Capacity
-Growth |
|
50 |
50 |
|
|
|
|
|
|
|
|
|
|
|
Back Flow mtce |
|
20 |
30 |
40 |
50 |
60 |
70 |
80 |
90 |
100 |
110 |
150 |
150 |
|
Pressure/Flow Rate
mtce |
|
30 |
36 |
36 |
36 |
36 |
36 |
36 |
36 |
36 |
36 |
50 |
50 |
|
Prelim CAPEX
reviews |
|
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
|
|
|
Natural Hazards
Assessment |
|
50 |
50 |
|
|
|
|
|
|
|
|
|
|
|
Water Loss
Reduction Strategy |
|
30 |
30 |
30 |
60 |
60 |
60 |
45 |
15 |
15 |
15 |
|
|
|
Total (a) ($,000s) |
|
10,490 |
10,892 |
10,353 |
10,589 |
10,373 |
10,622 |
10,619 |
10,655 |
10,721 |
11,056 |
12,164 |
12,164 |
Table
ES4: Renewals
|
Year |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
|
|
Long Term Plan |
2015/25 LTP |
2018/28 LTP |
2021/31 LTP |
2024/34 LTP |
|||||||||
|
Renewals Project Area |
2014/15 |
2015/16 |
2016/17 |
2017/18 |
2018/19 |
2019/20 |
2020/21 |
2021/22 |
2022/23 |
2023/24 |
2024/25 |
2025/26 |
2026/27 |
|
Pipeline |
838 |
544 |
794 |
794 |
850 |
850 |
850 |
900 |
900 |
900 |
950 |
950 |
950 |
|
Waimea Road
Renewal (Little Go Stream) |
|
500 |
|
|
|
|
|
|
|
|
|
|
|
|
Pump Stations -
Renewals |
|
0 |
270 |
70 |
3 |
20 |
0 |
13 |
136 |
495 |
497 |
0 |
3 |
|
Headworks -
renewals |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
|
Reservoir
Refurbishment Programme |
|
|
|
|
50 |
50 |
50 |
50 |
50 |
|
|
|
|
|
Residential Meters |
50 |
100 |
100 |
500 |
1,000 |
1,000 |
500 |
|
|
|
|
|
|
|
Commercial Meters |
301 |
185 |
150 |
150 |
300 |
300 |
300 |
300 |
300 |
300 |
|
|
|
|
Backflow
Prevention Renewals |
|
|
|
|
|
|
|
|
|
|
|
350 |
350 |
|
Water Treatment
Plant Membrane Renewals |
0 |
0 |
0 |
1,000 |
1,000 |
1,000 |
1,000 |
0 |
0 |
0 |
0 |
1,000 |
1,000 |
|
Water Treatment
Plant Renewals |
|
246 |
140 |
206 |
185 |
269 |
169 |
287 |
|
|
|
|
|
|
Maitai Resource Consent
Renewal |
80 |
200 |
200 |
200 |
|
|
|
|
|
|
|
|
|
|
Roding Resource
Consent Renewal |
80 |
200 |
200 |
200 |
|
|
|
|
|
|
|
|
|
|
Roding Pipeline |
|
100 |
0 |
0 |
0 |
0 |
100 |
100 |
1,000 |
1,500 |
1,500 |
|
|
|
Scada |
|
60 |
70 |
|
|
|
|
|
|
|
|
|
|
|
Total (a) ($,000s) |
1,249 |
2,195 |
1,984 |
3,180 |
3,448 |
3,549 |
3,029 |
1,710 |
2,446 |
3,255 |
3,007 |
2,360 |
2,363 |
Table
ES5: Capital Expenditure
|
Year |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
|
|
Long Term Plan |
2015/25 LTP |
2018/28 LTP |
2021/31 LTP |
2024/34 LTP |
|||||||||
|
Capital Projects |
2014/15 |
2015/16 |
2016/17 |
2017/18 |
2018/19 |
2019/20 |
2020/21 |
2021/22 |
2022/23 |
2023/24 |
2024/25 |
2025/26 |
2026/27 |
|
Malvern Hills -
Atawhai Pump & Ridge Resvr |
21 |
18 |
|
|
|
|
|
150 |
|
|
|
|
|
|
Atawhai #2
Reservoir |
|
87 |
100 |
285 |
|
|
|
1,000 |
2,500 |
|
|
|
|
|
Atawhai Trunk Main |
|
|
|
|
50 |
95 |
|
3,300 |
|
|
|
|
|
|
Backflow Prevention |
375 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
200 |
200 |
|
Maitai Pipeline
(Dam-WTP) |
|
2 |
|
|
|
|
|
|
|
|
|
|
|
|
Maitai Pipeline
(WTP-Westbk Tce) |
100 |
2,118 |
2,000 |
|
|
|
|
|
|
|
|
|
|
|
Maitai Planting |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
|
Telemetry /
control upgrades |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pressure
Enhancement |
|
|
|
|
|
150 |
100 |
|
|
|
|
100 |
|
|
NCC - TDC Link |
|
|
|
|
|
|
|
|
|
|
|
100 |
100 |
|
DMA establishment |
|
50 |
100 |
100 |
|
|
|
|
|
|
|
|
|
|
Water Loss
Reduction Programme |
|
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
|
|
|
Hira extension |
|
|
|
|
|
|
|
|
|
|
|
150 |
1,000 |
|
Future Growth
Additional Storage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Seismic Risk
Upgrades |
|
100 |
100 |
100 |
|
|
|
|
|
|
|
|
|
|
Water Treatment
Plant Membranes |
1,200 |
1,066 |
|
|
|
|
|
|
|
|
|
|
|
|
Natural Hazards
Risk Assessment |
|
|
|
|
100 |
100 |
100 |
|
|
|
|
|
|
|
Network Capacity
Confirmation for Growth Areas |
|
|
|
|
|
100 |
100 |
100 |
|
|
|
1,250 |
|
|
Network Upgrades Nelson North |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Network Upgrades Nelson Central |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Network Upgrades Nelson South |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fire Flow Upgrades |
100
|
100
|
100
|
200 |
200
|
|
|
|
|
|
|
|
|
|
Pipe Improvements/Pressure
Reduction |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
|
Ridermains |
155
|
75 |
75 |
75 |
155 |
155 |
155 |
55 |
55 |
55 |
55 |
55 |
55 |
|
System
Improvements & Misc Pipes & Fittings |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
50 |
50 |
50 |
50 |
50 |
50 |
|
Water Treatment
Plant Upgrades |
|
|
|
|
|
|
|
|
|
150
|
500 |
500 |
500 |
|
Dam Upgrades |
|
0 |
0 |
0 |
0 |
0 |
0 |
100 |
100 |
100 |
100 |
0 |
100 |
|
Total (a) ($,000s) |
2,231 |
4,086 |
2,945 |
1,230 |
975 |
1070 |
925 |
5,165 |
3,115 |
765 |
1,115 |
2,465 |
2,065 |
1.1 Background
1.1.1 Purpose of the Plan
An
Asset Management Plan combines management, financial, engineering and technical
practices to ensure that the level of service required by the community is
provided cost-effectively.
This
is the Asset Management Plan for the Nelson City Council water supply
network.
1.1.2 Relationship with Other Documents
The
Asset Management Plan is a key component of the Council’s strategic planning
function.
Financial
projections from the Asset Management Plan support and justify the financial
forecasts in Council’s Long Term Plan.
Similarly
the Asset Management Plan provides the basis for preparation of each Annual
Plan.
1.1.3 Water Sources
Nelson
City Council abstracts water from the Roding, Maitai South Branch and Maitai
North Branch Rivers for supply to the urban areas of the City. The water is coarse screened at the intakes
and conveyed by raw water trunk mains to the Water Treatment Plant at Tantragee
Saddle which was commissioned in August 2004.
Supply to the lower levels of Stoke and Tahunanui is available in an
emergency from Tasman District Council.
1.1.4 Area Covered
The
Nelson City water supply area extends to Saxton Field in the south. (The Wakatu Industrial Estate, the north side
of Champion Road, Hill Street North, Alliance Group and ENZA Foods, are within
Nelson City, but are supplied by Tasman District Council).
In
the north the area extends to Todds Valley, The Glen and Hillwood on the
Wakapuaka side of the Gentle Annie Hill.
Properties
in Marsden Valley, the Maitai motorcamp and a few of the adjacent houses in the
Maitai Valley are also supplied.
A
population of approximately 45,000 is served by the Nelson City Council
reticulated water supply. There are
approximately 18,000 residential connections and 2,000 commercial/industrial
connections.
1.1.5 Asset Description
The
assets covered are from the source water intakes in the water catchments to the
point of supply at individual customers’ boundaries. This includes dams, intake structures and
screens, control equipment, the Water Treatment Plant, tunnels, trunk mains,
secondary mains, rider mains, services, valves, hydrants, non-return valves,
pressure reducing valves, pumps, reservoirs, and water meters.
1.1.6 Key Stake Holders
The
plan recognises the following stake holders:
External
· The community
including iwi, ratepayers and residents,
· Residential
and commercial consumers,
· Government
departments and agencies, including Ministry for the Environment, Ministry of
Health, Audit NZ.
· Nelson
Marlborough District Health Board.
· New
Zealand Fire Service
· Consultants
and Contractors
Internal
· Mayor
and Councillors
· Council
staff
1.1.7 Nelson City Council Arts Strategy
Where
opportunities present themselves, consideration will be given to the
incorporation of artwork in the water network.
1.2 Goals and Objectives
of Water Supply Asset Ownership
1.2.1 Links
to Nelson City Community Outcomes
Councils are required by the
Local Government Act 2002 to have Community Outcomes – a statement of the
measures of success that Council is working to achieve for the community.
Council’s community outcomes are
set out in the Long Term Plan 2015-25. 2005 with significant input from the community. The Long
Term Plan 2012-22 also included seven Council priorities to provide a specific
focus within the wider outcomes Council aimed to achieve.
|
Community Outcomes |
How this Council activity contributes to the outcome |
|
·
Our unique natural
environment is healthy and protected |
·
Environmental impacts are understood
and managed, including through compliance with resource consents. |
|
·
Our infrastructure is
efficient, cost effective and meets current and future needs |
·
A good quality,
sustainable and affordable water network meets the needs of our current and
future community. |
|
·
Our communities are
healthy, safe, inclusive and resilient |
·
Safe and well managed
water resources deliver critical health outcomes for the community. |
|
·
Our region is supported by
an innovative and sustainable economy |
·
Water resources have an
important role in supporting a range of businesses that rely on clean and
plentiful water supplies. |
1.2.2 History and Justification for Asset
Ownership
The
Nelson City Council and its forebears have been responsible for water supply in
the City since the initial Brook Scheme was constructed in 1874.
· The
Roding supply was introduced in 1940.
· The
Maitai scheme was commissioned in the early 1960s with a river intake
· The
Maitai Dam was completed in 1987
· Subsequently
the Brook system was decommissioned in 2000
· The
Water Treatment Plant at Tantragee Saddle was commissioned in 2004.
The
City has expanded by amalgamation of adjoining areas.
· Tahuna
Town Board joined to the City in 1950.
· Stoke
was transferred from Waimea County Council in 1958
· Atawhai
in 1968
· Wakapuaka
and Stoke Rural in 1989
· Subsequently
the Glen reticulation was connected in 1991.
Historically,
therefore, the Nelson City Council has been the predominant water provider to
the residents of Nelson. The Council’s
authority to undertake water supply is contained in Section 12 of the Local
Government Act 2002. Under Section 25 of
the Health Act 1956, the Minister of Health may require a Council to provide
sanitary services, which includes waterworks.
Although it is discretionary whether or not it provides water, the
Council has a long term commitment to carry out this activity.
Nelson
City Council does not operate separate rating areas for its water supply zones
as they are essentially operated as one large zone.
This
Asset Management Plan is written on the basis that water supply is an ongoing
core responsibility of Council.
1.3 BACKGROUND
Over
the last 25 years the Nelson City Water Supply has been significantly improved from
a basic supply with a Ministry of Health water supply grading of Ed
(Unacceptable level of risk for source/treatment, Unsatisfactory Level of risk)
for distribution to a modern system with a grading of Ab (Completely
satisfactory – extremely low level of risk, Satisfactory – very low level of
risk).
These
significant improvements have been:
· Construction
of the Maitai Dam to provide storage and the ability to select the best raw
water
· Construction
of four 2,500 cubic metre reservoirs (Atawhai, Stoke #1, Stoke #2 and Stoke
High Level)
· Construction
of the Tantragee water treatment plant and second trunk main to Stoke
· Renewal
of all 75mm diameter cast iron pipes
The
work proposed in this Asset Management Plan:
Makes
provision for the renewal of water abstraction resource consents
· Increases
resilience to civil emergency by completing the duplication of key pipelines
· Continues
the work to reduce water losses and monitor demand reduction through new
technology, to defer the need for a future additional raw water source
· Provides
for growth
· Provides
timely renewal of assets as they reach the end of their economic life
· Manages
risk
· Achieves
and maintains the levels of service
1.3.1 Source
The
existing Maitai and Roding sources can provide sufficient water to meet the
City’s needs in a 1 in 60 year drought for the foreseeable future. By provision
of a rubber weir on top of the Maitai Dam spillway the water storage can be
increased by 10,000m3, equivalent to 20 years demand growth at current levels.
Future wider demand strategies will enable the existing supply to be adequate
until into the 22nd Century for current projected population increases.
Sufficient water of high quality is therefore available for urban supply for
the foreseeable future.
The
Council’s extraction of water from the Maitai and Roding rivers is controlled
by resource consents issued by both the Tasman District and Nelson City
Council’s. As the current consents
expire in 2017 it is proposed to lodge applications for new consents by the end
of June 2016.
Council
will also investigate the feasibility of removing gravel that has built up
behind the Roding Dam, in order to improve storage capacity.
1.3.2 Maitai Pipeline
The
Maitai pipeline between the Maitai Dam and the Water Treatment Plant transports
the majority of the water used in the City.
It has numerous small shrinkage cracks and is vulnerable to slips from
above and below the pipeline.
Current
demand projections show that the Maitai pipeline has sufficient capacity to supply
the City (in conjunction with the Roding pipeline and foothills link) through a
1 in 60 year drought until at least 2023 (refer Section 3). The Maitai pipeline has been identified as
the highest risk asset and is a “Lifeline” for the city. In 2007 Council established a Working Party
to consider long term water options and replacement, refurbishment and
duplication options for the Maitai pipeline.
Council subsequently resolved that the Maitai pipeline between the dam
and the Water Treatment Plant be replaced with a new main down the Maitai
Valley Road, but that the existing pipeline be kept in use to reduce pumping
costs, for as long as it is viable to do so.
The replacement of the section between the Water Treatment Plant and
Westbrook Terrace was deferred and is shown in this Asset Management Plan for 2015-17.
1.3.3 Trunk Mains and Reservoirs
With
increasing development, demand is spreading north and south beyond the current
trunk main system. Typically demand is
spread over a 16 hour period, whereas water treatment plants and trunk mains
function most effectively with demand spread over 24 hours. Also, in times of emergency water should be
available in the locality it is needed.
A
network of trunk mains and reservoirs is therefore necessary to transport and
store water overnight so that peak demand during the day can be met from
instantaneous flow and local storage.
Additional
trunk mains and reservoirs are therefore proposed to cope with demand from
growth.
1.3.4 Reticulation Condition
The
reticulation system has to reliably transport the required volumes of water
from the trunk mains and reservoirs to the consumers, at sufficient pressure
while maintaining quality.
Ongoing
condition assessment of the reticulation network is therefore necessary, and
timely proactive refurbishment or renewal of the pipes and fittings is
proposed.
1.3.5 Backflow Prevention
The
protection of the quality of the water supplied to customers is a vital responsibility
of any water supply authority. While the
quality of the water entering the system is known, chemical or microbiological
contamination can occur in some circumstances from water re-entering the system
from consumer’s premises.
Increased
emphasis has been placed on Risk Management by the Ministry of Health in recent
years. The 2007 amendments to the Health
Act require that water suppliers prepare Public Health Risk Management Plans
for their systems, and include the management of risk from backflow.
The
Nelson City Council Public Health Risk Management Plan (now named Water Safety
Plan under the 2013 amendment to the Health Act 1956) was completed and
approved by the Ministry of Health in 2012. This plan references the proposal
to install backflow prevention devices on all commercial/industrial activities
by 2024/25.
1.3.6 Critical Assets
Critical
Assets are defined in the Asset Management Plan as assets that are essential to
providing a water supply in times of emergency (albeit at a reduced level of
service), or have an unacceptable consequence in event of failure.
Critical
assets have been identified as:
· Headworks
including dams and intakes
· Raw
water trunk mains
· Raw
water pump stations
· Water
Treatment Plant including Clearwater Reservoir
· Treated
water trunk mains
· Treated
water pump stations
· Reservoirs
With
these assets operating, treated water will be available in each suburb for
distribution by water tanker or personal collection and by watermain as damaged
reticulation is repaired and brought back into service.
1.3.7 Water Supply Grading
The
Ministry of Health suggests that the minimum water supply grading for a
community size over 10,000 be
· Source
and treatment B (satisfactory, very low level of risk when the water laves the
treatment plan)
· Distribution
a (completely satisfactory, extremely low level of risk).
· However,
it stresses that irrespective of size a community should aim for as high a
grade as possible.
i)
The grading assessment
carried out in 2015
identified issues with the following areas of the distribution network:
· Pipe
age and condition. 1 demerit.
· Leak
detection and water loss. 1 demerits.
· Backflow
prevention. 4 demerits.
· Supply
(high) pressure. 1 demerit.
· Free
available chlorine monitoring. 1
demerit.
· Microbiological
compliance. 4 demerits.
· Chemical
compliance. 2 demerits.
· Corrosion of materials. 1 demerit.
ii)
The above issues highlight
the emphasis placed on a secure reticulation network and the need to keep the
network at a good level of maintenance and condition.
iii) In addition to the water supply grading scheme the Ministry of Health
monitors networked water suppliers to ensure that their supply meets the
Drinking Water Standards under the Health Act 1956.
iv) The Nelson City Council supply is assessed by the Ministry of Health on
an annual basis for compliance with the drinking water standards.
1.4 Plan Framework
The
plan is structured as follows:
Section 1 Introduction: sets out
the philosophy and scope of the plan and water supply asset.
Section 2 Levels of Service:
outlines the current and target levels of service with regard to customer
expectations, water quality, reliability, pressure, and flow rate, systems
operation, and emergency response.
Section 3 Future Demand: outlines
existing demand, demand projections, demand management, impact of changing
demand on assets.
Section 4 Risk Management:
Contains Risk Management Philosophy; Risk Register for Water Assets; Risk
Treatment Plan and Schedule for water asset lifelines.
Section 5 Lifecycle Management
Plan: Contains, asset details (including capacity, performance, condition and
valuations), maintenance and renewal strategies, capital programme and asset
disposal strategy.
Section 6 Financial Summary:
Outlines where funds will be sourced from.
Section 7 Asset Management
Practices: contains details of the Accounting/ Financial, Geographical
Information System, Information Flow, and Asset Management Systems.
Section 8 Plan Improvement Programme:
provides detail on planning to monitor the performance of the Asset Management
Plan and to improve Asset Management systems that will improve the level of
confidence in the Asset Management Plan, provides details in proposed
chronological order of the processes to be improved in the management of the
water asset.
Section 9 Action Plan: Summary of
actions, including deadlines, identified in the Asset Management Plan.
1.5 Asset Management
Planning
1.5.1 Benefits
Asset
Management Plans summarise the Council’s management, financial, engineering and
technical processes and procedures for the management of the Council’s water
supply assets.
· The
benefits of Asset Management planning are:
· Improved
understanding of levels of service objectives and standards
· Life
cycle (long term) costs are identified for agreed levels of service
· Showing
that necessary maintenance work will be undertaken
· Prevention
or the reduction of risk of system failure
· Better
understanding and forecasting of asset related management options and costs
· Improved
decision making based on historic records, performance data and cost benefit
analysis
· Justification
of future capital programmes
· Improved
accountability to the Community for funding requirements
· Increased
customer satisfaction and improved public perception of the Nelson City Council
· Overcoming
institutional memory loss
· Ensuring
a proactive approach to Asset Management
· Prolonged
life of water assets through optimisation and proactive maintenance
· Meeting
the principles of sustainable development
· Meeting
the requirements of the Local Government Act 2002, by supporting Long Term Plan
funding requirements
· Co-ordination
with other asset groups when construction is programmed for the same location
1.5.2 Core to “Core Plus” Approach
Asset
Management plans evolve in a continuous cycle of review and improvement so the
quality of outputs matches the changing business and legislative needs. The
International Infrastructural Management Manual 2006 details criteria for
assessing conformity to “core” and “advanced” levels of Asset Management in
New Zealand.
Features
of Core Asset Management are:
· A
lifecycle approach is taken;
· Core
Asset Management plans are developed based on;
· best
available current information and random condition sampling,
· simple
risk assessment,
· existing
levels of service,
· contrasting
existing management strategies with opportunities for improvement;
· Capital
works are prioritised using a simple ranking criteria;
· Long
term cash flow predictions for maintenance, rehabilitation and replacement are
calculated based on local knowledge of assets and options for meeting current
levels of service;
· Financial
and critical service performance measures against which trends and Asset
Management plan implementation and improvements can be monitored are provided.
Features
of Advanced Asset Management are:
· Asset
Management strategy is clearly derived from corporate strategic plan;
· Long
term, whole life plans and cost/risk/benefit optimisation;
· Objectives
and performance measures are aligned and complementary;
· IT
systems are integrated, used, and understood;
· Competencies
and training is aligned to roles, responsibilities and collaborative
requirements;
· Strategies
are risk based, with appropriate use of predictive methods, optimised decision
making;
· Iterative
continuous improvement.
1.5.3 Core to “Core Plus” Gap Analysis
In
recent years it has been recognised that a new rating level of “Core Plus” is
the most appropriate rating for cities of Nelson’s size. This rating reflects
that parts of the asset can be managed at a Core level and parts at an Advanced
level. The resultant provides an effective asset management tool without
becoming un-necessarily expensive.
At a
January 2006 workshop a gap analysis between “Core” and “Advanced” Asset
Management was undertaken for each asset group. The Water Supply Asset
Management Plan was considered to be midway between “core” and “advanced”. The detailed assessment is included in
Appendix D.
1.6 Sustainable
Development
1.6.1 Overview
of Sustainability
v)
The Local Government Act 2002 requires that local authorities take a sustainable
development approach to everything they do.
The publication, Nelson 2060 (June 2013) was developed by Council
through an inclusive process called “Framing our Future” and sets out Nelson’s
sustainability strategy.
vi)
The framework and checklist outlined
in this document will be used to guide the management of the city’s
infrastructure.
vii)
Infrastructure is installed and maintained on the understanding that the
assets are provided in perpetuity for the benefit of future generations. Longevity of an asset is a prime
consideration when design and planning is undertaken for new or replacement
components in the network.
viii)
Actions for Future Improvement
ix)
Further action in promoting the sustainability of this activity is
considered to centre on the following areas:
· More strategic monitoring of the condition and operation of the asset to
identify most appropriate renewal priorities;
· Enhanced network modelling to aid prediction of performance and renewal
strategies;
· Additional effort to reduce water losses through renewal of pipelines,
reduced water pressures and proactive water loss detection;
· Duplication of the trunk main from the treatment plant to the city
centre;
· Renewal of resource consents for the city water supply;
· Ongoing monitoring of water quality in the Maitai and Roding rivers.
1.6.2 Sustainability and Life Cycle
Historically
Council has recognised the fundamentals of sustainable development in the water
supply activity through the adoption of Engineering Standards and construction
practices that lead to the maximisation of gravity reticulation and use of long
life materials.
Sustainability
has been reflected in the decision making process when designing and
constructing the water supply network in the following areas.
· Ensuring
a reticulated water supply network is available to the greatest number of
residents;
· Where
appropriate, use of longer pipe sections, either coiled polyethylene or uPVC
replacing shorter cast iron, concrete and asbestos cement pipes, leading to
quicker installation and fewer joints;
· Water
pump stations with variable speed drive units for pumps, leading to more
economical use of pumps and longer service life;
· Maximising
elevated storage reservoirs and gravity reticulation to reduce reliance on
pumps;
· Investing
in new technologies to rehabilitate existing reticulation, where appropriate,
rather than excavate and replace;
· Identification
and rectification of losses from the network leading to reduced volumes of
water to be treated and pumped;
· Ongoing
investigation of impacts of the operation of the Maitai dam on the ecology of
the Maitai river;
· Ongoing
revegetation programme for the banks of the Maitai river.
These
initiatives meet the Sustainability Policy criteria to:
· Optimise
the efficient use of resources and minimise waste
· Increase
the use of renewable resources and reduce greenhouse gas emissions
· Deliver
on improved quality of life for the present and future residents of Nelson.
Community
infrastructure is installed and maintained on the understanding that the assets
are provided in perpetuity for the benefit of future generations. Longevity of an asset is a prime
consideration when design and planning is undertaken for new or replacement
components in the network.
Council
recognises the benefits that come from formalising asset management plans and
better monitoring and modelling of the condition and operation of the
network.
1.6.3 Actions for Future Improvements
x)
Further action in promoting the
sustainability of this activity is considered to centre on the following areas:
· More
strategic monitoring of the condition and operation of the asset to identify
most appropriate renewal priorities;
· Enhanced
network modelling to aid prediction of performance and renewal strategies;
· Additional
effort to reduce water losses through renewal of pipelines, reduced water
pressures and proactive water loss detection;
· Duplication
of the trunk main from the treatment plant to the city centre;
· Renewal
of resource consents for the city water supply;
· Ongoing
monitoring of water quality in the Maitai and Roding rivers.
This
section on levels of service is the vital part of any Asset Management
Plan. The levels of service set out the
community expectation for the service provided by the water supply asset and
therefore determine the amount of resources that are required to maintain,
renew and upgrade the water supply infrastructure.
Changes
to the levels of service may significantly change funding requirements in some
instances.
Levels
of service are specified for:
i) Water Quality
ii) Reliability of Supply
iii) Water Pressure
iv) Flow Rates
v) Emergency Response
vi) Protection of the Natural
Environment
The
2012/13 performance of the water supply assets in achieving Levels of Service
is broadly summarised as follows.
Table 2.1 Asset Performance
|
|
Excellent |
Good |
Moderate |
Poor |
Very Poor |
|
·
Water Quality |
·
100% |
1.
|
2.
|
3.
|
|
|
·
Reliability |
4.
99.6% |
5.
|
6.
0.4% |
7.
|
|
|
·
Pressure |
8.
82% |
9.
|
10.
18% |
11.
|
|
|
·
Flow |
12.
99.1% |
13.
|
14.
|
15.
0.9% |
|
Note: These percentages refer to the number of
customers receiving the level of service.
|
·
Performance Grade: |
·
Excellent |
·
No performance problem |
|
·
|
·
Good |
·
No significant effect on
performance |
|
·
|
·
Moderate |
·
Performance substandard
under peak demand |
|
·
|
·
Poor |
·
Performance regularly
substandard |
|
·
|
·
Very Poor |
·
Unacceptable performance |
Other
levels of service are specified for:
i) Customer response (Section 2.1)
ii) Emergency response (Section 2.6)
iii) Environmental
(Section 2.7)
Table 2.2 Links Between Levels of Service and Community Outcomes
|
xi)
What Council will provide |
xii)
Performance Measures |
xiii)
Targets |
xiv)
Targets in Years 4-10 |
||
|
xv)
Year 1 |
xvi)
Year 2 16/17 |
xvii)
Year 3 17/18 |
|||
|
xviii) Good quality water |
Meeting Drinking Water Standards for NZ 2005/08
sampling and test standards Number of public complaints |
Maintain Ab grading “A”for source and “b” for reticulation
and ensure potable water supplied to customers No more than 100 justifiable complaints relating to
clarity, taste or odour in any year |
Maintain |
Maintain |
Maintain |
|
xix) A reliable supply of water |
Day to day continuity of
supply Water loss from the
network Water usage |
1 in 60 year drought security until at least 2035. Supply 99.5% available under normal operating
conditions. Max 24 hr outage under normal operating conditions. Complete investigation to guide future work Compliance with resource consent abstraction
rates |
Maintain Maintain Maintain |
Maintain Maintain Maintain |
Maintain Maintain Maintain |
|
xx)
Acceptable water pressure |
Percentage of customers with
acceptable pressure, defined as minimum 30m head, max 90m head and maximum
fluctuation <35% from the average
pressure received by each customer |
Computer model identifies 80% of properties with
acceptable pressure |
Maintain |
Maintain |
Maintain |
|
xxi) Adequate
flows of water |
Meet NZFire Service fire flows (and therefore
domestic and commercial/industrial flows) to all parts of the city |
Computer model identifies at least 95% of properties
served by the network with acceptable flows |
Maintain |
Maintain |
Computer model identifies at least 95% of properties
served by the network with acceptable flows and 99% by 2021/22 |
|
xxii) A
prompt response to reported network issues |
Meet response times
identified in the external works contract |
Contractor to meet maximum response times under the
contract |
Maintain |
Maintain |
Maintain |
|
xxiii) A
network that protects the natural environment |
Comply with resource
consents RM025151 and RM975374 conditions for allowable water abstraction
rates, revegetation of stream banks and eel and fish passage requirements. |
100% compliance |
Maintain |
Maintain |
Maintain |
Community Outcomes 2015-25
|
1. Community outcomes |
2. How this Council activity contributes to the outcome |
|
3.
Our unique natural environment is healthy and
protected |
4.
Environmental impacts are understood and
managed, including through compliance with resource consents. |
|
5.
Our infrastructure is efficient, cost
effective and meets current and future needs |
6.
A good quality, sustainable and affordable
water network meets the needs of our current and future community. |
|
7.
Our communities are healthy, safe, inclusive
and resilient |
8.
Safe and well managed water resources deliver
critical health outcomes for the community. |
|
9.
Our region is supported by an innovative and
sustainable economy |
10.
Water resources have an important role in
supporting a range of businesses that rely on clean and plentiful water
supplies. |
1.7 Customer Research
and Expectations
1.7.1 Background
Nelson
City Council carries out Residents Surveys each year. These telephone interviews are conducted by
fully trained interviewers, using a random sample of Nelson residents and a
minimum quota set by gender and age to ensure the sample is representative of the
Nelson population 15 or more years of age.
A weighting procedure is applied to correct minor variations from the
ideal in the number of interviews achieved in each quota category, hence
ensuring the data is representative of Nelson residents.
In
2009 the survey questions changed from a 4 choice answer (Very Satisfied,
Fairly Satisfied, Not Very Satisfied, Don’t know) to a 5 choice answer (Very
Satisfied, Satisfied, Neither, Dissatisfied, Very Dissatisfied, Don’t know),
therefore the results from the 2010 residents survey are not directly
comparable to the previous years.
1.7.2 1998 Residents’ Survey
In
November 1998 AC Nielsen carried out a residents' survey on behalf of the
Nelson City Council.
Of
the Council’s 14 significant activity areas, residents:
· Were
least satisfied with the water supply;
· Rated
water supply the most important activity area in contributing to quality of
life of Nelson residents.
1.7.3 2001 Residents’ Survey
In
September 2001 AC Nielsen carried out a residents’ survey on behalf of the
Nelson City Council. Of the Council’s 14
significant activity areas, residents again:
· Were
least satisfied with the water supply;
· Rated
water supply the most important activity area in contributing to quality of
life of Nelson residents.
1.7.4 2004 Residents’ Survey
In
November 2004 AC Nielsen carried out a residents’ survey on behalf of the
Nelson City Council. This survey was
carried out some three months after the opening of the Tantragee Water
Treatment Plant.
Of
the Council’s 14 significant activity areas, residents:
· Rated
water supply as the most important activity area contributing to the quality of
life for Nelson Residents;
· Were
most satisfied with the water supply and gave it a similar satisfaction to
parks and open spaces.
Issues
identified within Water Supply were:
· Having
a permanent, continuous and reliable supply;
· Quality
of water, both from taste and health perspective;
· A
fair and affordable cost.
1.7.5 2007 Residents’ Survey
In
August 2007 the Neilson Company carried out a residents’ survey on behalf of
the Nelson City Council.
Of
the Council’s 14 significant areas, residents:
· Again
rated water supply as the most important activity area contributing to quality
of life for Nelson Residents;
· Rated
water supply second only to Parks and Open Spaces for satisfaction.
Issues
identified within water supply were:
· Cost
of the Water Treatment Plant/Cost of water too high;
· Adequate
and continuous supply necessary;
· Water
quality is a necessity of life and health.
1.7.6 2010 Residents’ Survey
In
June and July 2010 the Key Research carried out a residents’ survey on behalf
of the Nelson City Council.
Of
the Council’s 14 significant areas, residents:
· Perceived
water supply as the most important area for Council to focus on;
· Satisfaction
is high with regard to water supply with respondents rating this second highest
after parks and open space with 73% responding as satisfied or very satisfied.
Issues
identified within water supply were:
· Cost
of water;
· Quality
of water – in terms of taste and smell;
· Security
of supply and water pressure.
1.7.7 2011 Residents’ Survey
In
May 2011 the Key Research carried out a residents’ survey on behalf of the
Nelson City Council.
Of
the Council’s 14 significant areas, residents:
· Perceived
water supply as the most important area for Council to focus on;
· Satisfaction
remained high with regard to water supply with respondents rating this fourth
highest with 70% responding as satisfied or very satisfied.
Issues
identified within water supply were:
· Cost
of water
· Quality
of water – in terms of taste
1.7.8 2012 Residents’ Survey
In
May 2012 the Key Research carried out a residents’ survey on behalf of the
Nelson City Council. Satisfaction remained high with regard to water supply
with respondents rating this fourth highest with 71% responding as satisfied or
very satisfied.
1.7.9 2013 Residents’ Survey
In
May 2013 a residents’ survey on behalf of the Nelson City Council was carried
out. This survey was shortened from previous years and did not specifically
seek feedback on the water supply activity.
1.7.10 Conclusions from Residents’ Surveys
· Satisfaction
with the water supply has risen from 48% in 1998 to 60% in 2001, to 81% in 2004
and again in 2007 to 89%. The years 2010, 2011 and 2012 have seen the
satisfaction level remain consistent at 70%-73%. The Water Treatment Plant was
completed just prior to the 2004 survey;
· Residents
continue to want a reliable supply;
· Residents
continue to want quality water from a taste and health perspective;
· Residents
want an affordable cost for the water supply;
Figure 2.1 Residents’ Satisfaction with Water
Supply

The target performance measure is 80% satisfied or very satisfied.
This figure will be updated as part of the first
review
1.7.11 Consultation
The
levels of service for Quality, Reliability, Pressure and Flow set in this Water
Supply Asset Management Plan are based on legislative requirements and
Non-Statutory Standards set by government agencies.
These
include:
· Local
Government Act 2002
· Health
Act 1956
· Building
Act 2004
· Drinking
Water Standards for New Zealand 2005/08
· Public
Health Grading of Community Water Supplies 2003 Explanatory Notes and Grading
Forms.
· New
Zealand Fire Service Firefighting Water Supplies Code of Practice 2008.
There
is therefore little discretion for varying these Levels of Service and the Levels
of Service are not directly consulted on.
The Levels of Service are open to public submission during the Long Term
Plan and Annual Plan process.
Public
Consultation using a Special Consultative Procedure is however carried out for
changes to the Water Supply Bylaw.
1.7.12 Service Level Expectations and
Affordability
The
levels of service set in this asset management plan are subject to change as
legislation changes. The community can also request increases above the minimum
levels as long as there is a willingness to fund the financial implications.
As
the population changes and economic conditions fluctuate the cost implications
of higher than minimum levels of service may create affordability issues for
some in the community.
Resolution
of these issues is a governance role at both central and local government
level.
1.8 Water Quality
1.8.1 Statutory Obligations
The
Local Government Act 2002 requires Council to continue to provide water
services and maintain its capacity to meet its obligations.
The
Health Act 1956 prohibits local authorities from supplying polluted water that
is a risk to public health.
The
Health Act 1956 prohibits the construction of a dwelling unless an adequate and
wholesome water supply is available.
The
Building Act 2004 prohibits the use of a building if it does not have an
adequate supply of potable water.
The
Resource Management Act 1991 does not allow the Council to take, use, dam or
divert any water unless it is expressly allowed by a rule in a regional plan or
a resource consent.
The
Health (Drinking Water) Amendment Act was passed in October 2007. This Act
provides a comprehensive regulatory framework for community drinking water
supplies and requires water suppliers to have public health risk management
plans. It also allows water suppliers to require consumers to pay for the
installation and maintenance of backflow prevention devices at the boundary.
The Health Amendment Act 2013 changed the name of Public Health Risk management
plans to Water Safety Plans.
The
National Environmental Standard for Sources of Human Drinking Water regulations
came into force on 6 June 2008. The
purpose of the regulations is to reduce the risk of contamination of drinking
water sources by requiring Regional Councils to consider the effects of granting
water abstraction consents or discharge consents upstream of drinking water
abstraction points. As all the Maitai
and Roding catchments above the intakes are owned by Nelson City Council and
managed as a waterworks reserve, there is little benefit to the City’s Water
Supply from these regulations.
The
National Policy Statement- Freshwater Management 2011 (NPSFM) came into effect
on 1 July 2011. In 2013 Central Government proposed amendments to the NPSFM. An
analysis of the proposed amendments by Local Government NZ concludes that the
amendments now broadly require that:
1. Water quality must be maintained or improved in a region although the
proposal provides no additional
direction as to when or how trade-offs might be made;
2. There is an avoidance of any further over-allocation of water and a
phase out of existing over-allocation
(water quantity);
3. National bottom lines are set for ecosystem health and human health;
4. By 2030, regional councils are to have within their plans freshwater
objectives that reflect national and local values (there are proposed mandatory
national values and attributes). The framework recognises that improving water
quality in some places will take some time. While there is a requirement to set
objectives there is no timeframe set for their achievement
The
policy will need to be given effect to by regional rules in the Nelson Resource
Management Plan (NRMP). It is expected that the greatest impact will come in
the form of water quality controls and limits on water extraction.
1.8.2 Non-Statutory Standards
The
Drinking Water Standards for New Zealand 2005/08 list the maximum
concentrations of chemical, radiological, and microbiological contaminants
acceptable for public health in drinking water.
The standards also specify the sampling protocols that must be observed
to demonstrate that the drinking water complies with the standards. Although
entitled Drinking Water Standards for New Zealand (DWSfNZ) they have no
legislative standing.
However
there is a provision in the Health (Drinking Water) Amendment Act 2007 that
requires water suppliers, when they become aware that the water is not meeting
the drinking water standards to take appropriate steps to correct the problem.
The
Ministry of Health carries out regular grading of water supplies to measure
compliance. The grading schedule is
shown in Table 2.3.
The
Water Supply Grading System takes a risk based approach and assesses factors
that could affect the quality of the water supplied to consumers. For example excess pressure could result in
broken pipes, with contaminants entering the water supply. Insufficient storage could result in low
pressures or negative pressures, with contaminants entering the water supply.
Table 2.3 Ministry of Health Grading Schedule
Source
and treatment grading
Assessment
based on source and treatment factors will result in a grade:
|
·
A1 |
·
Completely satisfactory,
negligible factors will result in a grade; |
|
·
A |
·
Completely satisfactory,
extremely low level of risk |
|
·
B |
·
Satisfactory, very low
level of risk when the water leaves the treatment plant |
|
·
C |
·
Marginally Satisfactory,
low level of microbiological risk when the water leaves the treatment plant,
but may not be satisfactory chemically |
|
·
D |
·
Unsatisfactory level of
risk |
|
·
E |
·
Unacceptable level of risk |
Distribution
zone grading
Assessment
based on source and treatment factors will result in a grade:
|
Sum of demerit points |
Grade |
Description |
|
·
0-10 |
·
a1 |
·
Completely satisfactory, negligible
level of risk; demonstrably high quality; meets Aesthetic Guidelines in
Appendix C and has ISO 9001: 2000
accreditation. |
|
·
0-10 |
·
a |
·
Completely satisfactory,
extremely low level of risk |
|
·
11-20 |
·
b |
·
Satisfactory, very low
level of risk |
|
·
21-30 |
·
c |
·
Marginally satisfactory,
moderately low level of risk |
|
·
31-45 |
·
d |
·
Unsatisfactory level of
risk |
|
·
46 or more |
·
e |
·
Unacceptable level of risk |
Minimum
acceptable grading
Recognising
both public health cost considerations, the following table provides guidance
for the minimum grading acceptable for different sized communities. However, it should be stressed that
irrespective of size a community should aim for as high a grade as possible.
|
Community Size |
Source and Treatment |
Distribution |
|
·
Greater than 10,000 |
·
B |
·
a |
|
·
From 5,001 to 10,000 |
·
B |
·
b |
|
·
5,000 or less |
·
C |
·
c |
Reference: Report on Public Health Grading of a Drinking
Water Supply – Nelson City Council, Nelson Marlborough District Health Board,
May 2008.
1.8.3 Background
The
Nelson City water supply was graded “A” for source/treatment (completely
satisfactory, extremely low level of risk) by the Ministry of Health in May 2015.
The
Nelson City water supply was graded “b” for distribution (satisfactory, very
low level of risk) by the Ministry of Health in May 2015.
The
Ministry of Health table above suggests that a city the size of Nelson should
have a grade of “a” for distribution (completely satisfied, extremely low level
of risk).
The
reticulation grading system is based on the accrual of “demerit” points for
various attributes not present. The sum
of the demerit points determines the grading as shown in Table 2.3.
The
demerit points in the 2008 - 2015
gradings were received for:
Table 2.4 Demerit Points 2008 – 2015 grading
|
Question topic |
Comment |
2008 |
2009 |
2010 |
2011 |
2014 |
2015 |
|
·
Pipe age and records |
·
Fair |
16.
1 |
17.
1 |
18.
1 |
19.
1 |
20. 1 |
21. 1 |
|
·
Leak Detection and Water
Loss |
·
Poor |
22.
2 |
23.
2 |
24.
2 |
25.
2 |
26. 1 |
27. 1 |
|
·
Backflow Prevention |
·
Not met |
28.
4 |
29.
4 |
30.
4 |
31.
4 |
32. 4 |
33. 4 |
|
·
24 hours storage |
·
Less than |
34.
3 |
35.
3 |
36.
3 |
37.
0 |
38. 0 |
39. 0 |
|
·
Supply Pressure |
·
Excess |
40.
1 |
41.
1 |
42.
1 |
43.
1 |
44. 1 |
45. 1 |
|
·
Free Available Chlorine Monitoring |
·
With E.coli / not
continuously monitored |
46.
1 |
47.
1 |
48.
1 |
49.
1 |
50. 1 |
51. 1 |
|
·
Microbiological Compliance |
·
1 positive E.coli samples |
52.
0 |
53.
0 |
54.
0 |
55.
4 |
56. 4 |
57. 4 |
|
·
Chemical compliance |
·
Most |
58.
2 |
59.
2 |
60.
2 |
61.
2 |
62. 2 |
63. 2 |
|
·
Corrosion of materials |
·
|
64.
|
65.
|
66.
|
67.
|
68. |
69. 1 |
|
·
|
·
TOTAL |
70.
14 |
71.
14 |
72.
14 |
73.
15 |
74. 14 |
75. 15 |
The
work proposed in this Asset Management Plan for:
· Loss
Reduction (refer section 3.3.4)
· Backflow
Prevention (refer section 6.5.7 xii)
· New
reservoirs (refer section 3.2.4)
· Pressure
reduction (refer section 2.4.3)
· Water
Quality (refer section 2.2.5)
will
contribute to reducing the total demerit points by addressing the issues they
represent.
The
extreme rain events of December 2011 and April 2013 reduced the available staff
time resource within Council, which together with Central Government proposals
to review the grading initiative lead to suspending grading assessments until
2014.
1.8.4 Water Quality 2015-25
The
targeted water quality grading for the entire City is a minimum of:
i) Source and treatment:
Maintain Ministry of Health A grading (Completely satisfactory – extremely low
level of risk).
ii) Distribution: Maintain Ministry of Health b grading
(Satisfactory – very low level of risk).
iii) A water supply system
that fully meets the sampling and test standards of the Drinking Water
Standards for New Zealand 2005/08.
iv) Performance Measurement
and Monitoring
v) Measure quality in
accordance with the Drinking Water Standards for New Zealand 2005/08.
vi) Record compliance with
Ministry of Health grading.
vii) Record compliance of
premises with backflow prevention requirements.
1.8.5 Water Quality Investigations
As a
result of the water grading review 2014/15, 11 demerit points out of the 15 received were attributed to the
following areas of water quality and risk:
i) Backflow Prevention (4
demerits). Backflow prevention is required on all high risk activities to
protect the water network from contamination. Budgets for the installation of
the commercial/industrial backflow prevention devices are shown in this asset
management plan. Work will proceed as the expenditure is approved through
annual and long term plans.
ii) Free Available Chlorine
Equivalent (FACE) Monitoring (1 demerit). Chlorine is added to the final stage of
the water treatment plant process as a long lasting disinfection product.
Council continuously monitors the levels of chlorine in the water leaving the
treatment plant and at the stoke high level reservoir but does not continuously
monitor for this in the wider network. Tests for available chlorine levels are
carried out multiple times per week on a rotation of sites through the city
when samples are taken to test for the presence of E.coli. Undertaking a
cost/benefit analysis of continuous chlorine level monitoring would be valuable
as a means of comparing the relative merits of the current practice versus the
enhanced option.
iii) Microbiological
Compliance (4 demerits). E.coli are both pathogens in their own right and also
important indicator organisms for the possible presence of other pathogenic
material associated with the wastes of animals (including humans). Although the
routine sampling that identified the presence of E.coli in the network also
confirmed that FACE was also present, a study of the network and some
investigation to try and identify possible sources of the contamination would
be valuable.
iv) Chemical compliance
(2 demerits). A number of chemicals are present in water supplies from natural
sources and resulting from reactions of disinfectants and the constituents of
the water. Testing of the network has identified levels of Haloacetic acids
that need to be monitored. Haloacetic acids result from the interaction of
chlorine with the components of water. In large quantities these can be
carcinogenic in some people. The link with i), ii) and iii) above should be
reviewed.
1.8.6 Action Plan
Over
the next three years the following are considered important to complete:
· Public
Health Risk Management Plan (Health Amendment Act 2013 changed this name to
“Water Safety Plans”) was approved by the Ministry of Health in August 2012.
This plan has to be reviewed within 5 years of this date ie by August 2017. In
addition the implementation of the plan is checked on an annual basis by the
District Health Board;
· Backflow
Prevention Plan. Installation of
backflow prevention devices on commercial and industrial properties to be
completed by 2025;
· Review
of FACE, Microbiological compliance and Chemical compliance with the aim of identifying
ways of reducing demerit points accumulated through the Drinking Water Grading
process;
· Review
requirements of National Policy Statement- Freshwater Management 2011 (NPSFM)
and Proposed 2013
amendments as they impact on the water activity.
1.9 Reliability
1.9.1 Statutory Obligations
Specific
consents issued under the Resource Management Act 1991 through the Nelson
Resource Management Plan (NRMP) control the abstraction of water from the
various sources.
1.9.2 Non-Statutory Standards
The Regional
Policy Statement (March 1997) contains the following statements:
“Policy DH1.3.4 To ensure that
any proposals for urban subdivision and/or development include adequate and
appropriate provision of services including waste disposal, stormwater, water
supply, electricity and other network services.
Policy WA2.3.1 To establish
minimum flow regimes for the Maitai, Roding, Wakapuaka and Whangamoa Rivers,
and any other river or stream under stress from water abstraction
Policy WA2.3.3 To allocate water
for abstractive uses, which provide for the social, economic and cultural well
being of the people of Nelson City where adverse effects (including impacts on
the needs of instream values necessary for the integrity of aquatic ecosystems)
can be avoided, remedied or mitigated.
Policy WA2.3.4 To continue to
encourage urban water supply conservation.
Method WA2.4.4 Council will
continue to educate the public on the need for water conservation and will
continue to monitor water use and assess the future needs of the community and
ways of meeting these needs in an environmentally sustainable way.
Method WA2.4.5 Council will
continue to implement and extend water metering.
Method WA2.4.6 Council, in
consultation with Tasman District Council, will investigate and, as
appropriate, implement water resource enhancement measures (including storage
and/or diversion) where necessary to provide adequate water for public water
supplies.
Method WA2.4.8 Subject to Policy 1,
surface water shall be allocated to the most efficient and highly valued users
of water, on the basis of:
i) The ability to achieve significant
community benefit from that use;
ii) The need for the volumes of water sought;
iii) Where appropriate, whether alternative
water supplies are available including recycling/reuse;
iv) The likely effects of any abstraction on
instream values;
v) Achieve any established minimum flow
regimes;
vi) Where appropriate whether mechanisms are
available to reduce or suspend abstractions during periods of low flow;
vii) Existing or foreseeable water abstraction
requirements for domestic and community supplies, agricultural, industrial and
other consumptive needs; and
viii) The impact of the application on any
established minimum flow regimes.”
Method WA2.4.9 Where flow in a
river falls to the conservation flow level, to suspend further non-essential
abstraction from that river except where an approved “Water Conservation Plan”
exists. Where an approved Water
Conservation Plan exists, abstraction between conservation flows and minimum
flows will be permitted.
1.9.3 Background
In
its strategic goals, Council has determined that the urban water supply should
have the capacity to withstand a 1 in 60 year drought.
The
Council re-adopted a Water Supply Conservation Strategy in 2003.
An
analysis of the flows in the South Branch of the Maitai river by Tasman
District Council hydrologists has indicated that low flows for the 1, 50, 90
and 100 year return period droughts are as follows:
1
year: 203 litres per second
50
year: 90 litres per second
90
year: 84 litres per second
100
year: 83 litres per second
The
conditions of the Resource Consent for the Maitai abstraction require that a
residual flow of 175 litres per second be left in the Maitai River from 1
November to 30 April, and 300 litres per second be left in the river from 1 May
to 31 October. However, if the river flow is naturally low during this period,
the residual flow may be reduced. When
the mean daily flow exceeds 140 litres per second the minimum flow is 300
litres per second. When the mean daily
flow is less than or equal to 140 litres per second the minimum flow is 225
litres per second. When the mean daily
flow is less than 130 litres per second the minimum flow is 190 litres per
second. The storage held in the Maitai
dam is used to make up the shortfall in natural flows.
The
conditions of the Resource Consent for the Roding abstraction require that from
1 July 2008 a residual flow of 100 litres per second be left in the Roding
River.
The
Council has entered into an Engineering Services Agreement (2005) with Tasman
District Council regarding the supply of Roding water to Richmond and the use
of the Waimea Supply to serve the Wakatu Industrial Estate, and development off
Champion Road and Hill Street North. The supply of water to ENZA and the
Alliance Group processing plant is not part of this agreement and remains the
responsibility of Tasman District Council.
This
agreement combines the other cross boundary infrastructural service of sewer
reticulation into one agreement for a five year term with either party required
to give a minimum of two years notice of intention not to renew the agreement.
In
July 2015 the Agreement with As of March 2014 the agreement is being re-negotiated with Tasman
District Council was renewed.
The current agreement
remains in force until such time as a new agreement is finalised.
Under
this asset management plan consideration is given to investigating the supply
of these areas by Nelson City.
The
Nelson City Council Land Development Manual 2010 sets out requirements for the
design and construction of urban water supplies (e.g. material types, size of
pipe).
Water
supply networks are historically very reliable, with many customers not
experiencing a single loss of supply event. This extremely high reliability has
tended to make customers assume that reliability is guaranteed.
As a
consequence customers are becoming less tolerant of interruptions to the
supply. Some industrial and commercial
processes which are reliant on a continuous water supply have assumed a
continual supply and have no provision for standby facilities.
The
continuity of supply can never be guaranteed, in part because many causes of
supply failure are beyond the control of the water supply authority. An example is damage to a service main that
could be caused by a contractor excavating in the street while working on other
utilities (such as electricity, telephone, sewer, etc). Older asbestos cement pipes have deteriorated
and are the main source of spontaneous breaks.
The
Nelson City Council Water Supply Bylaw warns that continuity of supply is not
guaranteed.
Apart
from the need to provide very high levels of continuity to meet customer
expectations, there are good public health reasons for maintaining pressurised
mains at all times.
If
watermains are allowed to lose pressure, it is possible that the weight of
water in lower sections of mains will reduce the pressure in higher sections of
the mains below atmospheric pressure.
This will cause a vacuum in pipes which can suck back groundwater into
the mains through leaks, or contaminated water from tanks or other containers
not properly isolated from the public supply.
Council
has established well defined procedures for shutting down watermains by Council
staff, the Utilities Maintenance Contractor’s staff, and Water Connection
Contractor’s staff.
The
objective of the procedures is to minimise the amount of disruption and
inconvenience to customers by using good communication skills and by timing the
work to avoid times of peak demand.
1.9.4 Level of Service for Reliability
i) Security of Supply
Over a 20 year forward
planning horizon, ensure adequate quantities of water to meet reasonable (in
compliance with resource consent conditions and Water Bylaw) peak demand
through a 1 in 60 year drought.
ii) Continuity of Supply
a) A continuity of supply of 99.5% (this
represents maximum interruption of supply to any property of 35 hours in any
year).
b) Maximum duration of any disruption in
supply – 24 hours.
c) Normal duration of any disruption in supply
to not exceed 8 hours on 95% of occasions.
d) Shutdowns for planned work or minor leak
repairs (not causing property damage or excessive water loss) will be carried
out in a daily off peak time (i.e. not 7.00am–9.00am, 12 noon–1.00pm or
5.00pm–9.00pm any day and not Saturday or Sunday morning 7.00am-11.00am).
e) Shutdowns for planned work that will have
major impact on the community will be carried out outside normal business
hours.
iii) Notice of Shutdown
a) Verbal advice will be given
to schools, hospitals, dialysis patients, industrial and commercial premises of
a planned shutdown less than one hour in duration.
b) A minimum of 24 hours notice
will be issued to all affected customers of a planned shutdown greater than one
hour in duration.
1.9.5 Performance Measurement and Monitoring
The
following actions are currently undertaken to monitor the network reliability:
i) Record daily headworks
supply and treatment plant supply.
ii) Record the actual time the
water supply is interrupted and restored, and number of properties affected.
iii) Record all complaints
regarding “out of water”.
iv) Record time and type of
notice of shutdown given to consumers.
v) Monitor peak daily demands
annually and maintain graphical record to develop future demand curve.
1.10 Pressure
1.10.1 Statutory Obligations
No
defined statutory obligation. However the Public Heath Grading of Community
Water Supplies 2003 Explanatory Notes and Grading Forms imposes distribution
grading “demerit points” where there is:
· Pressure
in excess of 900 kPa in more than 5% of the zone; or
· Pressures
less than 100 kPa; or
· Pressures
lower than 150 kPa in significant parts of the zone during high demand.
1.10.2 Non-Statutory Standards
New
Zealand Fire Service Firefighting Water Supplies Code of Practice 2008 requires
10m head residual running pressure, i.e. pressure remaining in the pipe after
abstraction of the fire fighting water.
The
Nelson City Council Water Supply Bylaw does not guarantee any specified maximum
or minimum pressure.
NZS
4404: 2010 Land Development and Subdivision Engineering recommends water supply
pressure shall be between 250 kPa and 800 kPa (25m to 80m head)
Water
supply levels were set in the Nelson City Council Resource Management Plan to
ensure adequate supply pressure for new developments. These generally are the 67 metre contour
where the area is supplied at Low Level Pressure and the 110 metre contour
where the area is supplied at High Level Pressure
1.10.3 Background
i) Pressure Fluctuation
At present, Nelson’s
water supply is predominantly gravity fed from covered storage reservoirs. This means the elevation of the Water
Treatment Plant Clearwater reservoir and Stoke High Level Reservoir determines
which areas of the City can be supplied and how much pressure is provided.
Each supply area is
further broken down into high level and low level areas. The high level areas work on the full mains
pressure generated by the difference in elevation between the reservoirs and
the point of supply.
The low level areas
have the supply pressure stepped down by pressure reducing valves. This is to protect the mains and domestic
plumbing installations from continuously operating under excessively high water
pressures.
The Clearwater
Reservoir at the Water Treatment Plant is normally used to directly supply the
area encompassed by Atawhai, the Brook Valley, Bishopdale, the Port Hills, the
Port, and via the Thompson Terrace Reservoirs to Tahunanui and the Tahunanui
hillside, and at times Stoke. The
reservoir has an effective elevation of 155m above City Datum.
The Saddle Break
Pressure Tanks and Stoke High Level Reservoir on the foothills cross-City link
between the Brook and Enner Glynn Valley are at an elevation of 255m above City
Datum (but the pressure is lowered in Marsden Valley by a pressure reducing
valve to 170m above City Datum) and is used to supply Stoke.
The difference in
elevation between the two systems means that properties on the Stoke high level
areas can experience pressure fluctuations of at least 150kPa (15m head). This fluctuation in cold water pressure (and
flow rate) adversely affects showers, washing machines, dishwashers, etc.
The maximum available
pressure is called the static pressure.
This occurs overnight during the low flow period. As demand increases in a pipe network, the
friction of the moving water in the mains causes a reduction in pressure known
as friction loss.
The working pressure
(that experienced by the customer) is the static pressure less the friction
loss. Demand varies though the day and
year. With increased demand, customers experience lower pressures during the
day and in summer. A difference between
static pressure and working pressure of more than 35% is considered excessive.
ii) Minimum Pressure
The minimum working
pressure at the ground floor level of buildings should ideally be not less than
300kPa (30m head) with an absolute minimum of 150kPa (15 metre head) in
exceptional instances. The water supply
levels in the 1996 Resource Management Plan were set at 67m (low level zones)
and 110m (high level zones) to ensure these standards are met for all new
developments.
In some of the more
recent hill top developments above the water supply level, the issues of
continuity of supply and pressure fluctuations have been resolved by the
installation of storage tanks and in some cases pump stations (e.g. Observatory
Hill, Austen Ward Heights, Panorama Drive, Springlea, Wastney Terrace.) To
avoid the need for water towers and allow maximum land development, the
standards have been eased so that:
a) Dwellings with ground floor
level less than 30m below the floor of the reservoir are required to install a
domestic pressure pump and tank to ensure adequate pressures. Oversize service connections are provided to
minimise friction losses.
Conditions Book
entries advise of these special circumstances.
The system works well as the presence of the storage tank ensures
continuity of supply.
iii) Maximum Working Pressure
The maximum pressure
normally targeted would be in the order of 600kPa (60m head). Due to Nelson’s
hilly terrain and the ample pressure generated by the elevation of the
headworks, Nelson City Council pressures are substantially higher.
In the lower areas of
the city, static pressures can range from 400kPa to 950kPa. (40m to 95m
head). Pressures in some of these areas
have been reduced over the last 20 years (in particular, the Port and the
residential areas of Stoke and Tahunanui on the seaward side of State Highway
6), by installing new pressure reducing valves, adjusting down existing
pressure reducing valves, or installing new mains. This can cause difficulties where plumbing
and sprinkler systems have been designed for existing water pressures.
Pressures in the 60 to
95m head range are still acceptable for domestic supply, although not ideal,
and may need reviewing in the future.
Excessive pressures
can lead to early failure of mains and contribute to problems of Unaccounted
for Water losses (Section 3.3.3).
Of more concern are the
areas on the edge of high pressure zones (in particular, the bottom of the Port
Hills, the Tahunanui Hills, Toi Toi Valley, Washington Valley and the
Grampians. As a cost saving measure when
the City was developed, these areas were served by the high pressure mains that
also carry water to the top of the hills.
Static pressure in some of these areas is in the range of 1400kPa to
1800kPa (140m to 180m head).
These pressures are in
excess of normal working pressures. It
is likely that most of these residents have installed their own pressure
limiting valves. As mains in these areas
are relaid the opportunity is taken to provide additional capacity and change
them over into the pressure reduced zone.
$600,000 is included in the Capital
budget over the next 12 years i.e. $50,000 per year until 2026/27, for system improvements including the
installation of new pressure reducing valves and mains to address this problem
of excess pressure.
$10,232,000 is included in the
capital budget over the next 12 years i.e. $405,000 in 2012 and then $250,000 per year until
2018 to lay new mains to facilitate lower pressures.
1.10.4 Level of Service for Pressure
With
the exception of hillside development served by local storage tanks and
pressure pumps, provide a water supply of suitable pressure such that:
i) The maximum fluctuation
between the static pressure and working pressure at each property does not
exceed 35% from the average pressure received by each customer.
ii) The minimum working head
at the ground floor level of each property is not less than 300kpa (30m head)
excluding friction losses in the private pipework.
iii) The maximum static head
at the ground floor level of each property does not exceed 900kPa (90m head).
1.10.5 Performance Monitoring
In
2011 the water network model identified:
i) 4.2% of properties have
pressure fluctuations exceeding 35%;
ii) 1.4% of properties have
water pressure below 300 kPa;
iii) 18.4% of properties have
water pressure in excess of 900 kPa.
In
2012/13 the water network model identified:
i) 0.2% of properties have
pressure fluctuations exceeding 35% of the average pressure supplied;
ii) 1.4% of properties have
water pressure below 300 kPa;
iii) 14.9% of properties have
water pressure in excess of 900 kPa.
1.10.6 Action Plan
i) Routinely calibrate the
accuracy of the Network Analysis model so that reliable predictions are
provided.
ii) Target pressure
correction work so that areas of the network with most consumers and greatest
pressure problems are corrected first.
1.11 Flow Rate
1.11.1 Statutory Obligations
New
Zealand Fire Service Firefighting Water Supplies Code of Practice 2008
specifies volume and pressure requirements for the water supply system within
the Urban Fire District.
1.11.2 Non-Statutory Standards
The
Nelson City Council Land Development Manual 2010 specifies minimum demand
figures that must be allowed for when designing new work.
1.11.3 Background
The flow
rate available to each customer is the greatest influence on the customer’s
impressions as to the adequacy of the water supply. Low flow rates cause water to dribble from
shower heads and fill basins and baths slowly.
Many
low flow problems are caused by inadequacies of the plumbing within the
property and this is beyond the control of the Nelson City Council. Therefore the level of service is defined at
the point of supply (the toby or service valve).
Flow
rate requirements can be divided into three categories:
i) Domestic Flow Rates
Customer expectations
have changed in the last 35 years and whereas 20 litres per minute was
previously considered adequate customers now expect 30 litres per minute.
30 litres per minute
is the standard aimed for in Nelson.
Provided the minimum pressure standards discussed in Section 2.4.4 are
achieved then this flow rate should be readily available.
One of the symptoms of
excessive pressure is too high a flow rate.
This can cause water from the cold tap to bounce out of sinks and basins
and creates water hammer in both the property’s plumbing and the water
reticulation system when automatic valves in dishwashers and washing machines
close off.
To alleviate these
symptoms residents partially close the stopcock at the boundary. This practice shortens the life of the
stopcock and increases the Council's maintenance costs.
Resolution of the
excessive pressure problem will solve this problem.
ii) Industrial/Commercial
Flow Rates
The flow rates
required by industrial processors are specific to each individual site. These are almost impossible to predict in
advance so reticulation systems in industrial areas are provided with
additional capacity.
With the exception of
the Port Area, any proposal to use large volumes of water will be restricted by
the capacity of the existing local mains to deliver the water and the sewerage
system to convey and treat the effluent.
Commercial areas as
distinct from industrial areas generally have low water demand except for fire
fighting.
iii) Fire Fighting Flow Rates
The public supply is
designed to provide an effective fire fighting network. Hydrants are installed
on all service mains in urban supply areas in accordance with the New Zealand
Fire Service Firefighting Water Supplies Code of Practice.
The New Zealand Fire
Service issued a revised Firefighting Water Code of Practice in 2008.
The required fire
fighting water supply for each building (other than single or multi-unit
housing but excluding multi-storey apartment blocks) must now be calculated for
the floor area of the building and the fire hazard category involved rather
than being read directly from a table as previously. Any deficiencies identified for particular
premises would have to be remedied by the owner by increasing the fire fighting
water supply, reducing the fire hazard in order to meet the requirements of the
code, or installing a fire sprinkler system.
The required flow for
single or multi-unit housing (but excluding multi-storey apartment blocks) is
25 litres per second with a minimum of 12.5 litres per second from a hydrant
within 135 metres of the risk and a further minimum of 12.5 litres per second
from another hydrant within 270 metres of the risk.
Previous versions of
this code of practice measured the distances from properties to fire hydrants
as a radius centred on the property, the current version now measures the true
“along the road” distance. This has had
the effect of now increasing the number of properties that do not currently
meet the distance requirement.
The Fire Service Code
of Practice allows that where there is a reliably calibrated and accepted
system for computer modelling of flows in a reticulated water system, the Fire
Service may accept the outputs from such modelling in place of testing certain
fire hydrants.
Generally domestic
demand is not critical and the supply of water for fire fighting purposes will
determine the reticulation pipe sizes required.
Problems with
inadequate hydrant flows are experienced in some of the older areas of the City
where the original 75mm and 100mm diameter cast iron water mains are incapable
of delivering the flow rates required.
Renewal work in recent years has concentrated on replacing these mains. The programme of replacing all 75mm diameter
cast iron mains in the City was largely completed in 2006/07. This work also helped to address the problems
with fluctuating and low pressures outlined in Section 2.4.3.
$600,000 is included in the Renewals
budget over 4 years
i.e. $100,000 per year
from 2015/16 to 2018/19,
for upgrades to the water network in areas where the fire flows are not being
delivered. The areas to be upgraded will be regularly reviewed and identified
using the water network model.
1.11.4 Level of Service for Flow Rate
To
provide a reticulation network that delivers fire hydrant flows that comply
with the New Zealand Fire Service Firefighting Water Supplies Code of Practice
2008. This is generally 25 litres per
second in residential areas (12.5 l/s from each of 2 hydrants) and varying
flows in Commercial/Industrial areas depending upon the fire hazard (low–medium
hazards require 50l/s – 150l/s from a range of operating hydrants).
1.11.5 Performance Measurement and Monitoring
i) Record flows
ii) Determine theoretical
flows by use of computer model
1.11.6 Action Plan
i) Target
flow correction work so that areas with most consumers and greatest flow
problems are corrected first. Develop plan for properties identified in
2011. See A706990.
1.12 Emergency Response
1.12.1 Headworks
The
Maitai and Roding headworks are manned by resident caretakers employed by the
Water Treatment Plant contractor. During
the caretaker’s absence, resident relief caretakers are employed.
1.12.2 Water Treatment Plant
The
Tantragee Water Treatment Plant is manned during normal working hours. After hours and on weekends, operators are
able to monitor the plant remotely via a computer dial in system.
The
operators also carry cell phones that are linked to the plant control
system. Outside working hours, alarms
are immediately sent to cell phones, so that the operators can respond
immediately.
1.12.3 Supervision
The
Nelson City Council Utilities operations and maintenance duty staff carry cell
phones on a weekly roster so that at all times a Nelson City Council Operations
and Maintenance staff member is available to respond to major network faults or
faults that have been escalated by the Treatment Contractor or Network
Maintenance Contractor.
1.12.4 Contractors Service Response and System
Operation
The
Utilities Services Maintenance contract requires that the maintenance
contractor responds to calls within appropriate times depending on the
circumstances as follows.
i) Urgent
Works
Urgent works are
defined in the first column of the response timetable below in Table 2.5.
Response times apply
24 hours per day every day of the year.
The Contractor must
respond to and satisfactorily resolve maintenance works within the maximum
response times for the specified percentage of cases.
Table 2.5 Urgent Maximum Response Times
|
Definition of Urgent Works |
Investigation and Appraisal |
Repair Completed |
% of Cases |
|
·
Burst pipes or major
leakages likely to affect the water supply or cause damage to pavements or
property. |
·
30 minutes |
·
8 hours |
·
95% |
|
·
No water or pump station
failure. |
·
30 minutes |
·
8 hours |
·
95% |
|
·
Possible serious health
risk (life threatening) water quality problem. |
·
30 minutes |
·
2 hours |
·
100% |
i) Non-Urgent Works
Non-Urgent works are
as defined in the first column of the response timetable below in Table 2.6.
Response times defined
in hours apply 24 hours per day every day of the year.
Response times defined
in days are working days (Monday to Friday) excluding public holidays during
normal working hours. Such works are
programmed by the Contractor on a daily basis.
The Contractor must
respond to and satisfactorily resolve maintenance works within the maximum
response times in Table 2.6.
Table 2.6 Non Urgent Maximum Response Times
|
Definition of
Non-Urgent Works |
Investigation and Appraisal Night and Day |
Repair Completed |
|
·
Minor leaks including from
fittings, connections, meters, etc on sensitive hill slopes as identified on
drawing 34/78. Missing or damaged
service lids. |
·
1 hours |
·
24 hours |
|
·
Minor leaks including from
fittings, connections, meters, etc in areas other than above. |
·
12 hours |
·
3 working days |
|
·
Water Quality Problems: ·
- Taste and odour ·
- Colour and grit |
·
2 hours |
·
1 working day |
|
·
Non-serious water quality
problems including poor pressure and flow. |
·
N/A |
·
3 working days |
|
·
Engineers discretionary
work |
·
N/A |
·
As agreed |
1.13 Environmental
1.13.1 Statutory Obligations
The
Resource Management Act 1991
The
Nelson Resource Management Plan
Specific
consents issued under the Resource Management Act 1991 control the abstraction
of water from the various sources. The
conditions include maximum abstraction rates, residual flows which must be
maintained in the river, temperature and quality of compensation flows, and
biotic monitoring in the rivers.
1.13.2 Level of Service
Comply
with resource consents RM025151 and RM975374 conditions for allowable water
abstraction rates, revegetation of stream banks and eel and fish passage
requirements.
1.13.3 Performance Measurement and Monitoring
Record
natural river flows, abstraction flows, mitigation flows, river temperatures,
and water quality and biotic diversity and density.
1.13.4 Action Plan
i) Ongoing monitoring of
Resource Consent conditions.
ii) Begin preparations for lodging applications for new resource consents for the Maitai Dam, Roding Dam plus abstraction.
1.14 Existing Situation
As
noted in Section 2.3.3 the aim is to have the capacity to withstand a 1 in 60
year drought with only sprinkler and hosing restrictions until at least
2035. Outputs in this demand section are
therefore calculated on this basis.
Water
for the city is extracted directly from both the Maitai and Roding rivers,
piped to the treatment plant at the Tantragee saddle and then delivered to the
city.
Water
from the Maitai river is extracted from a run of river intake on the South
Branch of the headwaters or from the Dam reservoir on the North Branch. The dam has been constructed on the North
Branch to store water for use in low flow periods and for supplementary water
flows to compensate for extraction from the South Branch.
An
analysis of the flows in the South Branch of the Maitai river by Tasman
District Council hydrologists has indicated that low flows for the 1, 50, 90
and 100 year return periods are as follows:
1
year: 203 litres per second
50
year: 90 litres per second
90
year: 84 litres per second
100
year: 83 litres per second
The
Maitai Dam was designed to meet a peak demand of 37,000m3/day through a 75 year
return period drought but has the capacity to supply water at the rate of
50,000m3/day through a 60 year return period drought. With the completion of the Water Treatment
Plant a further 900,000m3 of water from the bottom of the Maitai Lake can be
treated and used for city supply.
However, pumping will be required to transport this water to the
treatment plant. This additionally
available water may need further conditioning prior to use as potable water to
address low oxygen levels, elevated organic material levels and heavy metal
concentrations.
The
existing Maitai pipeline has a maximum capacity of approximately 37,000m3/day.
The
Roding Dam has only limited storage and is a run of river intake. Provided there is an adequate flow in the
river the Roding pipeline can deliver a maximum of 22,000m3/day. The estimated flow in the Roding River in a 1
in 60 year drought is 11,200m3/day.
However,
the Resource Consent for water extraction from the Roding requires that from 1
July 2008 a minimum flow of 100 litres per second be left in the river.
100
litres per second (94 litres per second at the intake) equates to 8,122m3/per
day. The available abstraction from the
Roding River is therefore 3,100m3/day in a 1 in 60 year drought.
The
current dry weather capacity of the water supply system, limited by the
capacity of the existing Maitai delivery pipeline, from 1 July 2008 is:
Maitai 37,000m3/day
Roding 3,100m3/day
40,100m3/day
but
with the completion of the duplicate Maitai pipeline the 1 in 60 year drought
capacity will be:
Maitai 50,000m3/day
Roding 3,100m3/day
53,100m3/day
However,
the Roding resource consent also requires that if Tasman District Council
ceases taking water from Nelson City, the residual flow in the Roding River
shall be increased by 10.5 litres/sec which is 907m3/day. It is likely that Tasman District Council
will cease this take when the proposed Lee Valley Dam is completed.
The 1
in 60 year drought capacity would then be:
Maitai 50,000m3/day
Roding 2,193m3/day
52,193m3/day
The
current capacity of the Tantragee Water Treatment Plant is approximately
41,000m3/day. Addition of further
membranes to commission the fifth train would increase capacity to
50,000m3/day. New technology high
capacity membranes are expected to extend the plant capacity even further.
The
foothills link from the Roding River (Marsden Valley) to the Water Treatment
Plant has a maximum capacity of 22,000m3/day.
This allows the Maitai pipeline to be shut down for maintenance other
than during the peak summer demand. The
normal flow is 16,000m3/day to reduce pumping costs. However, when the Maitai Dam spillway stops
flowing i.e. when the lake level is below the crest, and there is still
sufficient flow in the Roding, Roding water can be used to supply the City, up
to the maximum allowed by the resource consent (residual) thereby minimising
draw off of stored water from the Maitai Dam.
The principal
trunk link between the Water Treatment Plant and Stoke is the foothills link to
Marsden Valley. This has a capacity of
16,000m3/day. Because water in the
foothills link is pumped, the use of the Marsden Valley route for treated water
is minimised to reduce operating costs.
The
other trunk link between the Treatment Plant and Stoke is through the Thompson
Terrace reservoirs. The size of the
trunk mains and the elevation of the reservoirs restricts the gravity flow
through this link to approximately 11,000m3/day. However, a booster pump station in Van Dieman
Street increases the peak capacity to 14,500m3/day.
The
supply capacity to Stoke and Tahunanui is:
Foothills Link 16,000m3/day
Cross City Link 14,500m3/day
30,500m3/day
1.15 Demand Forecast
1.15.1 Industrial and Commercial Demand
i) Since the water demand
was initially calculated in 1996 there have been significant changes in
Industrial and Commercial activities (and therefore water demand) at the Port.
ii) Fin fish quotas are
reduced, catches are down, and more processing is carried out at sea or in
Asia. The Sanford (South Island) Ltd
processing factory at the port has closed and is unlikely to reopen. It is also unlikely that any other similar
fish processing factory will be established in Nelson in the forseeable future.
iii) Port Nelson has
increased container and log marshalling areas with the demolition of existing
buildings, including the Milk Treatment Station. Further expansion of these areas is likely,
until ultimately the area bounded by the existing gated area at Graham Street,
Wildman Avenue, and the Calwell Slipway becomes port storage.
iv) Current fuel storage areas
are likely to decrease. The current BP
Oil NZ Ltd tank site is likely to revert to the Port Company in 2025 and become
a cargo storage area. Tank storage
volume may increase on the other existing site, but the bunding area will still
be required, and the land will not be available for other development.
v) Current engineering
activities are likely to remain around the slipway area, and current boating
activities are likely to remain around the marina area. These activities are not significant water
users.
vi) While total demand from
the Port area has steadily fallen from 1999, growth of 0.5% per annum (10.5% over
10 years) has been assumed from 2005 for demand purposes.
vii) Commercial/industrial
growth in the remainder of the City/Atawhai area is expected to be restricted
by lack of suitable land availability and limited sewer capacity. The Nelson Resource Management Plan limits
Trade Waste discharge to the sewer to 0.54 litres per second per hectare. Sites in the Central City and St
Vincent/Vanguard Streets area are generally small and a major wet industry is
not likely to set up in this area. The
recent development of New World and Harvey Norman stores in Vanguard Street,
together with their associated car parking, has further reduced
commercial/industrial land available for wet uses. Commercial users generally have a low water
demand.
viii) Recent Commercial/industrial
growth in the Stoke/Tahuna area has utilised most of the existing industrial
zoned land.
ix) The Nelson Urban Growth
Strategy consultation document suggested that 50 to 80ha of industrial land is
required for each 10,000 of population.
An average 65ha has been assumed.
x) The Nelson Urban Growth
Strategy consultation document suggested that there are limited options for
industrial growth within Nelson City.
Three options were identified:
· A
small additional area on Vanguard Street on flat area up to Northesk Street for
service industry (not generating air emissions/noise issues). Area of 2.5 hectares.
· Rationalisation
of the Tahunanui industrial area to make more use of the land – currently large
areas such as timber yards – where there is potential for more intensive
uses. Area of approximately 10 hectares.
· Coordination
with Tasman District Council regarding development of new land in Richmond
vicinity for industrial uses taking a regional planning approach. i.e. Industrial growth in Nelson will be low
water users on small sites.
xi) For the period 2005-2021
it has been assumed that new industrial growth will be located
· 46%
Stoke
· 46%
Tahunanui
· 8%
City
· 0%
Port
xii) For the period 2022-2051 it
has been assumed that:
· Stoke/Tahunanui
will have no land available for industrial growth
· The
necessary industrial land will be in the City area (created by further rezoning
in the Victory area, further reclamation adjacent to Akersten Street, or by
rezoning in the vicinity of the Nelson North Wastewater Treatment Plant).
xiii) It is also assumed that
Tasman District Council will continue to supply Alliance Nelson Ltd, Wakatu
Industrial Estate, and ENZA Foods Ltd through the Waimea Supply until 2021.
Nelson City Council could take over this supply and would be able to meet the
reduced demand requirements through a 1 in 60 year drought, with
restrictions. However mains would be
required in Stoke to provide sufficient pipe capacity. Further work is required
to evaluate actual industrial demand and costs to service this area.
xiv) Some potential for
industrial development has also been identified for the Wakapuaka flats adjacent State Highway
6, the Boulder Bank and the Glen Road. Currently a small area is being used for
aquaculture research and development. Council would be unable to supply large
volumes of water to this area without substantial upgrades of the trunk main.
xv) A review of the industrial
demand is expected over the next three years as Council reviews the Nelson
Resource Management Plan. The likely impact on the water network will be
reflected in future asset management plans.
1.15.2 Residential Demand
i) Residential
growth is based on Council’s adopted growth forecasts from Statistics New
Zealand 2012 population projections.
Tables
3.1, 3.2 and Figure 3.1 show the population figures that would result from the
growth projections used.
Table 3-1: Nelson City Population Projections
2011 – 2045. From Statistics New Zealand 2015 (A1393084)
|
|
2013 |
2015 |
2025 |
2045 |
|
Population |
48,700 |
49,740 |
53,320 |
56,020 |
|
Households |
|
20,470 |
22,310 |
24,150 |
|
Median
age |
42 |
43 |
46 |
50 |
|
Aged
65 years and over |
8,400 17% |
9,160 18% |
13,120 25% |
18,540 33% |
|
Aged
15-64 |
31,100 64% |
31,380 64% |
31,360 59% |
29,040 52% |
|
Aged
under 15 years |
9,200 19% |
9,200 18% |
8,780 16% |
8,260 15% |
Figure 3-1: Population Projections

Table 3-2: Nelson City Population Projections 2011
– 2045. From Statistics New Zealand 2015 (A1393084)
|
POPULATION |
2013 |
2015 |
2025 (change
between 2015 and 2025) |
2045 (change
between 2025 and 2045) |
TOTAL CHANGE between
2015 and 2045 |
|
|
NELSON |
48,700 |
49,740 |
53,320 |
56,020 |
+6,280 |
|
|
|
STOKE |
17,930 |
18,410 |
20,180 |
22,380 |
+3,970 |
|
TAHUNA |
5,510 |
5,590 |
5,930 |
6,110 |
+520 |
|
|
CENTRAL |
19,760 |
20,080 |
20,960 |
20,730 |
+650 |
|
|
NORTH |
5,480 |
5,650 |
6,240 |
6,780 |
+1,130 |
|
|
HOUSEHOLDS |
2015 |
2025 (change
between 2015 and 2025) |
2045 (change
between 2025 and 2045) |
TOTAL CHANGE between
2015 and 2045 |
|
|
NELSON |
20,470 |
22,310 |
24,150 |
+3,680 |
|
|
|
STOKE |
7,470 |
8,330 |
9,510 |
+2,040 |
|
TAHUNA |
2,460 |
2,650 |
2,810 |
+350 |
|
|
CENTRAL |
8,310 |
8,820 |
8,990 |
+680 |
|
|
NORTH |
2,270 |
2,550 |
2,850 |
+580 |
|
Stoke Demographics
Census Data
|
Stoke |
Census 2006 |
Census 2013 |
|
Usually resident
population |
15198 |
17163 |
|
As a % of Nelson |
35% |
37% |
|
Households in
private dwellings |
5850 |
6726 |
|
As a % of Nelson |
35% |
36% |
Projections
|
|
2015 |
2025 |
2045 |
|
Stoke |
|||
|
Population |
18,410 |
20,180 |
22,380 |
|
Population change |
|
+1,770 |
+2,200 |
|
Residents aged 14 and under |
3,400 (18%) |
3,370 (17%) |
3,420 (15%) |
|
Residents aged 65 and over |
4,070 (22%) |
5,400 (27%) |
7,350 (33%) |
|
Number of households |
7,470 |
8,330 |
9,510 |
|
Housing change |
|
+860 |
+1,180 |
i) The current peak
residential demand for Stoke and Tahunanui is assumed as 0.843m3/head/day and
for the City and Atawhai 0.463m3/head/day.
This difference occurs because more water is likely to be used in Stoke
and Tahunanui for garden and lawn irrigation as the land is more gravel soil,
and receives all day sun, whereas in the Central City and Atawhai the sections
are generally steeper, have clay soils and often shaded for part of the day.
ii) It is assumed that by
2021 Richmond will not be taking water from Nelson as by then the Waimea Water
Augmentation dam currently being investigated for the Lee River is expected to
have been built. However the current
resource consent requires that if Tasman District Council ceases to take water
from Nelson, then the residual flow be increased by 10.5 litres per second =
907m3/day.
iii) Residential demand for
2021 is assumed to be the 2012 demand for houses existing in 2012 as in ii)
above and for new houses in Stoke/Tahunanui 0.5m3/head/day and City/Atawhai
0.4m3/head/day for the following reasons:
· Improved
plumbing and appliance technology, (particularly being driven by the Australian
water shortages), future household use will be reduced e.g. superlow flush
4.5/3 litre toilet flush (compared with 11 litre single flush), low use washing
machines, low flow shower heads, aerator taps, reuse of grey water for toilets
and irrigation etc.
· Increasing
awareness of low water use gardening e.g. drought resistant planting, no mow
lawns, or no lawns at all
· With
intensification, smaller gardens or no gardens at all for many household units
· Reduced
use due to reduced supply pressures
· Consumer
education on tap use e.g. turn off while brushing teeth, shorter duration
showers, showers instead of baths, rinsing dishes in a partially filled sink
rather than under a running tap
· Possible
greywater and rainwater storage on site for reuse
· More
stringent hosing restrictions
· Pricing
incentives
· Central
Government Regulation
iv) Residential demand for
2045 is assumed to be the reduced figures for all properties as over the next
30 years a number of currently existing houses are likely to be rebuilt,
refurbished or refitted so that all residences will have low water use fittings
and appliances. The 2045 peak residential
demand for Stoke and Tahunanui is assumed as 0.5m3/head/day (300 litres
essential use and 200 litres outside use) and for City and Atawhai
0.4m3/head/day (300 litres essential use and 100 litres outside use) and for
Hira 0.5m3/head/day (300 litres essential use and 200 litres outside use).
v) Richmond is entitled to
the lesser of 909m3 of water/day or 1/15 of the Roding supply rate. However, the resource consent states that if
Tasman District Council ceases taking water from Nelson City the residual flow
in the Roding River shall be increased by 10.5 litres/sec which is 907m3/day.
vi) Hira is a possible area of
expansion not covered by current supply.
vii) A plan change to the
Nelson Resource Management Plan is currently underway to recognise the
subdivision activity in the Saxton Creek area North of Champion Road. This area
is currently supplied with water by Tasman District Council. If the present
supply arrangement with Tasman District Council continues, this portion of the
growth will not need to be supplied from Nelson City sources. However the agreement may be revoked on 2
years notice by either Council. The
increased population supplied is therefore allowed for in the figures in Table
3.1 above and a project to upgrade reticulation to the area is identified in
the capital expenditure budget.
viii) Previous Council Urban
Growth Strategy documents also predict that some of the population growth will
be by intensification of housing in Atawhai, Central Nelson, Hospital,
Tahunanui and Stoke areas. This implies
that gardens will be smaller and the peak demand per population will reduce.
ix) Council is concentrating
on improving services to developed areas and providing services to areas that
are currently being developed (Residential, Rural Zone High Density Small
Holdings, Suburban Commercial, Industrial). Servicing of other areas covered by
the Services Overlay, because one or more servicing constraints have been
identified as needing to be addressed prior to the complete development of that
property/area, will be considered as Council develops a policy on prioritising
these areas. The specific projects to
facilitate future growth, identified in this Asset Management Plan, therefore
consist of works required to eliminate servicing constraints on the former.
x) A Map of the areas zoned for
growth but constrained by lack of services is attached in Appendix I.
Construction of services to these areas should be carried out in line with
Council’s prioritisation policy. Appendix I sets out a draft “INFRASTRUCTURE
PLANNING TOOL FOR GROWTH PROJECTS” that reflects infrastructure prioritisation
factors. In 2014 Council is expected to
consider a proposal to review the Nelson Resource Management Plan and look at
wider prioritisation criteria for future development areas. Infrastructure
planning will align with any new policy that is developed.
xi) A specific project has
been identified to update desktop investigations, carried out in the past,
looking at servicing constraints to areas currently zoned for residential
development but restricted by a services overlay.
xii) A review of the
residential demand is expected over the next three years as Council reviews the
Nelson Resource Management Plan. The likely impact on the water network will be
reflected in future asset management plans.
xiii) Figure 3.2 compares the
capacity of the water sources and water treatment plant with the actual peak
day water usage over the last 15 years.
1.15.3 Raw
Water Supplied:
The following table shows raw water supplied to
the WTP and Treated water from the WTP. Figures are based on daily flows for
the peak flow month for each year.
Table 3.3 Source of Raw Water
|
·
Year |
·
Source |
·
Minimum (m3/day) |
·
Average (m3/day) |
·
Maximum (m3/day) |
|
·
2012-13 (January) |
·
Maitai |
·
10,000
|
·
15,710
|
·
23,000 |
|
·
Roding |
·
0
|
·
7,677
|
·
13,000
|
|
|
·
WTP |
·
19,226
|
·
23,364
|
·
30,658
|
|
|
·
2013-14 (February) |
·
Maitai |
·
7,000
|
·
12,893
|
·
17,000
|
|
·
Roding |
·
9,000
|
·
11,036
|
·
14,000
|
|
|
·
WTP |
·
18,148
|
·
23,461
|
·
27,902
|
|
Water sources: Currently: Roding can reliably
deliver 3,100 m3 /day in a severe drought- limited by resource consent. The
pipeline currently can and does supply 16,000 m3 /day plus. Capacity is of
the order of 20-22,000 m3 /day. Existing concrete
maitai pipeline can deliver 37,000 m3 /day. The duplicate
pipeline is 600mmdia and can deliver the following( from opus optimisation
report may 2009) and compliance testing (august 2014): Without pumping
18,144 m3 /day. With two pumps
running 30,240 m3 /day. With additional
pumps installed it is possible to supply up to 50,000m3/day These are steady
state flows. The water reservoirs are used to buffer peak hourly demand. |
Figure 3.2 Peak Water Demand
Table 3.4 Peak Daily Demand
|
·
Year |
·
Peak Daily Supply
(m3/day) |
·
Year |
·
Peak Daily Supply ·
(m3/day) |
·
Year |
·
Peak Daily Supply ·
(m3/day) |
|
·
2000 |
·
30,900 |
·
2007 |
·
31,950 |
·
2014 |
·
27,900 |
|
·
2001 |
·
34,500 |
·
2008 |
·
31,200 |
·
2015 |
·
|
|
·
2002 |
·
28,570 |
·
2009 |
·
29,050 |
·
2016 |
·
|
|
·
2003 |
·
30,850 |
·
2010 |
·
28,170 |
·
2017 |
·
|
|
·
2004 |
·
31,680 |
·
2011 |
·
27,160 |
·
2018 |
·
|
|
·
2005 |
·
29,850 |
·
2012 |
·
28,070 |
·
2019 |
·
|
|
·
2006 |
·
30,500 |
·
2013 |
·
30,660 |
·
2020 |
·
|
Table 3.5 Total Daily Demand
|
Month |
2007-2008 |
2008-2009 |
2009-2010 |
2010-2011 |
2011-2012 |
2012-2013 |
2013-2014 |
|||||||
|
|
Maitai
(000m3) |
Roding
(000m3) |
Maitai
(000m3) |
Roding
(000m3) |
Maitai
(000m3) |
Roding
(000m3) |
Maitai
(000m3) |
Roding
(000m3) |
Maitai
(000m3) |
Roding
(000m3) |
Maitai
(000m3) |
Roding
(000m3) |
Maitai
(000m3) |
Roding
(000m3) |
|
July |
349 |
312 |
420 |
204 |
315 |
280 |
NA |
NA |
268 |
313 |
309 |
277 |
336 |
239 |
|
Aug |
388 |
307 |
319 |
298 |
381 |
220 |
NA |
NA |
286 |
315 |
444 |
140 |
367 |
212 |
|
Sept |
307 |
345 |
361 |
238 |
485 |
69 |
359 |
208 |
291 |
316 |
353 |
200 |
330 |
226 |
|
Oct |
424 |
267 |
323 |
299 |
364 |
256 |
348 |
252 |
318 |
258 |
394 |
196 |
403 |
172 |
|
Nov |
461 |
358 |
423 |
182 |
382 |
322 |
356 |
344 |
346 |
278 |
398 |
288 |
355 |
286 |
|
Dec |
457 |
323 |
447 |
179 |
435 |
306 |
413 |
252 |
441 |
194 |
429 |
300 |
421 |
273 |
|
Jan |
445 |
408 |
444 |
322 |
458 |
281 |
410 |
278 |
425 |
278 |
487 |
238 |
443 |
241 |
|
Feb |
378 |
394 |
345 |
330 |
403 |
307 |
348 |
330 |
325 |
331 |
376 |
271 |
361 |
309 |
|
Mar |
366 |
364 |
439 |
246 |
456 |
313 |
385 |
267 |
409 |
214 |
393 |
281 |
458 |
225 |
|
Apr |
342 |
318 |
381 |
247 |
483 |
208 |
398 |
178 |
319 |
268 |
365 |
195 |
418 |
173 |
|
May |
329 |
314 |
465 |
108 |
421 |
218 |
467 |
82 |
328 |
267 |
389 |
195 |
298 |
248 |
|
June |
346 |
264 |
329 |
255 |
412 |
197 |
349 |
209 |
363 |
189 |
385 |
153 |
318 |
211 |
|
Sub-Total |
4,592 |
3,974 |
4,696 |
2,908 |
4,995 |
2,977 |
NA |
NA |
4,119 |
3,221 |
4,722 |
2,734 |
4,508 |
2,815 |
|
Total (000m3) |
8,566 |
7,604 |
7,972 |
7,188 |
7,340 |
7,456 |
7,323 |
|||||||
The water demand projections
for the next 30 years have been calculated.
The results are shown in Table 3.6.
Table 3.6 Water Demand Projections (Peak Day 1 in
60 year Drought)

Note: The projected figures are subject to round
off error and may not add exactly to the totals shown.
Based
on historical use figures and the supply capacity of the Water sources and
treatment plant, Nelson has sufficient water to supply reasonable demands within
the city beyond 2050.
As
the population increases additional storage reservoirs will be constructed and
reticulation upgraded where development requires.
1.15.5 Covered Storage
Currently
the Maitai and Roding together are capable of supplying 40,100m3/day. However, demand is more typically spread over
a 16-18 hour period. Therefore storage
is required to make full use of the night time supply capacity and to meet
peaks in demand during the day.
This
storage is also needed to ensure continuity of supply in the event of a major
problem (e.g. headworks damage, or trunk main failure) and to provide
opportunities to carry out planned maintenance.
The
Public Heath Grading of Community Water Supplies 2003 Explanatory Notes and
Grading Forms imposes distribution grading “demerit points” where there is not
covered secure storage of 24 hours average daily demand.
The
targeted level of service is 24 hours storage (at average demand) located in
the area it is to serve. This standard is met for the smaller hilltop
reservoirs and tanks served by pumped systems or night time filling but not for
the larger zone reservoirs.
A
total of 21,000m3 of covered storage is required to meet the current average
demand.
Table
3.7 shows the current reservoirs.
Table 3.7 Current Reservoirs
|
Name |
Location |
Year Commissioned |
Capacity m3 |
|
·
Thompson Terrace No. 1 |
·
Ariesdale Terrace |
·
1961 |
·
2,500 |
|
·
Thompson Terrace No. 2 |
·
Ariesdale Terrace |
·
1974 |
·
5,500 |
|
·
Stoke No. 1 |
·
Marsden Valley |
·
1996 |
·
2,500 |
|
·
Stoke No. 2 |
·
Marsden Valley |
·
2006 |
·
2,500 |
|
·
Atawhai No. 1 |
·
Walters Bluff |
·
2002 |
·
2,500 |
|
·
Clearwater |
·
Tantragee WTP |
·
2004 |
·
3,000 |
|
·
Stoke High Level |
·
York Valley Saddle |
·
2011 |
·
2,500 |
|
·
Various smaller reservoirs
and tanks |
·
Various |
·
Various |
·
1,550 |
|
·
Current Total |
·
22,550m3 |
||
Panorama Drive (180m3), Observatory
Hill (300 + 440m3), Todds Valley (23+23+23+23+23=115m3),
The Glen (100m3), Dodson Valley Strathaven Pl (23+23=46m3),
Springlea Hghts (23+23+23+23+23=115m3), NorWest Way (23+23+23+23=92m3),
Leach Pl (23+23=46m3), Bishopdale (23+23+23+23+23=115m3).
Total = 1,550m3
Table
3.4 shows the reservoirs proposed for the 30 year planning period until
2044/45.
Table 3.8 Proposed Reservoirs
|
Name |
Location |
Year Proposed |
Capacity |
|
·
Atawhai No. 2 |
·
Bayview Road or Marybank.
Yet to be determined. |
·
2014-24 |
·
2,500 |
|
·
Future Growth Areas |
·
Nelson- North and
South.Yet to be determined. |
·
2034-38 |
·
5,000 |
|
·
Proposed Total |
7,500 |
||
In
the 2006-2016 Long Term Council Community Plan a high level reservoir was
proposed for Marsden Valley in 2015/16 to serve future growth. However development is already proceeding in
Marsden Valley and the reservoir has now been completed.
The
projected increase in demand caused by development north of Cemetery Point
means that Atawhai No. 2 reservoir (2500m3) will be required by about 2021/24.
Other reservoirs will be required to serve local growth.
· Malvern
Hills to serve the ridge between Botanical Hill and Dodson Valley. This smaller reservoir was shown in the 1998
LTFS for 2001/02 but has been deferred several times until required by
development. An options report to identify the best solution for the Atawhai
No. 2 reservoir and the upper levels reservoir is currently shown for
2014-2016. It is expected that this report will look at locations and options
for servicing the Atawhai area.
· The
need for other reservoirs as the city expands has been recognised and allowed
for, in general terms, in the capital expenditure tables but not scheduled by
exact location as the timing and location of future development is
uncertain. Should full residential
development proceed at Hira, several large reservoirs supplied by a trunk
watermain will be required.
1.16 Demand Management
1.16.1 Universal Metering
The
Council resolved to adopt universal metering in 1996 and a capital programme
installed a meter for every property.
Universal metering has been in operation since 1 July 1999. The maximum two day average in 1997/98 was
42,300m3/day, whereas the peak since universal metering has been in operation
is less than 35,000m3/day.
Although
the peak one day water usage prior to universal metering reached 42,000m3/day
the typical winter usage is in the order of 21,000m3/day. Given that there is virtually no fluctuation
in commercial water usage between winter and summer, the difference of
21,000m3/day must be attributed mainly to residential sprinkler usage, although
the summer holiday influx of visitors in late December and early January to
Nelson does have an impact.
This
means that to meet uncontrolled garden watering demand the water supply system
needs up to 100% extra capacity which is only used for approximately 10% of the
time.
As
noted above the introduction of universal metering has reduced the summer peak
by over 37%.
Peak
demand is most affected by summer drought and consequent garden watering. The drought of 2000/01 is estimated to have a
return period of 1 in 30 years. Other
years have been average or wetter than average and this is reflected in the
peak demands.
The
peak one day flows from 2000 to 2010 are plotted on Figure 3.1.
1.16.2 Other Demand Management
Use of
alternative water sources for non-potable water would reduce the demand from
the city water supply, particularly under summer conditions. While rainwater tanks and greywater reuse
have some appeal, there are further implications with these, such as:
· The
Ministry of Health/Department of Building and Housing reservations as to
greywater reuse.
· Financial
cost to householder.
· Size
of tank versus Nelson rainfall (seasonal pattern and total).
· Siting
of rainwater tanks on the property.
· Rainwater
tanks needs to be considered in the wider concept of sustainability, e.g.
environmental cost of producing, transporting and disposing of a tank.
· Plumbing
and appliance technology is rapidly advancing, particularly in Australia due to
the droughts, and these may actually give better water conservation than
tanks/greywater reuse e.g. Very low water usage dual flush toilets 4.5/3 litres
per flush compared with 11 litre standard, and normal 11 / 6 dual flush, low
water use clothes washers, low flow shower heads.
A
full evaluation of alternative non- potable water sources suitable for Nelson,
taking into consideration Nelson’s current and future weather patterns was
proposed in the previous Asset Management Plan. This work still needs to be
carried out when resources permit.
1.16.3 Unaccounted for Water
All
water reticulation networks are prone to leakage to some extent. Leakage occurs both from the public system
and from individual customer’s plumbing.
International research suggests 60% of losses occur on private
property. A slowly dripping tap can leak
40 litres within a 24 hour period, and collectively the total losses from
dripping taps can be very significant.
The introduction of universal metering has provided consumers with the
incentive to promptly repair such leaks.
Networks
also have other losses which include:
· Fire
fighting and hydrant flow testing
· Overflows
at reservoirs and losses during their cleaning
· Mains
testing and flushing
· Unknown
connections
· Use
by contractors
Collectively
this total water loss is referred to as Unaccounted for Water (UFW).
Controlling
UFW can significantly reduce demand. UFW
control also has environmental benefit as it reduces the quantities of water
that are required.
1.16.4 Water Losses
The
reporting of annual water losses as a percentage of annual water production is
not a satisfactory measure, as losses are nearly constant each year and water
sales (and therefore production) is weather dependent. ‘Bench Loss’ software has been used to
calculate the Infrastructure Leakage Index (ILI) which allows year to year
comparisons and also benchmarking between water supply authorities.
The
infrastructure leakage index has been calculated since 2001/02. The results are shown in Figure 3.2.
Figure 3.3 Infrastructure Leakage Index for
Nelson

The
Infrastructure Leakage Index has fluctuated over the past with a slight
increase apparent over the past two years.
This calculation
was made with assumptions regarding un-metered consumption such as flushing of
mains, fire fighting, use by contractors etc.
Further work is required to refine these assumptions. The viability of
providing metered water tank filling points around the city and where possible
metered standpipes for flushing, needs to be undertaken. This would allow more
accurate measurements to be entered into the calculation.
The
World Bank Banding System for interpreting the Infrastructure Leakage Index is
shown in Figure 3.4.
Figure 3.4 World Bank Banding System for
Infrastructure Leakage Index
|
·
For Developed Countries |
·
ILI |
·
Performance in real losses
management |
|
·
< 2 |
·
A |
|
|
·
2 - 4 |
·
B |
|
|
·
4 - 8 |
·
C |
|
|
·
> 8 |
·
D |
World
Bank suggested strategies for each band are:
· A
(0<ILI<2) Further loss reduction may be uneconomic unless there are
shortages; careful analysis needed to identify cost-effective improvement.
· B
(2<ILI<4) Potential for marked improvements; consider pressure
management, better active leakage control practices, and better network
maintenance.
· C
(4<ILI<8) Poor leakage record; tolerable only if water is plentiful and
cheap; even then, analyze level and nature of leakage and intensify leakage
reduction efforts.
· D
(ILI>8) Very inefficient use of resources; leakage reduction programmes
imperative and high priority.
The
water loss evaluation for Nelson is shown in Appendix E.
The
Council’s maintenance contractor has leak detection equipment which is used to
search for and pinpoint the location of suspected water leaks. This service is made available free of charge
for locating leaks in private property.
Water
leaks on hillsides and areas with clay/rock subsoil usually show quickly on the
surface, but on flat and gravel subsoil areas the water from leaks may flow
away without coming to the surface. Zone
meters have been installed at strategic locations in Stoke and Tahunanui to
measure the flow into defined areas. Night-time flows (when there is little
domestic demand) can be checked for abnormalities and also the inflow into a
zone can be compared with the volume of water sold through the water
meters. Additional work is required to
break the city into District Metering Areas to better monitor water usage by
defined zones.
The Leakage Control Plan is shown in Appendix
F.
This
level of input will be continued until the scale of UFW can be more accurately
established and the need for additional effort assessed. One contributing factor to UFW in Nelson is
the very high water pressures in some areas of the City (refer Section
2.4.3). The Pressure Reduction Plan is
shown in Appendix G.
1.16.5 Water Conservation Strategy
The
Regional Policy Statement requires that the Council as a water user must
prepare a Water Conservation Plan to limit or restrict the ‘non essential’
portion of the urban water supply in times of drought.
A
“Water Supply Conservation Strategy” was re-adopted by the Council in February
2003 to take account of the reduced abstraction available from the Roding River
due to the residual flow required to be left in the river as a condition of the
Resource Consent. The water conservation
strategy is shown in Appendix B.
1.17 Supply Capacity
As
discussed in Section 3.1 above, the reliable Roding supply in a 1 in 60 year
drought is reduced to 3,100m3/per day after 1 July 2008.
At
the abstraction rates currently authorised in the resource consents, Nelson
City has sufficient source water to meet predicted demand through a 1 in 60
year drought for the foreseeable future.
Based on current
demand projections the capacity of the Maitai pipeline will become the limiting
factor in 2023.
It
should be noted that these
dates will this may
change if the resource consent is varied or demand varies from that predicted.
Possible
augmentation options to make up any future deficit were considered by Council
in 2007. It should be noted that these
do not replace the existing sources but merely bridge the difference between
existing supply and future demand.
Details are in the following reports prepared by Opus International
Consultants:
· Maitai
Pipeline and Alternative Water Sources – Options and Costs, Opus International
Consultants Ltd, 2006
· Feasibility
of Raising the Water Level of Maitai Dam, Opus International Consultants Ltd,
and Tonkin and Taylor Ltd, 2007
Options
are:
· Roding
High Dam. A high dam at the Roding could
increase the Roding supply. The
estimated cost for 10,000m3/day is $20.9million (2008 dollars) and for
20,000m3/day is $34.0 million (2008 dollars).
· The
Waimea Water Augmentation Committee was formed to pursue an additional water
source for the Waimea Plains. Nelson
City Council is represented on the committee. Currently (February 2014) the
site for the proposed dam has been refined down to the upper Lee River. Volumes
required for urban supply are small compared with agriculture and horticulture
irrigation requirements. Water would be
released from the dam and enter the aquifer just above the Brightwater
Bridge. It would then be pumped from the
aquifer by users on the Waimea Plains.
Bores for Richmond and Nelson (should Nelson City Council resolve to
commit to the dam) water supplies and a water treatment plant would be sited
near the Appleby Bridge. The water would
then be pumped to Stoke through a new pipeline.
A share in the dam in 2012/13 is estimated to cost $2.5 million (2008
dollars) and the cost of the bores, pumps, treatment and pipeline in the future
is estimated to cost $14.7 million (2008 dollars).
· The
present capacity of the Nelson Water Treatment Plant at the Tantragee Saddle is
42,000m3/day, however provision has been made in the construction of the Plant
for the addition of a further membrane train which will increase the capacity
to 50,000m3/day. It is likely that with
improved technology the flow rate of new membranes will improve. The addition of the fifth train is programmed
for completion in 2015/16 and the present
membranes are likely to be renewed from 2017/ 2018.
· Raising
the top water level at the Maitai Dam. An adjustable weir could be installed on
top of the existing spillway weir so that additional water could be impounded.
Obermyer Spillway gates are bottom hinged spillway gates. They are most simply described as a row of
steel gate panels supported on their downstream side by inflatable air
bladders. By controlling the pressure in
the bladders, the lake elevation can be maintained at user-selected
points. The standard pneumatic controller
provides accurate upstream pond control, and discharges water appropriately to
maintain upstream lake elevation through a range of flows. This means that the existing spillway with
such a spillway gate can be used to increase the water level, whilst allowing
flood flows through as per normal.
If the lake level is
raised by one metre, the storage is increased by 350,000m3. Additional work would be required to alter
the auxiliary spillway and to clear an additional one metre band of vegetation around
the lake perimeter. A rough order cost
for the complete project is $0.7 million (2008 dollars).
· “Dead”
Storage. At present the bottom 900,000m3
of water in the dam cannot be accessed.
Provision was made at the time that the dam was built to install a pump
in the control building pipe work to enable this water to be pumped out and
into the existing Maitai pipeline. However, the new pipeline completed up
Maitai Valley Road in 2013/14 it will be at a level that will enable the “dead”
storage to be used by using the booster pump proposed in the vicinity of the
Maitai Motor Camp.
The bottom layer of
the Maitai dam lake has high levels of organic material as well as elevated
levels of heavy metals from the surrounding hills. The anoxic nature of this layer
means that there will likely be additional capital expenditure required to
improve the quality of this water should it be required as a source of potable
water. There will also be additional operational costs in running the pump when
the “dead” storage is utilised.
1.18 Extensions to the
Area Supplied
1.18.1 Eastern Foothills
The
Foothills Trunk Main is able to provide water to a large area including Upper
Brook Valley, upper Enner Glynn Valley, Marsden Valley, the ridge between the
Ngawhatu and Marsden Valleys, and Ngawhatu Valley.
1.18.2 Nelson North/Hira
When
the City water supply was extended to the Glen in 1990, high pressure pipework
was laid along the State Highway 6 from Allisdair Street to Todds Bush Road,
with provision made for a pressure reducing valve at Todds Bush Road. This was to enable increased flow in the
pipeline as far as Todds Bush Road.
Provision
was also made in the pipework for an extension beyond the Glen turnoff. In 2003 the main was extended by a private
subdivider from the Glen turnoff to Hillwood at the foot of Gentle Annie.
Extension
over Gentle Annie would provide only a low volume rural restricted supply to
existing properties in the Hira Basin.
At
its meeting on 24 October 2002, Council resolved that the pipeline not be
extended beyond Hillwood subdivision unless a prior change to the Nelson
Resource Management Plan allows more intensive development in the Nelson North
area and the costs would be met by those being served.
The
Nelson Urban Growth Strategy 2006 suggests that Hira could be a residential
growth hub around 2026. This study has
not been adopted by Council and no changes to the Nelson Resource Management
Plan are currently proposed that would provide for increased residential
development in this area. Providing a water supply to serve any growth would
require a review of supply options. One option is to construct a pipeline from
the Water Treatment Plant, down the Maitai Valley to a pump station near
Sharlands Creek, a pipeline up Sharlands Creek and over the saddle to Lud
Valley. Ultimately three 2,500 cubic
metre reservoirs would be required (each similar to the Walters Bluff and Stoke
No1 and No2 reservoirs). A trunk main
would then extend down the Lud Valley to the vicinity of the present Hira
School. This system is roughly estimated
to cost $30 million (2007 dollars).
Construction of the reservoirs would be staggered to meet development
demand, but the pipeline and pump station would have to be constructed as soon as
development at Hira proceeds. Other options based on use of local water sources
in the Lud, Teal and Wakapuaka streams have not been investigated. Issues with
these sources would be the need for sustained available flows in summer drought
conditions.
1.19 Future Growth
i) As outlined in 3.2.2
Council is concentrating on improving services to developed areas and providing
services to areas that are currently being developed (Residential, Rural Zone
High Density Small Holdings, Suburban Commercial, Industrial). Servicing of
other areas covered by the Services Overlay, because one or more servicing
constraints have been identified as needing to be addressed prior to the
complete development of that property/area, will be considered as Council
develops a policy on prioritising these areas.
The specific projects to facilitate future growth, identified in this
Asset Management Plan, therefore consist of works required to eliminate
servicing constraints on these sites. Further work is currently underway by Council’s
strategic planning team looking at completing the project prioritisation
process in appendix H. A Map of the
areas zoned for growth but constrained by lack of services is also attached in
Appendix H.
ii) Changes to wet industry
demand can also impact on the network and these will be monitored over time.
iii) While the current demand
for water is well within the supply capacity, there may be issues with delivery
to areas North of the city and the Wakatu industrial estate, where existing
network reticulation is not sized for larger flows.
iv) Capital projects in this
asset management plan will provide options reports for parts of these areas and
construction of storage reservoirs to buffer demand. Long term planning for
trunk main upgrades will be re-assessed as Council formulates a policy of
future development areas.
1.20 Action Plan
· When
future growth projections are available from the 2013 census, the water supply
demand for the City will be revised for inclusion in the next Water Supply
Asset Management Plan.
· Reports
on the Atawhai No 2 reservoir site and the Tasman District – Nelson City link
will be commissioned.
· Continue
the water loss identification and reduction programme
· Continue
the pressure reticulation programme
· Complete
District Metering Areas and monitor demand by area in the city.
· Investigate viability of metered contractor filling points and metered standpipes for flushing to improve UFW results.
1.21 Background
1.21.1 Emergency Management
The
key components of Emergency Management are the four “R’s”:
· Reduction
of emergencies;
· Readiness
for emergencies;
· Response
to emergencies;
· Recovery
from emergencies.
Initially
risks have to be identified through the Risk Management Process so that
advanced planning for the four “R’s” can be carried out.
However
not all risks are of an emergency nature, for example legal and financial
risks.
1.21.2 Risk Management Policy
Risk
will be managed in a prudent manner to enable business objectives and strategic
goals to be consistently met.
1.21.3 Scope
The
scope of risk management is to ensure that:
· Risk
is understood and identified;
· Hazards
and practices that could cause financial loss, disruption to business goals,
injury to people or damage to the environment are controlled as far as
practicable; and
· Insurance
or other financial arrangements are made to protect the business interests should
a loss damaging to the finances of the business occur.
1.21.4 Objectives
The
objectives of risk management are to provide:
· Protection
and continuity of the core business activities and essential services;
· Fulfilment
of legal obligations
· Safeguards
for public and employee health
· Environmental
protection
· Operation
and protection of assets at lowest cost
· Contingency
Planning for foreseeable emergency situations
· Protection
of ratepayer equity
· Manage
borrowings and interest rate risks within Treasury Policy limits
· Manage
interest rate risks
1.22 Implementation
1.22.1 Identification of the Risks
To
effectively manage risk it is necessary to:
· Identify
the nature, extent and likely incidence of risks affecting the operation of the
system.
· Measure
and evaluate the likely impact which could arise from each type of adverse
effect.
· Manage
risk to minimise potential effects and be cost effective.
· Monitor
and report on the status of each risk on a regular basis.
Potential
risks are identified in the tables in Appendix C: Nelson Tasman Engineering
Lifelines Project Report 2004. Table 4.4 applies the results of looking at
these risks in a quantitative fashion. The Lifelines report should be reviewed
and risk schedules updated to reflect network improvements over the past ten
years.
The Christchurch Earthquakes of 2010 /2011
lead to significant damage to that city’s infrastructure including water
storage reservoirs and pipe network from direct shaking and liquefaction.
Recognising this, and the results of other natural hazard investigation post
the Nelson storm events of December 2011 and April 2013, Nelson City Council is
reassessing the risk to the network from earthquakes (including liquefaction,
tsunami and direct shaking), flooding, storms and sea level rise.
In particular a series of
reports have been compiled, as part of the city’s wider hazard planning, as
follows:
· Tsunami modelling and evacuation zone
modelling for Tasman and Golden Bay- GNS February 2012 (A261963)
· Review of tsunami hazard in new zealand (2013
update)- gns august 2013(A371109)
· Assessment of the
location and paleoearthquake history of the Waimea-Flaxmore Fault System in the
Nelson-Richmond area with recommendations to mitigate the hazard arising from
fault rupture of the ground surface- M. R. Johnston A. Nicol Geological Consultant GNS Science
395 Trafalgar Street PO Box 30368 Nelson Lower Hutt GNS Science
Consultancy Report 2013/186 August
2013(A673742)
· Revised Preliminary Assessment of the Liquefaction
Hazard in Tasman and Nelson February
2013 (A597463)
· Tahunanui Area
Liquefaction Assessment- Tonkin and Taylor Ltd November 2013(A1117884)
· Maitai River Flood Hazard Mapping Modelling
Report Tonkin and Taylor Ltd August 2013(A677152)
A further
report is expected in 2015, to update the 2009 report by the National Institute
of Water and Atmospheric studies (NIWA) looking at the latest state of
knowledge of the impact of climate change on sea level rise.
The
water supply network activity is less impacted by sea level rise than other
utilities because the reticulation is kept at a positive pressure, reservoirs
are positioned on elevated ground away from direct tidal impact and the city’s
water source is distant mountain catchments.
Climate
change is expected to bring with it more extreme weather in the form of higher
intensity and duration rain events (with associated flood damage) and drought
periods. The issue will be monitored and future asset management plans will be
adjusted to address impacts as they become better understood.
Climate
change is an evolving area of research and as such involves significant
assumptions with associated uncertainties. Council seeks to limit the impact of
those uncertainties by relying on expert guidance from Central Government and
programming capital works in a staged fashion. Future upgrades of the water
network are based on ensuring the work is designed for demand and conditions
anticipated during the service life of the asset.
1.22.2 Analysis of Risks
The
risk management framework is consistent with the joint Australian, NZ Standard
AS/NZI 4360:1999 Risk Management, to ensure risks are managed on a consistent
basis.
Risk
is the combination of the likelihood and consequence of an event happening.
Likelihood
is a description of the probability or frequency of an event occurring. Likelihood ratings are shown in Table 4.1.
Consequence
is the outcome of an event being a loss, injury, disadvantage or gain. Consequence ratings are shown in Table 4.2.
For
each event the likelihood score is multiplied by the consequence score for each
area of impact. (There will be only one
likelihood but several consequences for each event).
These
multiples are then totalled to produce the risk score for the event.
The
level of risk is determined by utilising the Risk Priority Rating Matrix shown
in Table 4.3. This ranks the
significance of the various combinations of likelihood and consequence into
extreme, high, moderate and low risks.
The
risk management process will be further enhanced by the completion of Risk
Treatment Schedules and Risk Action Plans.
The
Business Continuity Plans prepared in preparation for the potential Y2K (Year
2000) computer event identified in depth potential risks caused by computer
failure and associated power supply and communications failures. This existing information is carried into the
Risk Treatment Schedule and Risk Action Plans.
Table 4.1 Likelihood Ratings (Semi Qualitative
Measure)
|
·
Rating |
·
Description |
·
Score |
|
|
·
A |
·
Almost Certain |
·
Likely to occur frequently
and several times a year. |
·
0.9 |
|
·
B |
·
Likely |
·
Likely to occur more than
once during the life of the project. |
·
0.7 |
|
·
C |
·
Moderate |
·
Likely to occur during the
life of the project. |
·
0.4 |
|
·
D |
·
Unlikely |
·
May occur once in up to
100 years. |
·
0.2 |
|
·
E |
·
Rare |
·
Might occur once in 100+
years. |
·
0.01 |
Table 4.2 Semi-Quantitative
Measures of Consequence and Areas of Impact
|
·
Areas of Impact |
·
Consequence |
||||
|
·
Negligible (10) |
·
Minor (30) |
·
Moderate (50) |
·
Major (70) |
·
Catastrophic (100) |
|
|
·
Health and Safety |
·
Minor injury possible. |
·
Serious injury to one person. |
·
Serious injury to multiple members of staff,
contractor or public. |
·
Single fatality of staff, contractor or public. |
·
Multiple fatalities of staff, contractors or public. |
|
·
Public Health |
·
Temporary but non-serious health impacts. |
·
Localised serious health impact on one person. |
·
Localised serious health impact on more than 20
people. |
·
Localised or widespread serious health impact on
more than 100 people. |
·
Localised or widespread serious health impact on
more than 1,000 people. |
|
·
Asset Performance |
·
Asset failure impacting on one or more persons. |
·
Asset failure impacting on more than four people. |
·
Asset failure impacting on more than 40 people. |
·
Asset failure impacting on more than 400 people. |
·
Asset failure impacting on more than 4,000 people. |
|
·
Environment and Legal Compliance |
·
Short term and temporary impact requiring no remedial
action. |
·
Medium term environmental impact with immaterial
effects on environment or community. |
·
Measurable environmental harm to an internationally
or nationally significant site. Loss
of public access or conservation value of the site. |
·
Major environmental damage with long-term recovery
significant investment. High profile
legal challenge. Loss of public
access or conservation value of a significant environment. |
·
Permanent environmental damage to an internationally
or nationally significant site. Large scale class action. |
|
·
Historical or Cultural |
·
Loss of important records about a site. Work required restoring them. |
·
Unsympathetic development compromising the integrity
of a registered historical, cultural or archaeological site. |
·
Damage to a registered historical, cultural or
archaeological site, but capable of restoration. |
·
Loss or permanent damage to a registered historical,
cultural or archaeological site. |
·
Permanent loss of national icon. |
|
·
Financial |
·
Capital cost/ loss <$100k. |
·
Capital cost/loss $100k - $500k. |
·
Capital cost/loss ·
$500k - $1million. |
·
Capital cost/loss ·
$1million- $5million. |
·
Capital cost/loss ·
> $5 million. |
|
·
Customer Perception |
·
Service Request. |
·
Minor complaint. |
·
Justifiable complaint / information request. |
·
Ministerial questions /third party investigations. |
·
Public or ministerial enquiry. |
Table 4.3 Risk Priority Rating (Semi
Quantitative)
|
Risk Score |
Level of Risk |
Risk Response |
|
·
> 200 |
·
Extreme |
·
Awareness of the event to
be highlighted to Council |
|
·
150-200 |
·
High |
·
Risk treatment
required. Risk to be eliminated or
mitigated as soon as possible |
|
·
100-150 |
·
Moderate |
·
Risk treatment required |
|
·
0-100 |
·
Low |
·
Manage by routine
procedures |
1.23 Risk Identification,
Risk Analysis and Risk Priority Rating
1.23.1 Vulnerable Assets
Council’s
headworks, water treatment facilities, trunk mains, and reservoirs are vital
assets as without them water supply to the City is not possible.
Water
quality is another risk that is City wide.
Reticulation
mains are not as critical, as it is generally only the street the main is in or
adjoining streets, which are affected by a problem with a reticulation main.
Area wide liquefaction events are an exception to this.
Risk
events are shown in Table 4.4 following the flow from intakes to consumer.
Table 4.4 Risk Events Ratings (Semi-Quantitative)
|
·
General |
·
Event |
·
Likelihood |
·
Score |
·
Rank |
·
Risk |
|
Intakes |
Poison or organics accidental
spillage or sabotage |
0.2 |
80 |
10 |
Low |
|
Treatment Plant |
Movement failure caused by,
Earthquake, landslide or settlement |
0.4 |
68 |
11 |
Low |
|
Maitai Pipeline Dam -WTPlant |
Movement failure caused by,
Earthquake, landslide or settlement |
0.7 |
130 |
7 |
Moderate |
|
Maitai Pipeline WTP-City |
Movement failure caused by,
Earthquake, landslide or settlement |
0.7 |
210 |
1 |
Extreme |
|
Maitai Pipeline |
Flood damage |
0.7 |
108 |
8 |
Moderate |
|
Roding Pipeline |
Movement failure caused by, Earthquake,
landslide or settlement |
0.4 |
56 |
12 |
Low |
|
Roding Pipeline |
Flood damage |
0.7 |
182 |
3 |
High |
|
Trunk mains |
Movement failure caused by,
Earthquake, landslide or settlement |
0.2 |
52 |
13 |
Low |
|
Reservoirs |
Movement failure caused by,
Earthquake, landslide or settlement |
0.4 |
168 |
4 |
High |
|
Reticulation |
Backflow contamination from private
property |
0.2 |
132 |
6 |
Moderate |
|
Reticulation |
Backflow contamination from industry |
0.7 |
204 |
2 |
Extreme |
|
Reticulation |
Poison or organics accidental
spillage or sabotage |
0.2 |
102 |
9 |
Moderate |
|
Reticulation |
Damage from liquefaction (At risk
areas Port Nelson, Tahunanui/Stoke) |
0.4 |
140 |
5 |
Moderate |
1.23.2 Risk Treatment Schedule and Plan
The Risk
Treatment Schedule and Plan is shown in Table 4.5.
1.24 Risk Summary
1.24.1 Maitai Water Supply Scheme
Because
the Maitai Water Supply Scheme is a vulnerable asset, it was designed to
withstand 1 in 100 year seismic and flood events without damage.
Key
structures are designed to withstand maximum credible earthquake and probable
maximum flood without collapse (but not without some damage, possibly requiring
decommissioning and major repair work).
Details
of the design parameters of the Maitai Water Supply Scheme are contained in
“Nelson City Council Maitai Water Supply Project Design Report”, Tonkin &
Taylor Limited, 1984.
The
Maitai pipeline between the Dam and Brook Street has been identified as an
extreme risk from damage due to earthquake displacement or slip.
The
pipeline supplies two thirds of Nelson’s water, is above ground, on a sidling
bench along the hillside.
Repair/replacement of 5m of pipe would take 24-48 hours, with town
reservoirs holding sufficient water for approximately 8 hours daytime
consumption.
Design
of a new pipeline between the dam and the Water Treatment Plant has been
completed in 2011 with construction completed in 2014/15.
Design
and construction of a new pipeline between the Water Treatment Plant and
Westbrook Terrace is scheduled for 2014-2017.
Sections
of the Maitai pipeline remain close to, or within, the river with some ongoing
risk of flood damage. Identification of these sections and regular inspection
and maintenance are seen to be the best response.
1.24.2 Roding Water Supply Scheme
The
Roding Water Scheme poses low and moderate risks to structures other than a
200m length of pipe between the screenhouse and the chlorinator house. This pipe is suspended on piers along the
riverbank. A 30m section was washed out
in the large flood of January 1986.
Subsequently the pipes were more securely fixed and rock armouring was
constructed in front of the piers. There
is a possibility that a similar large flood could damage the pipe again. Reinstatement would take 2-3 days, during
which time the Maitai river/dam and Tasman District Council would be the only
sources supplying the City.
A
condition assessment was
being carried out
started in 2013/14 and will be completed in 2015/16
to allow renewal decisions to be made. A risk assessment of any new pipeline
route will be undertaken as part of any renewal design.
At a
Council workshop in 2014 Councillors expressed the wish for more regular gravel
removal behind the dam to improve water storage capacity in light of the
increasing risks associated with climate change and summer droughts.
1.24.3 Water Treatment Plant
A
portable chlorinator using sodium hypochlorite is held at the Water Treatment
Plant. It is a complete stand-alone
unit, run by a small petrol generator.
This has the capacity of dosing 30l/h of sodium hypochlorite, which is
sufficient to treat the full Maitai flow of 37,000m3/day.
A
separate Emergency Management Plan has been developed covering Risks and
Actions specific to the Water Treatment Plant.
A
portable chlorinator alternatively powered by either a petrol motor or an
electric motor is held at Princes Drive for emergency chlorination using High
Test Hypochlorite (HTH) powder. This has
a capacity of dosing 24kg of chlorine per hour.
This is sufficient to treat 12,000 cubic metres of water per hour at 2
grams per cubic metre (= 2ppm or 2mg per litre).
A
small slip occurred to an excavated bank adjacent the plant during the December
2011 rain event. The plant will remain at risk of small surface slips given the
excavations undertaken during construction.
1.24.4 Trunk Mains
Risks
posed to the trunk mains range from low to high. The high risk is from earthquake damage where
sections of key mains would be damaged. Presently
stocks of pipes and fittings are held to allow single repairs to each main.
New
trunk mains are typically constructed from more ductile materials.
Mutual
aid would be required from other water supply authorities to reinstate trunk
mains in the event of multiple major breaks.
Refer to section 4.5.2 for details of the Mutual Aid Plan.
1.24.5 Reservoirs
The
Clearwater, Stoke, Walters Bluff, and Observatory Hill Reservoirs have been
constructed to category 2. The large and
small Thompson Terrace Reservoirs have been strengthened to category 2 and
category 3 respectively.
Note: Category 2 is a 1 in 1000 year earthquake
and category 3 is a 1 in 333 year earthquake.
All
large reservoirs have been fitted or retrofitted with automatic seismic shut
off valves. When excess flow from the
reservoir is detected (such as from a broken outlet trunk main) the outlet
valve is automatically shut and an alarm sent to the Duty Officer via the SCADA
system.
In
2013/14 a project to review the seismic response and protection features of the
reservoirs, intake structures and pipework at the Maitai Dam and the steel
siphons on the Maitai Dam to treatment plant pipeline was initiated. This
project has been developed as a result of the damage to the Christchurch water
network from the February 2011 earthquake in that region.
The
project has a number of stages which can be modified as results of each stage
are available:
Stage
1- Review the seismicity of the sites and compare with the factors from AS/NZS
1170 Structural Design Actions. This provides a quick view of how design
standards might have changed since the reservoirs were constructed.
Stage
2- Review the on-site construction details of the pipework and valving
arrangements to ensure seismic valves are correctly positioned and pipework
details minimise the risk of water loss in earthquakes. This stage will provide
an early benefit by ensuring the reservoirs can contain stored water under less
than ultimate design level events.
Stage
3- Review the structural adequacy of the reservoir, dams and pipelines. This
stage will look at the structural design and detailing of the major components
of the network and may be undertaken in a number of stages.
1.24.6 Liquefaction
Ongoing
hazard investigation in 2013 identified the risk of liquefaction to the network
in parts of Nelson. The initial study was restricted to the Tahunanui area but
similar materials are expected to be part of the Port Nelson reclamation.
The
risk to the water network in Tahunanui arises from flotation of chambers and
damage to the mains from extension, shortening and translation arising from
ground movement.
During
the operative period of this plan further work will be carried out to better
identify at risk components and current industry response.
1.24.7 Water Quality
Risks
posed to water quality range from low to extreme. Completion of The Water Treatment Plant in
August 2004 has reduced the risk to source water to low.
The
extreme risk relates to possible backflow from premises into the water reticulation,
thereby putting other consumers in danger.
Dual check valves have been fitted to all residential connections as
part of the water meter manifold. These
will be replaced when the water meters are replaced in 2017-2020. Backflow preventors have been installed at
all Nelson City Council drainage pump stations and Council owned buildings and
facilities. However, there are fewer
protection devices on commercial and industrial premises.
A
programme of installing backflow preventors in conjunction with replacing
Commercial/Industrial water meters is shown in the Capital Works projections.
1.24.8 Public Health Risk Management Plans
The
Nelson Public Health Risk Management Plan 2012 (now referred to as a Water
Safety Plan- post the 2013 amendment to the Health Act 1956) outlines a range
of issues that are required to be addressed within the network. Budget has been
identified for developing the response to these issues. Any further works that
arise from the response will be developed in future annual or long term plans.
Table 4.5 Risk Treatment
Schedule and Plan - Water Supply
|
·
The Risk in Priority
Order from Risk Register |
·
Risk Before Treatment |
·
Possible Treatment
Options |
·
Preferred Options |
·
Risk After Treatment |
·
Timing |
|
·
1 |
·
E |
·
Maitai Pipeline: WTP-City
Damaged by Earthquake, Landslip or Rockfall ·
Regular inspection to look
for potential slips and possible rocks or logs that could fall. ·
Cover pipe during logging. ·
Construct “avalanche”
shutter in known rockfall areas. ·
Construct alternative main
down Brook Valley Road. |
·
New main to be laid down
road WTP to Westbrook Terrace via Brook Street |
·
L |
·
Design and Construct
2014/18 |
|
·
2 |
·
E |
·
Backflow from Industry |
·
Fit backflow preventors to
all commercial and industrial premises. |
·
M |
·
Install 2012/24 |
|
·
3 |
·
H |
·
Roding Pipeline Damaged by
Floods ·
Maintain rockwork on
riverbank. ·
Keep pipeline full to
reduce floatation. |
·
Both |
·
M |
·
ongoing |
|
·
4 |
·
H |
·
Reservoirs damaged by
Earthquake ·
Major reservoirs are
designed for 1 in 1000 or 1 in 333 year earthquakes. ·
Ensure seismic valves
properly located, ensure construction details adequate. |
·
Currently being
investigated |
·
L |
·
Installation details
reviewed 2014 post Christchurch 2011 earthquake. Remedial improvements in LTP
2015-25. |
|
·
5 |
·
M |
·
Damage from liquefaction
(At risk areas, Port Nelson, Tahunanui) ·
Anchor chambers |
·
Anchor chambers |
·
L |
·
TBA |
|
·
6 |
·
M |
·
Backflow from Residential
Property ·
Replace dual check valves |
·
Replace dual check valves |
·
L |
·
2015/19 |
|
·
7 |
·
M |
·
Maitai Pipeline: Dam to
WTP- Damaged by Earthquake, Landslip or Rockfall ·
Regular inspection to look
for potential slips and possible rocks or logs that could fall. ·
Cover pipe during logging. ·
Construct “avalanche”
shutter in known rockfall areas. |
·
Inspection |
·
L |
·
Ongoing |
|
·
8 |
·
M |
·
Maitai Pipeline Damaged by
Floods ·
Maintain rockwork on
riverbank. ·
Keep pipeline full to
reduce floatation. |
·
Both |
·
M |
·
Ongoing |
|
·
9 |
·
M |
·
Accidental Spillage or Sabotage
to Reticulation ·
Impossible to prevent.
Maintain vigilance |
·
Maintain vigilance |
·
M |
·
Ongoing |
|
·
10 |
·
L |
·
Accidental Spillage or
Sabotage to Intakes ·
Impossible to prevent. ·
Maintain Vigilance. |
·
Maintain vigilance |
·
L |
·
Ongoing |
|
·
11 |
·
L |
·
Treatment Plant Damaged by
Earthquake Landslide or Settlement ·
Plant has been designed to
a high standard. ·
Regular inspection for
likely problems. |
·
Regular inspections |
·
L |
·
Ongoing |
|
·
12 |
·
L |
·
Roding Pipeline Damaged by
Earthquake, Landslip ·
Regular inspection to look
for potential slips and possible rocks or logs that could fall. ·
Construct “avalanche”
shutter in known risk areas. ·
|
·
Regular inspections |
·
L |
·
Ongoing |
|
·
13 |
·
L |
·
Trunk mains disrupted by
Earthquake ·
Fitting of seismic valves to
water reservoirs to turn off water in event of earthquake. ·
Ensure movement joints in
network |
·
Seismic valves will not
protect pipeline but will retain water in the reservoirs to prevent it
draining out through a ruptured trunk main.
Water could then be distributed by tanker. ·
Movement considered with
new works. |
·
L |
·
Completed 2007/08. ·
Installation details
reviewed 2014 post Christchurch 2011 earthquake. Any improvements in LTP
2015-25. |
1.25.1 Lifelines
The
Civil Defence and Emergency Management Act 2002 requires that every lifeline
utility must:
· Ensure
that it is able to function to the fullest possible extent, even though this
may be at a reduced level, during and after an emergency.
· Have
plans for such a continuity that can be made available to the Director (of
Ministry of Civil Defence and Emergency Management) if requested.
· Participate
in the development of the National Strategy and Civil Defence Emergency
Management Plans (where requested).
· Provide
technical advice on Civil Defence Emergency Management issues, where reasonably
requested by Civil Defence Emergency Management Groups or the Director.
Lifeline
Utilities are: Gas, electricity, water
supply, wastewater, telecommunications, road, rail, airports, plants and some
broadcast media.
Nelson
City Council continues to participate in the Nelson Tasman Engineering
Lifelines project. The sections of the
final project report relevant to water supply are included in Appendix C of
this Asset Management Plan.
1.25.2 Water Supply Mutual Aid Plan
The
Nelson City Council is a signatory to the Water Supply Mutual Aid Plan
administered by the Water Managers’ Group of Water New Zealand (New Zealand
Water and Wastes Association).
The
purpose of the agreement is to:
· Provide
a framework for administration and Water Sector co-ordination;
· Create
a central register of contact details of personnel with designated authority;
· Create
a central register of approximate resource levels available at each of the
Agreement signatories (personnel, equipment, specialist materials);
· Define
protocols and principles for requesting and providing assistance during an
emergency;
· Set a
policy for charging and reimbursement of costs;
· Address
liability and indemnity issues.
1.25.3 Local Authority Protection Programme
Disaster Fund
Nelson
City Council is a member of the Local Authority Protection Programme Disaster
Fund. This is a mutual pool created by
local authorities in 1993 to cater for the replacement of infrastructure following
catastrophic damage by natural disaster.
Central
government’s Disaster Recovery Plan (currently overseen by the Ministry of
Civil Defence and Emergency Management-MCDEM) states that beyond a threshold,
central government will pay 60% of restoration costs. Local government are responsible for the
remaining 40% thus effectively moving part of the onus from the tax payer to
the rate payer. Central government will
only provide their 60% following a major catastrophe provided that the local
authority can demonstrate it can meet the remaining 40% through:
· Proper
maintenance
· The
provision of reserve funds
· Effective
insurance
· Participation
in a mutual assistance scheme with other local authorities e.g. Local Authority
Protection Programme Disaster
·
The Fund is designed to
cover local authority owned infrastructural assets which are considered
generally uninsurable. These include:
· Water
reticulation, treatment and storage
· Sewage
reticulation and treatment
· Stormwater
drainage
· Dams
and canals
· Flood
protection schemes including stopbanks
· Floodgates,
seawalls and harbour risks such as buoys, beacons and uninsurable foreshore
lighthouses
Roads
and bridges are not covered by the Fund as local authorities have access to
TransFund subsidies.
The
Fund is designed as catastrophe protection only, covering serious disruptive
loss or damage caused by sudden events or situations which may or may not
involve the declaration of a Civil Defence Emergency. Perils include, but are not necessarily
limited to, earthquake, storms, floods, cyclones, tornadoes, volcanic eruption,
tsunami and other disasters of a catastrophic nature such as a major gas
explosion.
The
damage resulting from the Canterbury Earthquakes of 2010 and 2011 has severely
depleted the reserves of the Local Authority Protection Programme Disaster
funds and as a consequence the fund directors have signalled the intention to
increase annual levies until the fund recovers.
This will increase administration costs in this activity.
1.26 Action Plan
Refer
Table 4.5 for Risk Treatment Schedule and Plan.
1.27 Review
The
Risk Analysis will be reviewed each year.
In light of the significant seismic activity
in Canterbury in 2010/2011 a review of the water reservoirs and sections of the
trunk main for damage prevention and post-event response has been undertaken in
2013/14. A separate budget item has been included in the capital works
programme for 2015-2017 for any remedial works to the water reservoirs and raw
water trunk main sections that are vulnerable to damage. The latter are
initially expected to be the steel arch siphons from the Maitai Dam to the
water treatment plant.
A
more extensive review of the network is required to address the risks
identified. This will be undertaken over the duration of this plan and will
support the next review of the Nelson- Tasman Lifelines initiative.
1.28 Health and safety
The
Maintenance Contractors carry out monthly inspections of assets, which include
identifying any Health and Safety issues.
Internal
Audits of Health and Safety practices for construction works on the water
supply assets are carried out periodically.
1.29 Background Data
Assets
have a life cycle as they move through from the initial concept to the final
disposal. Depending on the type of
asset, its lifecycle may vary from 10 years to over 100 years.
1.29.1 Key stages in the asset life cycle are:
· Asset
planning; when the new asset is conceived.
Decisions made at this time influence the sustainability of the asset,
the cost of operating the asset and the lifespan of the asset. Alternative, non asset solutions must also be
considered.
· Asset
creation or acquisition; when the asset is purchased, constructed or vested (by
a subdivider). Sustainability, capital
cost, design and construction standards, commissioning the asset, and
guarantees by suppliers influence the cost of operating the asset and the
lifespan of the asset.
· Asset
operations and maintenance; when the asset is operated and maintained. Operation relates to sustainability,
efficiency, power costs, throughput etc, and is usually more applicable to
mechanical plant rather than static assets such as pipes. Maintenance relates to preventative
maintenance where minor work is carried out to prevent more expensive work in
the future, and reactive maintenance where a break is fixed.
· Asset
condition and performance monitoring; when the asset is examined and checked to
ascertain when and how an asset will fail, what corrective action is required
and when (i.e. maintenance, rehabilitation or renewal).
· Asset
rehabilitation and renewal; when the asset is restored to ensure that the
required level of service including sustainability can be delivered.
· Asset
disposal and rationalisation. Where a
failed or redundant asset is sold off, put to another use, or abandoned.
1.29.2 Sustainability
xxiv) Overview of Sustainability
xxv)
The Local Government Act 2002 requires that local authorities take a
sustainable development approach to everything they do. The publication, Nelson 2060 (June 2013) was
developed by Council through an inclusive process called “Framing our Future”
and sets out Nelson’s sustainability strategy.
xxvi) The framework and checklist outlined in this
document will be used to guide the management of the city’s infrastructure.
xxvii) Infrastructure is installed and
maintained on the understanding that the assets are provided in perpetuity for
the benefit of future generations.
Longevity of an asset is a prime consideration when design and planning
is undertaken for new or replacement components in the network.
xxviii)
Actions for Future Improvement
xxix) Further action in promoting the sustainability
of this activity is considered to centre on the following areas:
· More strategic monitoring of the condition and operation of the asset to
identify most appropriate renewal priorities;
· Enhanced network modelling to aid prediction of performance and renewal
strategies;
· Additional effort to reduce water losses through renewal of pipelines,
reduced water pressures and proactive water loss detection;
· Duplication of the trunk main from the treatment plant to the city
centre;
· Renewal of resource consents for the city water supply;
· Ongoing monitoring of water quality in the Maitai and Roding rivers.
Figure 5.1 Sustainability Impact at Various
Lifecycle Stages

Retrofitting
of “sustainability” is possible for some assets but the best outcomes will be
with new assets.
Sustainability
Actions Already being Implemented
· Universal
Water Metering
Nelson implemented
universal water metering (i.e. a water meter on every residential, commercial
and industrial supply) in 1999 and was among the first councils in New Zealand
to do so. Charging for water used
through the meter has a major impact on demand and reduces water abstraction,
pumping and treatment, and defers the need for newer and larger intakes, pipes
and other infrastructure.
· Hydro
Electric Generation
The hydro electric
generation plant installed at the Water Treatment Plant (WTP) in 2009 will
recover energy that would otherwise be dissipated through a Pressure Reducing Valve.
· Use
of Abandoned Pipes as Service Ducts
In the past, water
pipes abandoned when replacements were constructed were grouted with
concrete. They are now capped to prevent
the ingress of water and retained as service ducts for use by other network operators,
rather than them having to trench a road and install their own ducts.
· Gravitating
Water rather than Pumping
Treated water can be
supplied from the Water Treatment Plant to Stoke by gravity via the City and
the Thompson Terrace Reservoirs or by pumping over the foothills. As much water
as possible, particularly at times of low demand, is gravitated to reduce the
use of electricity for pumping.
Similarly, while there
is sufficient water available from the Maitai, that source is used in
preference to the Roding River to reduce the raw water pumped over the
foothills to the Water Treatment Plant.
· Pump
Timing
Where possible pumping
is carried out in off- peak power times.
This not only reduces the country’s dependence on fossil fuels to meet
peak load, but also reduces Council’s electricity costs.
· Water
Loss Reduction
Over time the loss
reduction programme currently underway will reduce the loss of water. This will reduce water abstraction, pumping
and treatment, and may defer the need for newer and larger intakes, pipes, and
other infrastructure.
Sustainability
Actions Under Consideration
· Demand
Reduction
Council’s Land
Development Manual recognises the use of rainwater tanks to supply garden and
outdoor use, particularly during summer months.
The practicality and cost of installing large tanks on urban sites to
make a significant contribution to demand means that it is not considered
feasible at this point to rely on these as viable means of reducing demand. This is a topic that will be monitored as the
demand and supply curves begin to converge.
Other methods of
reducing demand such as water efficient appliances and fittings will also be
monitored as Council is made aware of their use. Currently Council does not
actively evaluate water use in new and older homes to compare relative
efficiencies of new construction. This is something that is expected to be
developed in the future.
· Pipe
and other Materials
Manufacturers of
various pipes have started reporting on the sustainability of their products. This work will be reviewed to ensure that
appropriate selections are made for future projects. Considerations will include material,
manufacture, transport, laying, maintenance, renewal, reuse and disposal
ability and cost.
1.29.3 Sustainability Action Plan
· Sustainability
will be considered in future decisions.
1.29.4 Asset Failure Modes
Generally
it is assumed that physical failure is the critical failure mode for many
assets. However the Asset Management
process recognises that other modes are relevant and are often critical to
effective delivery of services.
The
range of failure modes includes:
· Structural;
where the physical condition of the asset is the measure of deterioration,
service potential and remaining life.
· Capacity;
where the level of under or over capacity against the required level of service
establishes the remaining life.
· Level
of service failure; where reliability of the asset or performance targets are
not achieved.
· Obsolescence;
where technical change or lack of replacement parts can render assets
uneconomic to operate or maintain.
· Cost
or economic impact; where the cost to maintain or operate an asset is greater
than the economic return.
· Operator
error; where the available skill level to operate an asset could impact on
asset performance.
1.29.5 Condition Assessment
Historically
asset monitoring to determine condition has been subjective, based on local
knowledge and experience. Formal
procedures now exist to assess asset condition in a qualitative fashion.
The
development and continued use of condition assessment data is expected to
support the preparation of verifiable predictive decay curves for particular
asset types and hence permit prediction of remaining life. Consideration of economic influences and
other factors will also be required in the adopted life for the asset type.
By
considering the current condition point on an assumed decay curve, the profile
can predict the effective life (time) before failure. This failure time can be the physical end of
life, minimum level of acceptable service, or limit of capacity of the asset.
Condition
assessment ranks assets on a five step scale as follows:
|
·
1 |
·
Very Good |
·
Very good condition, where
only normal maintenance is required. |
|
·
2 |
·
Good |
·
Minor defects only where
minor maintenance is required to approximately 5% of the asset. |
|
·
3 |
·
Fair |
·
Maintenance required to
return to accepted level of service where significant maintenance is required
to 10-20% of the asset. |
|
·
4 |
·
Poor |
·
Requires renewal where
significant renewal or upgrade is required to 20-40% of the asset. |
|
·
5 |
·
Very Poor |
·
Asset unserviceable where
over 50% of the asset requires replacement. |
It is
not necessary to assess all assets immediately.
It is only necessary to assess those that are going to become
unserviceable in the next 20 years.
The
extent and repetition of condition assessment will be influenced by:
· The
criticality of the asset
· The
type of asset
· The
relative age of the asset
· The
rate of deterioration of the assets
· The
economic value of the outcomes to the business
· Unplanned
maintenance history
Generally
the older the asset the more frequent the assessment of condition is
required. It is necessary to know whether
failure is imminent and, if previous assessments have shown degradation, at
what rate.
1.29.6 Critical Assets
Critical
Assets are defined as those assets that are essential to providing a water
supply in times of emergency (albeit at a reduced level of service), or have an
unacceptable consequence of failure.
Critical
assets have been identified as:
· Headworks
including dams and intakes
· Raw
water trunk mains
· Raw
water pump stations
· Water
Treatment Plant including Clearwater Reservoir
· Treated
water trunk mains
· Treated
water pump stations
· Reservoirs
With
these assets operating treated water will be available in each suburb for
distribution by water tanker or personal collection and by watermain as damaged
reticulation is repaired and brought back into service.
1.29.7 Condition and Performance Assessment
Process
Condition
relates to the physical integrity of the asset.
Performance
relates to the capability of the asset to meet defined service criteria, and
can address other failure modes such as reliability, capacity, and effect on
water quality.
Two
complementary approaches to Condition and Performance Assessment will be
utilised. The “top down” which provides
an overview, and “bottom up” which collects information on each individual
asset.
The
top down method produces a one off statement of asset condition and performance
using a robust statistical methodology.
It relies largely on information already available supplemented by
targeted studies to improve the quality of the data. It groups pipes of similar size, material,
age and operating conditions. The data
is then extrapolated to provide estimates of long term expenditure needed to
maintain, improve or extend network assets. Information from the “bottom up
method” is used to update the data fed into the “top down” method. The top down method should be repeated every
three years.
The
bottom up method provides a long term database on the condition and performance
of assets, which is updated as further information becomes available. A 20 plus year history is considered to be
required to build up the base level of information on each specific asset. To obtain a representative assessment of the
pipe condition, sampling must be from unfailed pipes as well as failures.
Condition
assessment, involving in-situ testing and visual evaluation, is being carried
out in 2013/14 -2015/16
on the raw water pipeline from the Roding Dam to Marsden Valley as a means of
establishing the renewal timing for this asset.
1.29.8 Current Position on Condition Assessment
Presently
the simple approach to condition assessment is being used.
Whenever
the maintenance contractor is working on pipe repairs a condition report is
made and entered into the Asset Management System. It is anticipated that this database will be
used to plot developing problem areas on a city wide basis and allow
relationships between pipe types, construction techniques, age and geology to
be developed.
Pipe
samples will also be recovered, where unexpected failures occur, so that
sophisticated condition assessment can be implemented and the data recorded on
the Asset Management System.
The
Asset Management System will be used as part of an Optimised Decision Making
process. The level of sophistication will increase as the condition data base is
developed.
1.30 Asset Condition and
Performance Assessments
1.30.1 Reticulation
Figure
5.1 provides details of the age/material distribution of the Council’s water
supply network.
Figure
5.2 presents the same information, but showing the likely time of replacement
on age, material and criticality.
The
Council has implemented the Hansen Asset Management System. It is used to generate works instructions or
Service Request Instructions to the utility services maintenance contractor and
to link job instructions to the particular section of the network requiring
repair, thereby building up a long term maintenance history of the network.
Once
a history has been established, maintenance history and age will be used to
assist in a deterioration model that will be used to optimise pipe
replacements.
With
the purchase of Network Analysis software and monitoring equipment, further
work, such as area metering, has been carried out to determine areas of
excessive water loss.
When
considering the condition of the reticulation, the City can be considered as
three reasonably distinct areas:
· The
Central City and Port Hills was one of the first areas developed in Nelson and
was reticulated with cast iron and steel pipe.
The 75mm diameter cast iron pipes have largely been replaced with 100mm
or 150mm diameter PVC pipes over the last 10 years.
The
reticulation is considered to require minor maintenance only i.e. Condition
Grade 2 – Good.
· Stoke
and Tahunanui came within the City boundaries in the 1950’s. Water reticulation was provided at that
time. Typically cast iron and asbestos
cement pipe was used. Early asbestos
cement pipes are softening and starting to fail and needs replacement. The reticulation is considered to be in
satisfactory condition, i.e. Condition Grade 2 - Good.
· The
Atawhai and Stoke South areas have been developed since the 1970’s. Asbestos cement and more recently PVC pipe
have been used. The reticulation is
considered to be in very good condition, i.e. Condition Grade 1 – Very Good.
1.30.2 Asbestos Cement Watermains
The
Water Supply Managers Group of the New Zealand Water and Waste Association has
produced a report entitled “Condition Rating of Asbestos Cement Watermains”
which includes (on hard copy and diskette) a copy of: the National
Specification for Sampling and Testing, the Life Expectancy Model, the
Deterioration/Life Curves, and a copy of the current database of results.
This
document will be used to assess the condition of asbestos cement pipes in
Nelson.
Pipes
of larger diameters and pipes of higher pipe pressure classes have thicker
walls to provide the necessary hoop strength.
However
pipe wall degradation is nearly constant for all pipe sizes and classes,
therefore smaller diameter, lower pressure class pipes will fail earlier, and
large diameter higher pressure class pipes may never fail from deterioration.
Most
asbestos cement pipe laid in Nelson is Class D.
The exceptions are where higher pressure classes were required for
specific high pressure lines.
It
appears that the relationship between ground conditions and deterioration is
not completely proven but may be worth investigating for critical pipelines.
By
sampling and testing the remaining wall thickness on existing pipes it may be
possible to predict the year of first deterioration failures in each asbestos
cement pipeline.
Most
AC pipelines in Nelson are 100mm and 150mm Class D pipes, laid between the
1950s and 1980s during the subdivision boom in Stoke, Atawhai and the Victory
Square area.
These
pipelines are of the same size, class, operating pressure, and ground
conditions, and can therefore be aggregated to derive the top down
deterioration model for Nelson.
Similarly
there are some 50mm diameter class D rider mains which can be aggregated. As noted above these pipes are likely to be
the first to fail from deterioration.
They are also most likely to fail due to, for example, traffic loading,
again due to the relatively thin wall thickness required for the low internal
pressure hoop stresses.
A few
trunk mains are 200, 300, 375, and 450 mm asbestos cement of varying pressure
classes (e.g. the 375mm trunk main from Neale Park to Vickerman Street is
C28. A 375mm pressure class C dimension
pipe, but with a stronger asbestos cement mix in the wall). As noted above, these pipes are the least
likely to fail from deterioration.
Sampling
and testing for pipe wall softening will be carried out using the standard
methods described in the “Condition Rating of Asbestos Cement Watermains”
manual.
The
performance of asbestos cement pipes does not generally deteriorate with time.
Asbestos
pipe was imported from Britain and Italy in the early 1950s. It is coated with bitumen and is colloquially
known as “Black Asbestos” cement pipe.
New
Zealand made “Fibrolite” asbestos cement pipe does not appear to be
softening. A programme of replacing 50mm
diameter “Fibrolite” pipe and 100mm diameter “Black Asbestos” pipe has
commenced.
Table 5.1 Best Estimate of Condition of Asbestos
Cement Watermains
|
·
|
Very Good |
Good |
Fair |
Poor |
Very Poor |
Total |
|
·
Metres Length |
·
80,434 |
·
15,157 |
·
12,956 |
·
7,762 |
·
3,467 |
·
119,781 |
|
·
% |
·
67.0 |
·
12.6 |
·
10.8 |
·
6.5 |
·
3.0 |
·
100 |
1.30.3 Cast Iron Watermains
Cast
iron pipes generally have a long life before deterioration failure.
Their
performance however suffers from iron tubercles developing on the inside of the
pipes. These restrict the flow, and
slough off giving dirty water complaints.
However, the strength of the pipe is not affected by the tubercles.
Growths
develop on the inside of cast iron pipes caused by iron bacteria. The bacteria are autotrophic and obtain
energy from inorganic compounds. They
use carbon dioxide as a carbon source.
They oxidise soluble ferrous iron to less soluble ferric iron. The bacteria deposit oxidised iron Ferric
Hydroxide as a red-brown coloured slime.
Iron bacteria thrive in unlined cast iron pipes.
Another
source of dissolved iron was from lower levels of the Maitai Lake when this
water is used in preference to turbid water from upper levels when the river is
in flood. This problem has however been
overcome now the water treatment plant has been commissioned.
The
deposits form growths or tubercles which restrict the flow in the pipe. With age the growths die and as a result
decompose and release foul odours and tastes.
The growths slough off the inside of the pipe and can cause orange
specks in the water which can stain washing.
There
is no simple or inexpensive way of controlling iron bacteria in distribution
systems.
The
growths can be minimised by using high chlorine residuals, treating the water
at source and lining of unlined cast iron pipes.
The
failure of cast iron is often at the joints.
Older
pipes are lead jointed. These joints
sometimes work loose due to internal pressure, earthquake, or traffic
vibration. The joints are repaired by
re-caulking where possible or by cutting out the joint area and replacing it
with a new section of pipe and two gibault couplings.
There
is also a possible health hazard with the lead dissolving in the water,
particularly near dead ends where there is reduced flow, and the water is in
contact with the joint for longer.
There
are proprietary processes to scrape and reline cast iron pipes with either
cement mortar or epoxy coatings. This
eliminates the effects of tubercles and lead joints as noted above.
It is
therefore proposed to investigate the feasibility of refurbishment of cast iron
reticulation pipes 100mm diameter and larger rather than abandoning them.
Cast
iron pipes may be weakened by changes to the chemical composition of the pipe
material over time, such as graphitisation.
Cast
iron pipes, being brittle are liable to damage due to traffic loadings and
point load over or under another service such as stormwater pipe, etc.
In
assessing the reason for a cast iron pipe failure the cause of the failure will
be carefully ascertained.
Table 5.2 Best Estimate of Condition of Cast Iron
Watermains
|
|
Very Good |
Good |
Fair |
Poor |
Very Poor |
Total |
|
·
Metres Length |
·
- |
·
- |
·
6,460 |
·
37,708 |
·
7,007 |
·
51,175 |
|
·
% |
·
- |
·
- |
·
12.6 |
·
73.7 |
·
13.7 |
·
100 |
1.30.4 Trunk mains
Figure
5.1 provides details of the age/material distribution of the Council’s water
supply pipework.
The
Maitai Pipeline was laid in 1963 using 900mm diameter concrete pipe on concrete
cradles. 750mm diameter steel pipe was
used for the syphons where the pipeline crosses from one side of the valley to
the other.
As
noted in Section 4.4.1 above the Maitai Pipeline is the highest risk asset.
Cycles
of direct sunshine and frosts have resulted in circumferential cracking of the
concrete pipes. In areas exposed to the
full afternoon sun there are typically three to four cracks per pipe. The flow from the cracks is usually no more
than a weep. In the more shady lengths
of the line the pipes are in excellent condition. The worst area is immediately downstream of
the dam as far as the first syphon.
The
pipeline is vulnerable to damage from rock fall which can be caused by either
major storms or earthquakes. The leakage
that can be caused by a rock fall is far more serious than the weeps from
circumferential cracks.
The
pipeline is inspected monthly and also following major storms and
earthquakes. In November each year an
engineering inspection is made.
An
inspection in 1998 identified movement in a section of the pipeline near Groom
Creek. This was caused by a large earth
flow following a period of heavy rain. A
100m long section of affected concrete pipe was replaced by a welded steel
pipe, supported on concrete columns, founded on solid ground beneath the
earthflow. This work cost $350,000 (1998
dollars).
Tonkin
and Taylor Ltd have completed a geotechnical assessment of the existing Maitai
Pipeline route. The level of risk is
rated from low to extreme and has been based on:
· Identification
of hazards (e.g. rockfall, slumping, shallow sides, etc);
· Likelihood
of the event or hazard (e.g. almost certain to unlikely rare);
· Consequence
of event hazard (e.g. from superficial damage – no leaks or obstructions to
catastrophic – multiple or greater than 10m of pipe destroyed, access lost,
loss of all flow).
No
section of the pipeline was rated extreme (i.e. immediate action required).
The
section of pipeline identified with the greatest risk is from the dam down to
the Fiddlers Elbow syphon. This section
is also the section with the most cracks, as noted above.
Since
1989 maintenance effort has been put into repairing the worst of the cracks and
sandblasting and painting the steel syphons. To clear the ground from under the
pipe to allow complete painting, it has been necessary to construct additional
concrete supports under the pipe.
Expenditure is approximately $60,000 pa.
In
2001 and 2002, as a result of increased awareness of possible terrorist,
sabotage or vandalism activities, security of the surge towers was improved,
rather than maintenance work on the pipes being carried out.
Proactive
maintenance of the pipeline was deferred in recent years until the future of
the line was determined.
In
2007 Council decided to replace the section of the pipeline from the Maitai Dam
to the Water Treatment Plant with a new pipe laid down the Maitai Valley
Road. The pipe size may be optimised by
providing pumping for peak flows. It was
also decided that the existing pipeline should be kept in use for as long as
possible to minimise pumping costs. As
the break even point is about 20 years, painting of the steel syphons should be
continued.
A
condition assessment of the steel pipeline section was completed in March 2011.
This report has evaluated the condition of the pipeline and provided
remediation specifications. The pipeline has significant sections requiring
repair and recoating. Provision for the work has been made in the financial
section table 6.3 for 2012-2015.
The
pipeline passes through a 240m long tunnel near the Tantragee Saddle. The timber shoring in the tunnel was upgraded
in 1994 and is considered to be in good condition. The tunnel is inspected annually.
The
section of the pipeline from the Water Treatment Plant to the Westbrook Terrace
valve chamber was assessed as having the least risk as the geotech and pipe condition
was the most favourable. On 30 July 2008
a section of the pipeline approximately half a kilometre downstream of the
Treatment Plant was damaged by wind thrown trees. Reinstatement of this section of pipeline
(WTP to Westbrook Terrace) with a pipeline laid in Tantragee Road, Brook
Street, and Westbrook Terrace is scheduled in the Capital Works programme to be
completed in 2016/17.
The
maintenance schedule to date is shown in Table 5.5.

Figure 5.2 Water Pipelines:
Age/Material Distribution
Figure 5.3 Theoretical Life Expectancy/Material
Distribution

Table 5.3 Maitai Pipeline
Maintenance Schedule (over next five years)
|
Location |
Work Done |
Work to be Done |
|||||
|
Support Blocks |
Painting |
Repairs |
Support Blocks |
Painting |
Repairs |
||
|
·
Fiddlers Elbow Syphon |
|
|
|
·
|
·
2012/15 |
·
|
|
|
·
River arch span ·
West abutment (true right) ·
East abutment (true left) |
·
·
1991 ·
2000 |
·
1989 ·
1992 ·
|
·
|
·
·
·
|
·
2012/15 ·
·
|
·
|
|
|
·
Motor Camp Syphon ·
River arch span ·
West abutment (true left) ·
East abutment (true right) |
·
·
·
·
·
1995 |
·
·
1980 ·
·
·
1996 |
·
|
·
Investigation 2011 ·
·
·
|
·
2012/15 ·
|
·
|
|
|
·
Andrews Farm Syphon ·
East abutment ·
West abutment |
·
|
·
·
1993 ·
1993 |
·
|
·
·
To be abandoned ·
To be abandoned |
|||
|
·
Brook Street Falling Main |
·
|
·
|
·
|
·
To be abandoned |
|||
|
·
Surge Towers and Valve
Specials |
·
|
·
|
·
2001/02 |
·
|
·
|
·
|
|
|
·
Tunnel Repairs |
·
|
·
|
·
1994 |
·
|
·
|
·
|
|
|
·
Concrete Pipe Crack
Repairs |
·
|
·
|
·
1996 |
·
|
·
|
·
ongoing |
|
|
·
Rockfall Protection |
|
|
|
|
|
|
|
The
Roding pipeline was constructed in the early 1940s at the same time as the
Roding weir. The pipeline runs through a
2.7 km long tunnel under the Barnicoat Range, down Marsden Valley and
along SH6 to Tahunanui.
The
timber shoring in the tunnel was upgraded in 1992 and is considered to be in
good condition. The tunnel and the
concrete pipeline within it are inspected annually.
The
remainder of the pipeline is constructed of steel pipe. Replacement should be programmed within 20
years on an age basis only. Condition
inspection was carried out in 2014 and subsequent analysis will be used to
determine the actual replacement timing.
Foothills
Trunk Mains: The Roding Transfer Pipeline was constructed in 2003/04 using
300mm and 375mm diameter ductile iron pipe.
Steel pipe, of the same size, was used where the pipeline crosses two
steeply incised creeks.
The
pipeline is made up of two pipes buried full length in the same trench.
One
pipeline carries raw Roding water from the Marsden Valley (raw water) trunk
main to the Water Treatment Plant. The
other pipeline carries treated water back to the Marsden Valley (treated water)
trunk main.
The
pipeline is inspected yearly, but is also continuously monitored by computer
for sudden changes in pressure and flow.
It is in very good condition.
Water
is pumped to a high point (250m) at the saddle between Brook and Enner Glynn
valleys. It then falls under gravity the
remaining distance. Pressure reducing
valves at the Marsden Valley end reduce the pressure to 170m maximum and at the
Water Treatment Plant to 7m.
The
raw water pipeline is also connected to a hydro electricity generator to
capture some of the energy of the water in the pipeline.
Other
Trunk Mains: The remainder of the trunk mains in the City have been installed
since the 1960s and are in good condition.
Refer to section 5.2.1 above regarding Asbestos Cement pipelines, and below
for steel trunk mains.
Steel
Trunk Mains: Steel pipe is used for trunk mains as they are larger diameter,
high pressure mains.
Steel
pipe suffers from electrolytic corrosion due to “cell effects” between the
steel pipe, other metals, and the soil.
Where electrons leave the pipe, the metal is eaten away. Properly coated
pipe is insulated from the soil and is therefore protected. The coating can however be incomplete, or
have been damaged during pipe laying.
The
trunk mains in Brook and Tasman Streets (between Larges Lane and Bridge
Street), and under the Maitai River (at QEII Drive) are protected by an
impressed current system where electrons enter the steel pipe via the coating
defect and exit to the soil in a special anode bed. The Fiddler’s Elbow Syphon on the Maitai
Pipeline is similarly protected, but with a sacrificial zinc anode.
The
systems were installed in 1995 and 1996 and are tested every three months for
correct operation, and audited every two years by an independent expert. In 2000 it was found that the ground anode
bed in Bronte Street needed replacement.
This was carried out in the 2001 financial year.
Above
ground pipes are inspected annually to ensure that the pipe coating (epoxy or
wrapping) is intact.
Because
steel pipes corrode through localised action as described above, sampling is
not a reliable means of determining pipe condition.
An
assessment of the above ground steel pipe sections was carried out in 2011 by
Inspection and Consultancy Services Ltd. This assessment concluded that the
condition of the protective coating of the above ground pipework was
“poor”. A maintenance specification has
been developed and budget provision made to allow the pipeline to continue to
operate for at least the next 10-20 years.
The
overall condition of the mains varies from fair to very good condition i.e.
Conditions Grade 1-3.
1.30.5 Headworks (including Dams and Intakes)
Maitai
Water Supply Scheme: The Maitai Water Supply Scheme was commissioned in
1987. The Scheme can abstract water from
the North Branch Reservoir or the run of river intake on the South Branch. The reservoir has a total live storage of
3.3M m3, and dead storage of 900,000m3.
The
Maitai Dam is an earthfill dam with crest height approximately 36m above the
North Branch riverbed. The performance
of the dam is monitored monthly and following major earthquakes. Tonkin and Taylor Ltd, the designers, carry
out an annual inspection of the dam and every five years independent
consultants review the original design against current practice.
Maintenance
work is programmed in response to their recommendations and those of the Maitai
Caretaker.
While
these procedures are effective at ensuring year to year reliability of the main
supply dams, more work is needed on assessing the longer term requirements for
items such as valves, pipework, and electronic equipment.
Assets
can fail for reasons other than physical failure. Among other modes are capacity failure,
obsolescence, and level of service failure.
Comprehensive
Safety Reviews (CSR) of the Maitai Water Supply Dam, which included the Annual
Inspection have been commissioned by Nelson City Council. Tonkin & Taylor
Ltd undertook the work in 2003 and Riley Consultants Ltd in 2009. The review is
to be repeated in 2014.
The
2003 review and inspection found the dam and associated works to be in a very
good condition, and to have been operated appropriately since the previous CSR
in 1998. Particular attention was paid
to reviewing the flood hydrology of the Maitai catchment and the role of the
dam in flood attenuation and the seismic risk associated with movement on
regional faults: the dam was found to be
appropriately designed and constructed in both respects.
Recommendations
were made for review of some operational aspects of mechanical equipment and of
the linkage of the existing dam emergency procedures with Nelson City Council’s
overall procedures in terms of an Emergency Action Plan and the associated
response procedures. This has been done.
The
latest CSR inspection was carried out in January 2014. The
final report was received in June
2014 (A1204425).
The
report concluded that the dam embankment, spillways, culvert and reservoir are
all in good condition.
Recommendations
were made as follows for the
next five years:



Roding
Dam: The Roding Weir was commissioned in 1940.
In 1972 the concrete structure was raised by 1.5m to its current height
of 11m above the downstream riverbed.
The
weir initially created approximately 40,000 cubic metres of storage. Major floods in 1985 severely damaged some of
the upper catchment so there are now significant amounts of gravel and sand
coming down the catchment that have filled in the storage behind the weir. This material has been removed but every time
the storage area was cleaned out nature simply delivered more material to fill
it in.
With
the need for storage reduced by the presence of the Maitai Dam, the decision
was taken to build an intake on the downstream face of the weir in 1988. As the
water flows over the weir some of it falls through the intake’s screens and
into the pipe work which then delivers it into the water supply system. This
has proved very effective and has stopped a lot of the silt and sand getting
into the water supply system. The volume
behind the weir has been allowed to fill in and it now appears to have reached
a stable level. The storage volume
behind the weir is now no more than 3,000 cubic metres. The diversion tunnel gate was renewed in
2002/03. It is now more readily opened
to allow gravel to be flushed through on the falling side of a flood, to
prevent gravel build up.
There
is a caretaker living on site at the Roding Weir. Routine maintenance work is programmed in
response to his recommendations.
The
scheme is considered to be in very good condition.
Building Act 2004 - Dam Safety Regulations
The
Building Act 2004 requires that dam owners assess their dam against regulatory
standards as being high, medium, or low impact in the event of failure, and to
provide that information to their regional authority.
In 2015 the Building and Construction Minister
confirmed that these requirements were to be removed from the Building Act and
new requirements would be considered for inclusion in the Resource Management
Act.
For existing dams, this must be done within three
months of the dam safety regulations commencing. The Building (Dam Safety) Regulations 2008
were promulgated on 7 July 2008 and were due to commence on 1 July 2010. On 10
June 2010 the Building and Construction Minister confirmed a two year delay in
commencement to allow a review of the regulations to be undertaken by
Parliament. This review has been
completed with final details with cabinet in 2014. The scheme is to come into
force on the 31 March 2015.
A dam classified as either medium or high potential
impact will require a dam safety assurance programme, to be prepared on a
prescribed form, and provide ongoing evidence of compliance. In June 2010 Tonkin & Taylor Ltd
completed an assessment of the dams within Nelson City as the first step in the
procedure. The work currently carried out for the Maitai Dam probably complies
but further assessment work may be necessary for the Roding Dam and York Valley
Dam.
1.30.6 Reservoirs
The
City has 21,900m3 of covered storage available.
The locations of the reservoirs are shown in Figure 2.2.
The
two reservoirs at Thompson Terrace were constructed in 1963 and 1974 and
provide total storage of 8,000m3. Both
reservoirs were strengthened in 1991/92 to improve the seismic performance. The 5,700m3 reservoir now meets Category 2
design requirements and the 2,300m3 reservoir Category 3 design requirements.
Table 5.4 Reservoir Risk Categories
|
Category |
Description |
|
·
2 |
·
Tanks which are intended to
remain functional in the emergency period for a major earthquake, for
example, fire fighting water. |
|
·
3 |
·
Tanks which should be
functional in the restoration period for a major earthquake, for example,
potable water. |
(From
NZS 3106: Code of Practice for Concrete
Structures for the Storage of Liquids)
The
Stoke Nos.1and 2 Reservoirs, Stoke High Level Reservoir (2,500m3 each), Walters
Bluff Reservoir (2,500m3), Clearwater Reservoir (3,000m3) and the Observatory
Hill Reservoir (300m3) are of more recent design and are a category 2 risk.
There
is both mechanical and electronic equipment at the reservoirs to control and
monitor refilling.
Reservoirs
are long life above ground structures.
Monthly routine maintenance inspections are carried out. Full condition and performance assessment are
carried out every five years.
In
2000, an engineering inspection was carried out on the roof structure of the
2,300m3 reservoir at Thompson Terrace.
It was found that the roof cladding was perforated and that some of the
trusses were badly corroded. The roof
was replaced in 2001/02 with fibreglass cladding supported by an external steel
structure.
A
further engineering inspection was carried out on the rest of the reservoir in
2002 while it was drained for roof construction. It was found that the water seals in the
floor were in need of replacement. This
has been completed.
In
November 2003 engineering inspections were carried out on Thompson Terrace No.
2, Stoke No. 1, Princes Drive and Glen Reservoirs.
Weathering
of the concrete dome roof of Thompson Terrace No. 2, corrosion of the internal
steel surface of the Glen reservoir, and blistering of the water seals in the
Stoke Reservoir were noted. Remedial
work of the Glen was completed in 2005/06.
Seals
in the Thompson Terrace No 2 reservoir were partly replaced after seepage was
noted in the underdrain collector.
Anodes were fitted to the internal ladder to prevent further corrosion.
Seismic
shut off valves have been retrofitted to the Stoke No.1 and Thompson Terrace
Nos.1 and 2 Reservoirs. The newer
Atawhai No. 1, Stoke High Level and Stoke No. 2 reservoirs were fitted with
seismic valves during construction.
The
pipework at the Thompson Terrace reservoirs has been modified to prevent “short
circuiting” of the water flow with possible water quality problems.
Work
on replacing the seals to Observatory Hill and Panorama Drive reservoirs was
completed in 2010.
An
additional reservoir at Observatory Hill is under construction in 2014 to provide
water storage for the residential subdivisions in the area. This reservoir has
a 440 cubic metre storage capacity.
All
reservoirs are considered to be in very good condition, i.e. Condition Grade 1
– Very Good.
1.30.7 Pump Stations
Nelson
has a gravity fed system. (The Marsden
Supply is at 170m City Datum and the Clearwater Reservoir at 155m City
Datum). There is therefore low
dependency on pumps.
The
City has eight pump stations. The
locations are shown in Figure 2.2. All
have been constructed since 1990 and are in good condition.
At
both ends of the Foothills Trunk Main (commissioned 2004) are large inline pump
stations. These are critical for the
transfer of water to and from the Water Treatment Plant.
The
pump stations are inspected weekly, with individual components serviced
regularly.
There
is a large inline underground pump on the cross town trunk watermain in Van
Diemen Street. This was designed to boost the flow from the Treatment Plant to
Stoke via the Thompson Terrace Reservoir at times of high demand. It is regularly used to part fill Thompson
Terrace to maintain the operation of the pump and reduce the risk of
sedimentation in the pipework.
There
are five other relatively small above ground pump stations that boost water to
higher hillside properties. These are Panorama Drive (two pumps), Princes Drive
(two pumps), Austen Ward Heights (one pump), Springlea (two pumps), and Wastney
Terrace (three pumps, commissioned in 2008).
Monthly
routine maintenance and inspections are carried out. Full performance and condition assessment are
carried out every two years.
The
pump stations follow a ‘rolling’ pump overhaul programme. The Van Diemen Street pumps were overhauled
in 2010. These works are funded from
maintenance budgets, which cannot be exceeded.
The
condition of the pumps stations is considered to be very good, i.e. Condition
Grade 1 – Very Good.
1.30.8 Pressure Reducing Valves
The
City has 32 pressure reducing valves in the reticulation system, (refer to
Section 2.4.3). Their locations are
shown in Figure 2.2.
Three
pressure reducing valves are located at the Marsden Pump Station on the
Clearwater Foothills Trunk Main and one is located at the Water Treatment Plant
on the raw water foothills trunk main.
These
were installed in 2004 as part of the Water Treatment project.
The
water maintenance contract has been amended to provide for more preventative
maintenance to be carried out on the pressure reducing valves so the potential
for malfunction is reduced.
At
present, pressure gauges linked to the alarm system monitor the performance of
10 of the pressure reducing valves.
These gauges monitor the pressure in the reticulation and generate an
alarm if the pressure moves outside set tolerances. The alarm allows maintenance staff to respond
to a malfunctioning pressure reducing valve before the excess pressure damages
both public and private pipe work.
It is
intended to progressively install gauges to monitor the performance of the
remaining pressure reducing valves over the next five years.
The
condition of the pressure reducing valves is considered to be very good, i.e.
Condition Grade 1 – Very Good.
1.30.9 Service Pipes and Meters
Service
pipes are the pipes between the watermain and the property street
boundary. These pipes are part of the
water asset. Pipe materials used are
galvanised iron, copper and polyethylene.
Galvanised pipes were installed prior to the 1950s. Copper was installed from the 1950s to the
1990s. In recent years polyethylene has
been installed.
The
quantity of each type of pipe is unknown.
Whenever a street is upgraded or a new watermain is laid the water
service pipes are relaid if they are galvanised. This procedure has been in force since
1990. The condition of service pipes
varies from very good to unserviceable, i.e. Condition Grade 1 to 5.
Supply
pipes are the pipes between the property boundary and the building on the site.
These pipes may be shared by several properties where there is a Right of Way
or Cross Lease access. Supply pipes are
privately owned.
All
properties connected to the Water Supply are metered. Meters and manifolds are generally situated
at the property street boundary. The
exception is where one or more properties are served by a common supply
pipe. In this case the meter is located
in a practical location where the supply pipe branches to serve only one
property. The meter and manifold is part
of the water asset, although it may be sited on private property on a private
supply pipe.
Manifolds
were installed as replacements for all residential toby repairs, and on all new
subdivisions from 1993. Manifolds were
installed on all other residential properties in 1997 and 1998 as part of the
Universal Metering Project. Meters were
installed into these manifolds in the first six months of 1999.
These
manifolds are in very good condition, i.e. Condition Grade 1 – Very Good.
In
2009 a small sample (23) of residential water meters were bench tested for
accuracy by Water Meter Services Ltd as part of the water losses
investigation. These tests were carried
out at flows or 0.38 litres per minute, 15 litres per minute and 50 litres per
minute. The results show readings
ranging as follows:
Flow
0.38 litres per minute -27.3% to +3.47%
Flow
15 litres per minute -3.31% to +0.77%
Flow
50 litres per minute -31.87% to -1.02%
The
variability confirmed a general view that some losses must be attributed to
meter performance. The testing was
repeated in 2013 to monitor changes and to begin developing a failure curve.
Renewal of the simple double check valve assembly in the meter manifold has
been identified as a priority, owing to ongoing failure of these units. Budget
for this work is shown starting from 2015/16.
The
increasing use of automated meter reading technology in the power supply
utility field offers real advantages to the water supply activity, principally
in reducing costs of meter reading and billing and providing early warning of
excess water use that may be an indication of leaks. To investigate the feasibility
of adopting this technology it is proposed to develop a trial with a technology
supplier in 2014/15.
The future proposed renewal of residential
water meters, scheduled over a three year period from 2017/18 at $1,000,000 per
year, may make use of new technology if the proposed trial delivers positive
results.
Meters
on commercial and industrial properties vary in age and size. Most meters have been installed since 1980 in
business groups i.e. all schools, all hotels, all hairdressers etc. Meters were installed on parks in 1998, on
small users such as offices and small shops as part of the Universal Water
Metering project in 1999, and in new subdivisions and developments as they
occur.
Trends
in each property’s water usage are tracked and if a meter appears to be
“slowing down”, then it is removed for testing or replacement. Worn meters tend to under-read and are
therefore in that customer’s favour, but true costs are not being recovered
from the customer who is therefore subsidised by other consumers.
Renewal
of commercial and industrial water meters is scheduled over a 9 year period
from 2014/15 at $300,000 per year.
The
meters therefore range from near new with a condition assessment of very good
to nearly 30 years old i.e. Condition Grade 1 to 5 – Very Good to Very Poor.
1.30.10 Water Treatment Plant
Commissioned
in August 2004, the Water Treatment Plant is made up of several hundred
components. Each component is maintained
regularly on a scheduled maintenance programme in accordance with vendor data.
Operators
stationed at the plant regularly inspect, check and calibrate components of the
plant to ensure they are performing their design function. The cost of routine maintenance is covered by
an operations contract with an external contractor.
Large
portions of the plant and the components are computer monitored and alarms are
raised if they go outside predetermined performance limits.
The
plant and equipment is in Grade 1 – Very Good condition.
In
2012 an S:CAN unit was installed at the treatment plant to measure the
following parameters in the raw water:- total organic carbon, dissolved organic
carbon and turbidity; and automatically adjust chemical coagulation dosing.
Early results are promising with more efficient use of coagulation chemicals possible.
In
2013 Council commenced a trial of dosing the raw water delivery from the Maitai
with carbon dioxide as a means of adjusting the pH below 8 which will improve
the efficiency of the coagulant chemicals used to remove organic loading in the
raw water. The pilot trial has
proven to be successful in reducing chemical use and the operational contractor
is currently making provision for a more permanent installation.
1.30.11 Asset Condition and Performance: Land, Access Roads, Fences, Landscaping and
Houses
Land,
access roading, fencing and landscaping have now been included in the asset
register. These facilities are regularly
maintained and are in good condition.
The houses at the Maitai and Roding waterworks are listed in Council’s
fixed asset register.
1.31 Background
The
works proposed in the previous sections on Levels of Service, Future Demand,
Risk Management and Lifecycle Management all impact on expenditure.
There
are cost implications in:
· Meeting
levels of service;
· Meeting
future demand;
· Managing
risk;
· Maintaining/improving
asset condition;
· Maintaining/improving
asset performance;
· Operating
assets;
· Maintaining
assets;
which
affect the Operations and Maintenance Renewal, and Capital Financial Plans.
Depreciation
is an expense which allows for the future replacement of an asset by setting
aside its replacement value during its working life.
Operations
and Maintenance is an expense to run assets and keep them in good working
order.
Renewals
are an expense to replace existing assets.
Capital
is an expense to create new assets.
1.32 Asset Valuation and
Depreciation
1.32.1 Valuation Method
The
Maitai Water Supply Scheme, the Maitai Pipeline, the Roding Weir, the Roding
Pipeline, the Roding Tunnel, the Thompson Terrace Reservoirs, the Walters Bluff
Reservoir, the Ridgeway Reservoir, the Glen Tank and the Observatory Hill
Reservoirs have been valued by Opus International Consultants in 2014.
All
pipelines have been valued based on optimised replacement costs (ORC), assuming
the use of modern techniques and pipe materials. The prices for reticulation pipes are based
on recent costs for similar work within Nelson City.
The
value of pump stations, pressure reducing valves and the remaining reservoirs
was based on recent costs for similar work within Nelson City.
The
values were peer reviewed by Opus International Consultants Ltd.
All
costs are reported in June 2014
dollars and Goods and Services Tax is not included in the costs.
All
assets have been revalued as at 30 June 2014.
In
addition to direct purchase/construction costs, professional fees for
investigation, resource consent (where applicable), design, construction and
‘as built’ information have been included.
Valves,
hydrants, service pipes, meters, manifolds and boxes have been valued
separately.
Financial
charges incurred in carrying project costs in the period prior to commissioning
have not been included.
Replacement
costs have been optimised to represent the lowest cost and most efficient
combination of assets providing the same service as the existing assets. Optimisation involves adjustment to deduct
any surplus capacity or over design.
Land,
access roads, caretakers’ houses and fencing are not included on the inventory,
as they are recorded in Council’s Fixed Asset Register.
Table
6.1 shows the total optimised replacement value of the Nelson City Council
water supply system to be $246.6
million (June 2014
dollars, excluding GST).
Table 6.1 Water Supply Asset Valuation - June 2014
|
·
Asset Category |
·
Quantity |
·
Unit |
·
Replacement Value $,000s |
|
Reticulation High Pressure |
104.1 |
km |
32,399,508 |
|
Reticulation Low Pressure |
219.9 |
km |
61,301,794 |
|
Trunk Mains |
39.9 |
km |
18,455,112 |
|
Maitai Pipeline |
9.3 |
km |
17,666,517 |
|
Roding Pipeline |
3.9 |
km |
2,160,916 |
|
Maitai Water Supply Scheme |
|
|
20,670,500 |
|
Roding Dam |
|
|
2,859,900 |
|
Treatment Plant |
|
|
20,191,669 |
|
Tunnels |
3 |
No |
11,677,100 |
|
Reservoirs and Tanks |
37 |
No |
13,155,170 |
|
Pump Stations |
11 |
No |
2,544,228 |
|
Pressure Reducing Valves |
32 |
No |
383,922 |
|
Air & Non Return Valves |
136 |
No |
324,224 |
|
Gate Valves |
3,349 |
No |
7,273,282 |
|
Manholes |
94 |
No |
343,288 |
|
Hydrants |
2,481 |
No |
6,323,027 |
|
Meters |
20,252 |
No |
3,037,432 |
|
Customer Connections |
20,161 |
No |
25,913,634 |
|
Total |
xxx) |
|
246,681,222 |
1.32.2 Depreciation
The value
of the assets has been depreciated on a straight-line basis over their nominal
working life. Table 6.2 shows the
nominal working life or total life (TL) of each of the classes of assets.
The
nominal working life of the reticulation pipework is based on a survival model
prepared on the basis of experience of 10 European water supply systems. The results of the model show good agreement
with the experience to date in Nelson City.
High
pressure reticulation was assigned a slightly shorter life because of the
greater working stresses the pipe and fittings will experience.
Trunk
mains have been assigned a shorter life again, because of the more serious
implications of a pipe failure and the consequent need for a higher standard.
Fixed
structures such as dams, tunnels and reservoirs have been assigned a life of
expectancy of 100 years.
Pump
station structures have been assigned a life expectancy of 100 years,
pipes/valves a life of 70 years, and pumps/control equipment 20 years.
The
construction year for each individual section of pipe has been researched from
field books, plans and other records.
This information has been entered into the database to allow the age of
the pipes to be calculated.
Sometimes
assets have either a positive salvage value or significant disposal cost (that
is, a positive or Negative Net Realisable Value (NRV)).
Watermains
are generally relaid off line and the existing pipes left in the ground. Thus zero NRV has been assigned to these
items.
Sometimes
an asset may have a Residual Value (RV) at the end of its economic life,
instead of being totally removed or replaced, all (or part) of it continues to
be used. It has been assumed that the
items have zero residual value.
Table 6.2 Nominal Working Life of Water Assets
(Years)
|
Type |
Low Pressure |
High Pressure |
Trunk Main |
Maitai Pipeline |
Roding Pipeline |
|
·
Asbestos Cement (Black) |
·
80 |
·
70 |
·
65 |
·
|
·
|
|
·
Asbestos Cement
(Fibrolite) |
·
80 |
·
70 |
·
65 |
·
|
·
|
|
·
Ductile Cast Iron |
·
110 |
·
95 |
·
90 |
·
|
·
|
|
·
Pit Cast Iron |
·
120 |
·
105 |
·
100 |
·
|
·
|
|
·
Spun Cast Iron |
·
100 |
·
90 |
·
85 |
·
|
·
|
|
·
Concrete |
·
|
·
65 |
·
60 |
·
58 |
·
75 |
|
·
Copper |
·
90 |
·
80 |
·
75 |
·
|
·
|
|
·
Galvanised Iron |
·
70 |
·
55 |
·
50 |
·
|
·
|
|
·
HDPE |
·
85 |
·
70 |
·
65 |
·
|
·
|
|
·
PVC |
·
85 |
·
70 |
·
65 |
·
|
·
65 |
|
·
Concrete Lined Steel |
·
90 |
·
80 |
·
75 |
·
|
·
75 |
|
·
Pitch Lined Steel |
·
90 |
·
80 |
·
75 |
·
58 |
·
|
|
·
|
Life (Years) |
|
|
·
Manholes |
·
|
|
|
·
|
·
Standard < 1250 dia |
·
84 |
|
·
|
·
Standard >= 1250 dia |
·
72 |
|
·
|
·
Flow measuring manholes |
·
50 |
|
·
|
·
Meter manhole |
·
80 |
|
·
Valves |
·
|
|
|
·
|
·
Air/NRTN |
·
35 |
|
·
|
·
Pressure Reducing |
·
35 |
|
·
|
·
Gate valves <250 dia |
·
84 |
|
·
|
·
Gate valves >=250 dia |
·
72 |
|
·
Hydrants |
·
|
|
|
·
|
·
<250 dia |
·
84 |
|
·
|
·
>=250 dia |
·
72 |
|
·
Maitai Water Supply Scheme |
·
|
|
|
·
|
·
Dam and platform |
·
200 |
|
·
|
·
Concrete structures
(spillway etc) |
·
100 |
|
·
|
·
South Supply Intake |
·
50 |
|
·
|
·
Roding Dam |
·
100 |
|
·
Other |
·
|
|
|
·
|
·
Reservoirs |
·
100 |
|
·
|
·
Tunnels |
·
100 |
|
·
|
·
Stoke reservoir overflow
pipe |
·
80 |
|
·
|
·
Manifold and meter boxes |
·
80 |
|
·
|
·
Service laterals |
·
80 |
|
·
|
·
Meters |
·
15 |
Straight
line depreciation is used.
Because
the NRV and Residual Value are zero, the Depreciated Replacement Cost
(Depreciated Value) is given by
DRC = RC *
Where
DRC is Depreciated
Replacement Cost
RC is
Replacement Cost
TL is
Total Life
The Depreciated
Replacement Cost for each item has been calculated and each class of items has
then been aggregated to give the Depreciated Values in Table 6.1.
The
depreciated optimised value of the water supply system is assessed at $125
million (June 2012 dollars, excluding GST).
1.32.3 Assumptions
Table
6-3 details possible and actual significant forecasting assumptions and
uncertainties relating to the Nelson City Council water supply activity.
Assumptions for 2015-25 Nelson Long Term Plan
Council
is required to identify the significant forecasting assumptions it has made in
preparing its ten year Long Term Plan.
Assumptions are necessary to allow Council to plan for expenditure and
costs over the next ten years. They are
the best reasonable assessment made on the basis of currently available
information.
Table 6-3: Significant
Forecasting Assumptions and Uncertainties 2015-25
|
Forecasting
Assumptions |
Risk |
Impact |
Comment |
|
Population growth: Based on advice from Statistics
New Zealand in February 2015, the population in Nelson has grown faster than
was expected. Nelson’s population is expected to grow by 3,600 residents in
the next 10 years to almost 53,400 by 2025. The age group with the biggest proportional
increase is those over 75 years, which will rise from 8% in 2015 to 20% by
2045. The rate of population growth is then expected to
slow down after 2025, reaching 56,000 in 2045. The number of households in Nelson is projected to
increase by about 1,800 in the next 10 years to reach almost 22,400 in 2025,
and almost 24,200 in 2045. Approximately half of the growth during the life
of this Long Term Plan will be in the wider Stoke area. |
Growth
higher than projected, putting pressure on Council services and
infrastructure. The age
profile could vary from forecast, with more accelerated ageing putting
pressure on certain services/facilities. |
Low |
Council takes
a generally conservative approach in applying population growth estimates in
its infrastructure planning, using a mid-range estimate and continually
updating and revising as new data is available. This limits the risk
exposure. |
|
Affordability: The Nelson Tasman economy has grown
more slowly than the national average for a number of years but overall has
weathered the global economic downturn reasonably well. Council is taking a
cautious approach to prospects for the regional economy, noting that the
ageing demographic will bring older residents who are no longer in employment
and potentially less able to afford increasing rates. |
Economic
pressures lead to more residents defaulting on rates payments than expected. |
Medium |
This will
be a medium to long term impact particularly if, as predicted, the average
retirement age also rises significantly. |
|
Census data shows that those entitled to
superannuation in paid employment is less than the national average, however
this may change as the age of superannuation entitlement may be raised over
the period of this Long Term Plan. Housing affordability in the area continues to be
an issue, with Nelson remaining in the five least affordable regions in New
Zealand (Statistics
NZ, Roost). |
There is
a risk that as a result of a higher cost of living in the region and the
higher percentage of older residents, that there may be difficulties in
attracting key staff |
|
The
risks of an ageing demographic may be balanced by the potential to bring
economic opportunity to the region in specific industries such as retirement
villages, and specialised services. |
|
Inflation/Price changes: Council uses inflation
forecasts from Business and Economic Research Ltd (BERL) to estimate inflation
over time. These figures were updated in September 2014, and are prepared
specifically for Local Government. It is assumed that inflation rates are as
predicted and modelled in budgets. Year end -ing CPI% BERL LGCI Opex % BERL LGCI capex % BERL LGCI % 30-Jun-16 1.7 2.2 2.3 2.2 30-Jun-17 1.9 2.3 2.6 2.5 30-Jun-18 2.0 2.4 2.6 2.5 30-Jun-19 2.1 2.6 2.7 2.6 30-Jun-20 2.1 2.7 2.8 2.8 30-Jun-21 2.2 2.9 3.0 2.9 30-Jun-22 2.3 3.0 3.1 3.0 30-Jun-23 2.4 3.1 3.3 3.2 30-Jun-24 2.4 3.3 3.5 3.4 30-Jun-25 2.5 3.4 3.7 3.5 CPI = Consumer price index LGCI = Local government cost index Opex = Operating expenditure Capex = Capital expenditure |
Inflation
higher than expected, increasing costs for Council. |
Medium |
Likely
to be some variation in actual rates of inflation from predictions and this
will impact on the financial results of Council. Changing costs may mean the
timing of projects needs to be adjusted. Council
has relied on the current parameters the Reserve Bank is required to operate
under in terms of inflation being held within the range of 1 – 3 % |
|
Interest rates: In preparing the Long Term Plan
Council has assumed an interest rate of between 5.15 and 5.45%. Assumptions
are based on detailed analysis of the cost of both existing and future debts and
anticipated interest rates. |
The
prevailing interest rates differ significantly from those estimated by the
Reserve Bank of New Zealand. |
Medium |
Increase
in interest rates flow through to higher debt servicing costs and higher
rates funding requirements. Council has mitigated these risks with a prudent
hedging programme developed within the limits of a prudent treasury policy. |
|
Development contributions: Assumptions on
development contributions are included in the updated Development and
Financial Contributions Policy. With changes to the legislation around
development contributions there is uncertainty about the level of
contributions and any costs associated with the new processes. Council has
assumed it will collect $1.2 million per year in Development Contributions
during the 10 year of the Plan. Not all lots available for development will be
developed during the 10 years of the Plan and therefore the development
contributions collected will be less than the maximum calculated under the
policy. |
The
level of development contributions collected could be insufficient to cover
the costs of required growth infrastructure. Low |
Low Low |
Costs
for infrastructure will need to be met from other allocations. Council
has made a conservative estimate of income from development contributions. |
|
Climate change and natural disasters: It is
assumed that natural disasters will occur with increasing frequency. This has
been the experience of recent years and is consistent with predictions of
climate change impacts. Exposure of low lying land to the risk of inundation
from sea level rise is another assumption related to climate change. Council
relies on Ministry for Environment guidelines in estimating sea level rise.
Council’s Land Development Manual currently provides for a 0.5m sea level
rise by the end of the century but this will be reviewed in line with the
latest MfE advice (1m for 100 years). The Nelson Tasman Civil Defence Emergency Plan
states that the most significant natural hazards for Nelson are: earthquakes
(greatest impact) and flooding (most likely). The probability of a magnitude 7 earthquake in
Nelson is 87% in the next 50 years, and 98% in the next 100 years. The
probability of a magnitude 8 earthquake is 43% in the next 50 years, and 67%
in the next 100 years. |
Climatic
events lead to increased costs for Council in both responding to events and
building greater resilience into infrastructure. |
Medium |
A
characteristic of the Nelson community is the concentration of lifelines
infrastructure (roading network, port, airport etc) on low-lying areas.
Council has been increasing its contributions to the Emergency Fund as one
method of mitigating the risk of natural disasters. |
|
Hazards: It is expected that dealing with
contaminated land in capital and maintenance projects will become more common
as the HAIL register is refined and added to. |
Investigation,
consenting, handling and disposal of contaminated material lead to an
increased overall cost of projects. |
Medium |
Increased
design and construction budgets in the annual and long term plans. If
Council has made past decisions that were compliant with the legislation at
the time of consent being granted, then it is unlikely that it would then be financially
liable for remediation or mitigation of identified hazards after that time. In
relation to the private use of land, council has a duty of care in issuing
LIM’s, and must ensure that an applicant has been informed properly and
fairly about relevant features or characteristics of the land and its uses.
Council includes HAIL information on LIM reports to ensure all known
information is made available. In granting a resource consent, where there
are likely or known hazards, then any consent issued requires these hazards
or adverse effects to be mitigated or removed. |
|
Useful lives of significant assets: It is assumed
that there will be no reassessment of the useful lives of assets during the
10 year period covered by this plan. The detail of useful lives for each
asset category is covered in the Statement of Accounting Policies. |
Assets
wearing out earlier than predicted and funding needs to be found for
replacements. |
Low |
This may
result in changes needing to be made to the underlying capital expenditure
programme. |
|
Loan arrangements: It is assumed that Council’s
bankers will continue to renew the existing loan facilities. |
Access
to committed loan facilities less than expected. |
Low |
The Local
Government Funding Agency now in place should allow Council to diversify
funding sources away
from the local banks as well as being able to borrow for longer terms. |
NZ Transport Agency funding: NZTA has reviewed the
principles and methods used in setting its financial assistance rates. For
2015/16 the FAR will be 47% and will rise by 1% per year to 51% over six
years. |
NZTA
providing less funding than currently indicated and Council’s share of
project costs therefore increasing. |
Medium |
Changes
to the funding priorities of NZ Transport Agency are outside Council control. |
|
Weather tight
building claims: It is assumed that there will continue to be claims for
weather tightness but these will not be significantly more than accounted
for. |
Claims on Council
higher than forecast. |
Medium |
A higher level of
claims would impact on rates by increasing the rate requirement. |
|
Earthquake
prone buildings: It is assumed that Council will face ongoing costs with
regard to earthquake prone building assets, but that decisions about works to
undertake and the timing of any necessary works will allow costs to be
adequately spread. The
proposed Building (Earthquake-Prone Buildings) Amendment Bill proposes that
Councils must complete seismic capacity assessments of specified buildings
not later than 5 years after the day the Act comes into force. New work
is identified, or required work is more significant than anticipated. Medium Significant
additional expenditure on earthquake strengthening buildings could not be met
by the current budget. |
New work
is identified, or required work is more significant than anticipated. |
Medium |
Significant
additional expenditure on earthquake strengthening buildings could not be met
by the current budget. |
|
Resource consents: It is assumed that resource
consents held by Council will not be significantly altered and any due for
renewal during the life of the plan can be renewed accordingly. |
Conditions
of resource consents altered and significant new compliance costs or consents
cannot be renewed as expected. |
Medium |
Budgets
are in place for renewal of resource consents and there is no expectation of
significant departure from requirements over the next 10 years. |
|
Vested Assets: It is assumed that vested assets
increase by $3m per year adjusted by inflation. Council assumes that the impact of vested assets will be
neutral, in that the costs associated with the additional assets will be
offset by a proportionate increase in rates revenue. |
That
Council will have more assets vested thereby increasing the depreciation expense in subsequent years that is not
offset by a proportionate increase in rates revenue. |
Low |
Assets
must be maintained by Council, so there would be an impact on costs if more assets
than expected were vested in Council. An example of where a vested asset may
increase cost to Council is where land is bequeathed to be maintained as a
reserve, or similar. Vested
assets can fluctuate from year to year but the impact is ordinarily offset by
a proportionate increase in rates revenue. It would be highly unusual for
Council to enter into an arrangement with a developer where the ongoing costs
associated with the vested assets are disproportionate to the increase in
rates revenue. |
|
Insurance costs: It has been assumed that
insurance premiums continue at current levels plus inflation and that we can
get 100% cover and that the Local Authority Protection Programme Disaster
Fund continues |
Premiums
increasing above inflation and/or Council cannot get 100% cover. |
Medium |
Any
increase in premiums above the level assumed will have an impact on rates.
Council may need to make decisions about cover levels during 10 year period. |
|
Return on investments: It is assumed that the
return on investments and retained earnings on subsidiaries will continue at
current levels plus inflation. While planning in the Long Term Plan will take a
conservative approach with expected returns on investments, there will be an
expectation when agreeing on annual performance that higher returns will be
generated. |
Returns
lower than expected. |
Low |
This
would impact on Council’s ability to fund services and infrastructure and
would likely require an increase in rates. |
|
Government Policy Changes: It is assumed that any
future Government legislation changes will take into account the need for a
stable working and statutory framework. The Government has made known its intention to
reform the Resource Management Act 1991, to receive a report back from the
Rules Reduction Taskforce, and to continue to seek ways of addressing housing
affordability and social housing need. It has also introduced the Building
(Earthquake-Prone Buildings) Amendment Bill which includes a requirement on
Councils to complete seismic assessments and to earthquake strengthen
specified buildings. Further changes to legislation impacting on local
government may take place, but this is not known at this time. It is assumed
that Government will work with Councils to ensure that any legislative
changes are managed appropriately. |
Government
policy shifts may result in new or amended legislation either requiring
significant response and cost to administer by Council or result in changes
to services delivered. |
Medium |
Financial
impact resulting from a need to respond to significant legislation changes
would impact on rates or fees and charges. It is
not possible to quantify the potential financial impact of any future
legislative changes at this time. |
|
Co-funding arrangements: It is assumed that for
projects where other partners are contributing part of the funding, this
funding will still be available. |
Partners
will no longer be in a position to provide funding which will result in an
increased level of input from Council, or the termination of the project |
High |
Viability
of projects would be threatened and Council would need to consider its
ongoing funding commitment. |
|
Treaty Settlements for Te Tau Ihu: It is assumed
that Council obligations to work with Iwi as a result of Treaty settlements
can be met within existing resources. This may involve provision of training to current
staff, increased emphasis on relevant experience in the recruitment of new
staff, or a need in some instances to employ external assistance. |
Establishing
new ways of working with Maori requires greater Council resource than
anticipated. |
Low |
Financial
impact of dedicating resources to meet Treaty commitments would impact on
rates |
|
Emissions Trading Scheme: New climate change
agreement to be concluded by end of 2015 to come into force by 2020 which
will increase costs to Council for waste disposal to landfill and increase
costs for the operation of the landfill site. |
Carbon
pricing costs higher than expected or impact earlier. |
Medium |
Financial
impact of responding to unexpected changes in carbon pricing would affect
rates. |
|
Accounting Policy: Nelson City Council’s
accounting policy provides for its most significant asset classes
(infrastructure assets and land, excluding land under roads) to be revalued
with sufficient regularity that the carrying value does not differ materially
from fair value. Infrastructure assets are revalued annually and land is
reviewed annually and revalued at least every five years or if there is a
material movement. For the purposes of this long-term plan, land revaluation
is assumed to occur in years 2, 5, and 8. Council’s investment property is
revalued annually in accordance with generally accepted accounting practice. Revaluations have been based on the Business and
Economic research Ltd (BERL) forecasts of price level change adjusters and
revaluation movements are shown in the prospective Statement of Comprehensive
Revenue and Expense. |
Actual
revaluation results differ significantly from those forecast in this long
term plan. |
Medium |
If the
revaluations are different from those forecast it will affect fixed asset
values and impact levels of depreciation expense and the rates funding
requirement. Future
Annual Plans and Long-term Plans will reflect the outcomes of actual
revaluations. |
|
Growth in rating units: The estimated growth in
the City’s ratings units is 1% for each of the 10 years of the Long-term
Plan. As a
result, the ‘real’ average increase in rates funding required is reduced by
an equivalent amount as there are a greater number of ratepayers across which
the rates funding requirement will be allocated. |
Growth
in rating units is higher or lower than projected. |
Low |
Council
has used current property information from its valuation service provider
(Quotable Value) to assess the level of growth in rating units, along with an
assessment of year by year increases from recent years. |
|
Sources of funds for the future replacement of
assets: It is assumed that funding for the replacement of existing assets
will be obtained from the appropriate sources as detailed in Council’s Revenue
and Financing Policy. |
That a
particular funding source is unavailable. |
Low |
Depreciation
is used to fund renewals and is funded mainly through rates and user charges.
Should other |
Assumptions
As well as the general assumptions that apply as the basis for
forecasting budgets across Council’s work, the following assumptions apply
specifically to water supply:
Council assumes renewals will be continued at a rate that is sustainable,
based on consideration of both resource and financial aspects
It is assumed that Nelson’s climate will remain substantially unchanged
for the next decade, with enough rain to meet our water needs. Factors such as
climate change and population growth will receive increased analysis as the
Infrastructure Strategy is reviewed in future years
It is assumed that new resource consents for the existing sources of
water supply and abstraction volumes will be granted
It is assumed that there will be
reductions in water losses
Water supply is expected to continue to be funded from water charges
and, consistent with Council’s financial policies, most of the capital
expenditure will be funded from borrowings
Council will provide education and promotion of the importance of water
conservation; however the demand for water is expected to continue to primarily
be managed through Council’s water charging system
The service delivery strategy is expected to be sustained for the term
of this Long Term Plan
Existing treatment plant membranes will continue to operate
satisfactorily.
1.33 Operations and
maintenance plan
1.33.1 Background on Operations and Maintenance
i) Operations
Operations is the
running of the water supply system. It
includes:
· Management;
· Engineering
supervision;
· Electricity
and telephones;
· Meter
reading and billing.
ii) Forecast
Maintenance Programme
Planned maintenance is
discussed in Section 5 Lifecycle Management Plan.
As expenditure on
condition assessment, planned maintenance, condition modelling and optimised
renewals is increased, reactive maintenance should be reduced. However, there may be little overall
reduction in maintenance expenditure.
The real benefit will be a reduction in unplanned shutdowns and
disruption to consumers caused by breaks and failures.
iii) Routine
Maintenance
Routine Maintenance is
the regular on-going day-to-day work necessary to keep assets functioning
including instances where portions of the asset fail and need immediate repair
to make the asset operational again.
This includes:
· Regular
and ongoing annual expenditure necessary to keep the assets at their required
service potential;
· Day-to-day
and/or general upkeep works designed to keep the assets operating at required
levels of service;
· Works
which provide for the normal care and attention of the asset including repairs
and minor replacements;
· Unplanned
(corrective) maintenance, i.e. isolated failures requiring immediate repair to
make the asset operational again
iv) Planned
Maintenance
Planned Maintenance is
carried out in accordance with the requirements of the Utility Services
Maintenance Contract.
Additional planned
maintenance work is carried out on the reticulation to address faults
identified by the leak detection work.
v) Unplanned
(Reactive) Maintenance
Reactive maintenance
is carried out in accordance with the requirements of the Utility Services
Maintenance Contract.
vi) Maintenance
Standards
The work performed and
material to be used complies with the Nelson City Council Land Development
Manual 2010 (and subsequent amendments) and all relevant New Zealand Standards,
in particular those listed in the Utility Services Maintenance Contract.
1.33.2 Assumptions
It is
assumed that operations and maintenance will be carried out at the same levels
as at present. Where there are specific
one off or periodic items (such as the three yearly review of the Water
Treatment Plant contract) these have been allowed for in the financial plan.
1.33.3 Level of Service Implications
The
key levels of service are pressure, flow, quality and reliability.
For the
water supply system to deliver the levels of service it must be intact and
functioning. Reactive maintenance must
be carried out promptly. Planned
maintenance must be carried out to ensure that downtime is minimised by
carrying out maintenance before it becomes reactive.
1.33.4 Demand Implications
With
increasing demand there will be an increase in total variable costs
particularly as more water is treated and pumped.
1.33.5 Risk Implications
Intakes,
raw water trunk mains, the Water Treatment Plant, treated water trunk mains and
reservoirs must all be maintained, kept secure and protected from natural
hazards so that they can continue to function through an emergency albeit at a
reduced level of service.
1.33.6 Lifecycle Implications
Operations
and maintenance is the longest period of the asset lifecycle and ongoing
maintenance is necessary to ensure that the design life of the asset is
achieved.
1.33.7 12 Year Operations
Table
6.3 shows the planned 12 year operation and maintenance financial plan.
1.33.8 Sensitivity
Treatment
and pumping are dependant on demand. In
dry summers the demand by domestic irrigation is high and so total costs of
treating and pumping water are higher however revenue is also increased.
Routine
Planned Maintenance is essential so that assets do not fail unexpectedly,
leading to other failures. For example
regular maintenance of a pressure reducing valve ensures that it works
correctly and does not fail, introducing high pressures into the system that
cause pipes to fail.
Table 6.3.1 Water Supply Operation and
Maintenance Projections
|
Year |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
|
|
Long Term Plan |
2015/25 LTP |
2018/28 LTP |
2021/31 LTP |
2024/34 LTP |
|||||||||
|
O&M Expense |
2014/15 |
2015/16 |
2016/17 |
2017/18 |
2018/19 |
2019/20 |
2020/21 |
2021/22 |
2022/23 |
2023/24 |
2024/25 |
2025/26 |
2026/27 |
|
Administration |
1,650 |
2,109 |
1,694 |
1,659 |
1,649 |
1,679 |
1,649 |
1,650 |
1,649 |
1,660 |
2,830 |
2,830 |
|
|
Depreciation |
|
3,996 |
4,010 |
4,021 |
4,032 |
4,041 |
4,050 |
4,082 |
4,137 |
4,169 |
4,187 |
4,187 |
4,187 |
|
Electricity |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
463 |
|
|
Water Treatment |
1,600 |
1,600 |
1,600 |
1,600 |
1,600 |
1,800 |
1,800 |
1,800 |
1,800 |
1,800 |
1,800 |
1,800 |
|
|
WTP Lagoon desludge |
|
|
|
|
|
|
|
|
|
|
100 |
|
|
|
Physical Works – Programmed |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
205 |
|
|
Physical Works – Reactive |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,070 |
2,300 |
2,300 |
|
|
Headworks |
216 |
179 |
179 |
204 |
179 |
179 |
179 |
179 |
204 |
400 |
179 |
179 |
|
|
Roding Dam Gravel |
|
50 |
50 |
5 |
200 |
|
|
|
|
|
|
|
|
|
Fish Passage |
|
20 |
|
|
|
|
|
|
|
|
|
|
|
|
PHRMP |
|
30 |
|
|
|
|
|
|
|
|
|
|
|
|
Network Capacity -Growth |
|
50 |
50 |
|
|
|
|
|
|
|
|
|
|
|
Back Flow mtce |
|
20 |
30 |
40 |
50 |
60 |
70 |
80 |
90 |
100 |
110 |
150 |
150 |
|
Pressure/Flow Rate mtce |
|
30 |
36 |
36 |
36 |
36 |
36 |
36 |
36 |
36 |
36 |
50 |
50 |
|
Prelim CAPEX reviews |
|
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
|
|
|
Natural Hazards Assessment |
|
50 |
50 |
|
|
|
|
|
|
|
|
|
|
|
Water Loss Reduction Strategy |
|
30 |
30 |
30 |
60 |
60 |
60 |
45 |
15 |
15 |
15 |
|
|
|
Total (a) ($,000s) |
|
10,490 |
10,892 |
10,353 |
10,589 |
10,373 |
10,622 |
10,619 |
10,655 |
10,721 |
11,056 |
12,164 |
12,164 |
Notes:
(a) Projections are in
2015 dollars. Figures in the Long Term
Plan are adjusted for inflation
1.34.1 Background on Renewals
i) Definition
Renewal expenditure is
major work which does not increase the asset’s design capacity but restores,
rehabilitates, replaces or renews an existing asset to its original capacity.
Work displaying one or
more of the following attributes, can be classified as rehabilitation or
renewal expenditure:
· Works
which do not increase the capacity of the asset, i.e. works which upgrade and
enhance the assets restoring them to their original size, condition, capacity,
etc;
· The
replacement component of augmentation works which increase the capacity of the
asset, i.e. that portion of the work which restores the assets to their
original size, condition, capacity etc;
· Reconstruction
or rehabilitation works involving improvements, realignment and regrading;
· Renewal
and/or renovation of existing assets, i.e. restoring the assets to a new or
fresh condition.
Work over and above
restoring an asset to original capacity is capital expenditure. However if the additional cost is within 10%
of the renewal cost then the total cost will be treated as renewal expenditure.
ii) Renewal
Decisions
Assets can fail from
various modes other than the normally recognised physical, failure or breakage.
The range of failure
modes includes:
· Structural: where the physical condition of the asset is
the measure of deterioration, service potential and remaining life, for example
a steel watermain may suffer from corrosion.
· Capacity/utilisation: where it is necessary to understand the level
of under or over-capacity against the required level of service to establish
remaining life or timing for renewal, for example a watermain may be too small
to carry the required flow.
· Level
of service failures: e.g. reliability,
image, where performance targets are not achieved, for example iron tubercles
in a cast iron main may lead to complaints of orange specks in the water.
· Obsolescence: technical change or lack of replacement parts
can render assets uneconomic to operate or maintain, for example electronic
equipment may no longer be serviceable as components may no longer be available.
· Cost
or economic impact: where the cost to
maintain and operate an asset is likely to exceed the economic return expected,
or the customer’s willingness to pay to retain an asset.
Each of these modes
has distinct attributes that require evaluation to allow an understanding of
the effect on the assets. Assessment of
the performance related to the type of failure is important.
Condition assessment
is a typical failure mode assessment activity.
To evaluate cost and
obsolescence as failure modes it is necessary to capture the asset’s operating
and maintenance cost information, and to compare this with the lifecycle cost
expectations.
Renewals of assets
will be assessed and reviewed annually when this can be achieved through the
following processes or decision making steps:
· What
is the cost of rehabilitation versus replacement?
· What
are the possible increases in effective life following the different treatment
options?
· What
is the probability and consequences of failure if rehabilitation / renewal do
not take place?
· What
are the customer benefits that are derived from the different levels of service
that each option offers?
· What
are the funding requirements and options?
· What
are the future annual and periodic maintenance and operating costs following
rehabilitation or replacement?
· What
is the justification for any premium being paid for increased level of service?
As condition
assessment and maintenance histories are built up, these will be used in
determining renewal priorities.
iii) Renewal
Standards
The work performed and
materials to be used shall comply with the Nelson City Council Land Development
Manual (and subsequent amendments) and all relevant New Zealand Standards
(complete with amendments).
1.34.2 Assumptions
It is
assumed that renewals will be continued as necessary whilst still at a rate
that is attainable both from resource and financial aspects.
1.34.3 Level of Service Implications
It is
necessary to renew pipes and equipment before they impact on levels of
service. For example renewal or relining
of cast iron pipe to improve water quality, renewal of softening asbestos
cement pipe to maintain reliability.
1.34.4 Demand Implications
Renewals
will be sized to allow for future demand.
Where the increase is greater than 10% then the difference will be
funded from capital (for example, ridermains being laid in conjunction with
cast iron and asbestos cement renewals).
1.34.5 Risk Implications
There
is a risk to water quality, financial income, and consumer parity by not
undertaking renewals of pipes, meters and dual check valves.
1.34.6 Lifecycle Implications
Pipes
and equipment must be renewed before maintenance costs become excessive. Decisions made at the time of renewal have
impact on the whole lifecycle costs of the asset.
1.34.7 Renewal Plan
· Relining
of selected 100mm diameter and larger cast iron pipes will be considered in the
future
· Asbestos
Cement Pipe - 50mm diameter Fibrolite pipes and 100mm diameter “Black Asbestos”
pipes which are identified as being near the end of their economic life are
scheduled for renewal from 2007/08 to 2020/21
· Steel
Pipe - Steel pipes tend to corrode randomly.
Individual sections of steel pipe which fail will be replaced as
maintenance expenditure
· Water
Treatment Plant Filters – Installation of the fifth train is proposed to begin
2014/15 in order to provide greater flexibility with the filter renewal
programme and possibly extend the life of the existing filters. Renewal of the
existing filters is shown in the renewal projections for 2017/18. As the Water
Treatment Plant has been in operation for ten years and the filters are
guaranteed for 10 years advice from the manufacturer will guide the replacement
timetable.
· Water
Meters - Residential water meters were installed in 1999, and have a life of 12-15
years. It is cheaper to replace these
sizes rather than test and refurbish them.
These are expected to be replaced under renewal budgets over 3 years
from 2017/18. As part of the renewal
process consideration will be given to the installation of “smart meters” that
allow 24 hour real time monitoring of water use. This type of information would be valuable in
the leak detection programme.
· Residential
Backflow Prevention – The dual check valves in the water meter manifold are
spring operated and lose effectiveness with time. An increasing number of the valves are also
disintegrating in the manifolds and a programme to replace these will commence
in 2015/16. As the dual check valve is fitted immediately underneath the meter
it was initially considered to be appropriate for them to be replaced at the
same time as the meter. The number of failures and risk of pieces of the valves
impacting the water meters and household water fittings has lead to the need to
begin the replacement in advance of the meters.
Water
Meters – Commercial and Industrial water meters were installed from 1980 to
1999. Larger sizes can be refurbished
but spare parts for early models are not now available. Renewal of commercial and industrial water
meters is scheduled over a 9 year period from 2014/15 at $300,000 per year.
Water
Supply Renewal Projections are shown in Table 6.4.
1.34.8 Sensitivity on Renewal Plan
The
Renewal Plan assumes that pipework and other water assets will be renewed using
optimised decision making and condition/failing modelling. As these techniques are still being developed
for the water assets, a fixed but realistic sum each year is shown in the
Renewal Plan.
Table 6.4 Water Supply Renewals
Projections
|
Year |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
|
|
Long Term Plan |
2015/25 LTP |
2018/28 LTP |
2021/31 LTP |
2024/34 LTP |
|||||||||
|
Renewals Project Area |
2014/15 |
2015/16 |
2016/17 |
2017/18 |
2018/19 |
2019/20 |
2020/21 |
2021/22 |
2022/23 |
2023/24 |
2024/25 |
2025/26 |
2026/27 |
|
Pipeline |
838 |
544 |
794 |
794 |
850 |
850 |
850 |
900 |
900 |
900 |
950 |
950 |
950 |
|
Waimea Road Renewal (Little
Go Stream) |
|
500 |
|
|
|
|
|
|
|
|
|
|
|
|
Pump Stations - Renewals |
|
0 |
270 |
70 |
3 |
20 |
0 |
13 |
136 |
495 |
497 |
0 |
3 |
|
Headworks - renewals |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
|
Reservoir Refurbishment
Programme |
|
|
|
|
50 |
50 |
50 |
50 |
50 |
|
|
|
|
|
Residential Meters |
50 |
100 |
100 |
500 |
1,000 |
1,000 |
500 |
|
|
|
|
|
|
|
Commercial Meters |
301 |
185 |
150 |
150 |
300 |
300 |
300 |
300 |
300 |
300 |
|
|
|
|
Backflow Prevention Renewals |
|
|
|
|
|
|
|
|
|
|
|
350 |
350 |
|
Water Treatment Plant
MembraneRenewals |
0 |
0 |
0 |
1,000 |
1,000 |
1,000 |
1,000 |
0 |
0 |
0 |
0 |
1,000 |
1,000 |
|
Water Treatment Plant
Renewals |
|
246 |
140 |
206 |
185 |
269 |
169 |
287 |
|
|
|
|
|
|
Maitai Resource Consent
Renewal |
80 |
200 |
200 |
200 |
|
|
|
|
|
|
|
|
|
|
Roding Resource Consent
Renewal |
80 |
200 |
200 |
200 |
|
|
|
|
|
|
|
|
|
|
Roding Pipeline |
|
100 |
0 |
0 |
0 |
0 |
100 |
100 |
1,000 |
1,500 |
1,500 |
|
|
|
Scada |
|
60 |
70 |
|
|
|
|
|
|
|
|
|
|
|
Total (a) ($,000s) |
1,249 |
2,195 |
1,984 |
3,180 |
3,448 |
3,549 |
3,029 |
1,710 |
2,446 |
3,255 |
3,007 |
2,360 |
2,363 |
Note: Projections are in 2015 dollars. Figures in the Long Term Plan are adjusted for inflation
1.35.1 Background on Capital
New
works are those works that create a new asset that did not previously exist or
works which upgrade or improve an existing capacity. They may result from growth, social or
environmental needs.
Capital
expenditure projects display one or more of the following characteristics:
· Construction
works which create a new asset that did not previously exist in any shape or
form;
· Expenditure
which purchases or creates a new asset (not a replacement) or in any way
improves an asset beyond its original design capacity;
· Upgrading
works which increase the capacity of the asset;
· Construction
works designed to produce an improvement in the standard and operation of the
asset beyond its present capacity.
Capital
Work Standards
The
work performed and materials to be used shall comply with the Nelson City
Council Land Development Manual (and subsequent amendments) and all relevant
New Zealand Standards, (complete with amendments).
Table
6.5 shows the Capital Work program and projections.
1.35.2 Assumptions on Capital
The
major items of capital expenditure are the duplication of the Maitai Pipeline construction
of a second storage reservoir for the Atawhai area, a fifth filtration train
and new filters at the treatment plant and installation of backflow prevention
devices as noted in 6.5.7 below.
1.35.3 Level of Service Implication on Capital
The capital
works for system improvements and ridermains are to address problems with
pressure, flow, and continuity of supply to the levels of service required.
1.35.4 Demand Implications on Capital
The
capital works proposed will address the need for more storage and trunk mains
to meet growth requirements. Failure to
meet growth requirements will then impact on Levels of Service.
1.35.5 Risk Implications on Capital
The
capital works proposed address the need for decreasing the risk on the Maitai
Pipeline and preventing backflow from commercial and industrial promises.
1.35.6 Lifecycle Implications on Capital
Decisions
made to construct a capital project will have implications for the life of the
asset, as will subsequent design decisions.
Optimised decision making will therefore be used to identify and
prioritise all potential solutions for water supply projects over $0.5million
value.
1.35.7 Capital Financial Plan
i) Maitai
Pipeline (Water Treatment Plant – Westbrook Terrace Valve Chamber)
The section of the
existing Maitai pipeline below the Treatment Plant is of less risk from
geotechnical and pipeline condition hazards.
However it was damaged by falling trees in the storm of 30 July 2008. A replacement pipe would be laid down the
Treatment Plant access road, down Brook Street and Westbrook Terrace to the
existing valve chamber at the corner of Westbrook Terrace and Silverbirch Grove
where it would connect to the existing trunk main system. This work is scheduled for completion in 2016/17.
ii) System
Improvements
Minor works to achieve
and maintain the levels of service.
Minor issues are identified through modelling, service technician
comments and staff knowledge each year.
Initially it is proposed to concentrate on water loss correction work to
reduce the losses.
iii) Atawhai
Hills Reservoir and Pump Station
To improve supply
capacity and facilitate green field development to the upper levels of the
Atawhai foothills, one option considered was a pump station alongside the Walters
Bluff reservoir, pumping up to a small storage reservoir (300-500m3)
on the ridgeline above. In this plan a
detailed options report will be developed from 2015- 2016/17 to identify
preferred location(s) for the Atawhai No 2 reservoir and upper level
reticulation options.
iv) Atawhai
No. 2 Reservoir
Modelling work by Opus
International Consultants Ltd for the Walters Bluff Reservoir in 2000
identified that a second reservoir between Walters Bluff and Dodson Valley
would be required in the future as a result of growth. Final timeframes will be established by
either demand through developer interest and subdivision consent applications
or the need to establish a water source for emergencies. Currently the reservoir
is shown in the CAPEX tables for 2020-2024.
v) Atawhai
Trunk Main
An additional trunk
main will be required to link the Atawhai No. 2 Reservoir to the existing trunk
main system. This is proposed for
2021/22.
vi) Ridermains
The renewal budgets
allow for the replacement of 50mm and 100mm asbestos cement watermains. However, the Land Development Manual requires
a watermain on one side of the street and a ridermain on the other. To
accommodate this a separate budget is identified for new ridermain installations.
vii) System
Improvements/ Miscellaneous Pipe and Fittings
There is an ongoing
need for small improvements to the water network to address localised issues
that arise with flow, pressure, taste and turbidity. A budget for these is
included in the CAPEX tables. Larger issues are addressed as specific CAPEX
projects.
viii) Lee
Valley Dam
Nelson City Council is
currently a stakeholder in the investigations for the dam in the Lee Valley
proposed by the Waimea Water Augmentation Committee. To secure a share in the dam (for water
required at the turn of the century) a yet to be determined payment of $4.4 million (10% of the expected construction cost of
$44M) would have to be made at the time of construction.
As discussed above in
section 3 other options are expected to provide sufficient water for the city
and a share in the Lee Valley Dam is not required for the water supply
activity. No funding is therefore shown
in the Capital Works Projections.
ix) Backflow
Prevention.
Backflow prevention is
one of the factors considered in the Ministry of Health water gradings. The water supply does not currently meet
Ministry of Health requirements as not all premises have backflow
prevention. Backflow is identified as
the second highest risk to the water supply (refer section 4.4.6).
Reduced pressure
backflow preventors have been installed on all connections to sewage treatment
plants and pump stations and new connections to Reserve facilities.
The meter manifolds
installed on domestic and some commercial connections (refer Section 5.2.7)
incorporate a spring loaded dual check valve.
While not providing an absolute guarantee, these valves significantly
reduce the possibility of accidental contamination of the water supply from a
residential property, which is also considered to be a low level risk of
contamination source.
A survey has begun of
all commercial and industrial premises to determine the exact backflow
prevention needs, so that a programme for installation of backflow preventors
can be established. Installation of
backflow preventors has been established as an important means of protecting
the network from contamination.
The sum of $3.8
million over 11 years ($350,000 per year) has been shown in the Capital Works
Projections from 2014/15 for the fitting of backflow preventors to Commercial
and Industrial premises in conjunction with meter renewals.
x) Fire
Flows
Budget allowance of
$600,000 per year for
seven years from 2014/15-2018/19 has been made for works required to improve the fire
flow issues in the city. These issues have largely been created by the change
in the requirement for fire flows to be available within specified “as measured
along the road” distances from fire hydrants, rather than as a straight line
measure direct from the hydrant.
Table 6.5 Water Supply Capital Expenditure
Projections Note: Projections are in 2015 dollars. Figures in the Long Term Plan are adjusted
for inflation
|
Year |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
|
|
Long Term Plan |
2015/25 LTP |
2018/28 LTP |
2021/31 LTP |
2024/34 LTP |
|||||||||
|
Capital Projects |
2014/15 |
2015/16 |
2016/17 |
2017/18 |
2018/19 |
2019/20 |
2020/21 |
2021/22 |
2022/23 |
2023/24 |
2024/25 |
2025/26 |
2026/27 |
|
Malvern Hills - Atawhai Pump
& Ridge Resvr |
21 |
18 |
|
|
|
|
|
150 |
|
|
|
|
|
|
Atawhai #2 Reservoir |
|
87 |
100 |
285 |
|
|
|
1,000 |
2,500 |
|
|
|
|
|
Atawhai Trunk Main |
|
|
|
|
50 |
95 |
|
3,300 |
|
|
|
|
|
|
Backflow Prevention |
375 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
150 |
200 |
200 |
|
Maitai Pipeline (Dam-WTP) |
|
2 |
|
|
|
|
|
|
|
|
|
|
|
|
Maitai Pipeline (WTP-Westbk
Tce) |
100 |
2,118 |
2,000 |
|
|
|
|
|
|
|
|
|
|
|
Maitai Planting |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
|
Telemetry / control upgrades |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pressure Enhancement |
|
|
|
|
|
150 |
100 |
|
|
|
|
100 |
|
|
NCC - TDC Link |
|
|
|
|
|
|
|
|
|
|
|
100 |
100 |
|
DMA establishment |
|
50 |
100 |
100 |
|
|
|
|
|
|
|
|
|
|
Water Loss Reduction
Programme |
|
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
|
|
|
Hira extension |
|
|
|
|
|
|
|
|
|
|
|
150 |
1,000 |
|
Future Growth Additional
Storage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Seismic Risk Upgrades |
|
100 |
100 |
100 |
|
|
|
|
|
|
|
|
|
|
Water Treatment Plant
Membranes |
1,200 |
1,066 |
|
|
|
|
|
|
|
|
|
|
|
|
Natural Hazards Risk
Assessment |
|
|
|
|
100 |
100 |
100 |
|
|
|
|
|
|
|
Network Capacity Confirmation
for Growth Areas |
|
|
|
|
|
100 |
100 |
100 |
|
|
|
1,250 |
|
|
Network
Upgrades Nelson North |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Network
Upgrades Nelson Central |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Network
Upgrades Nelson South |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fire Flow Upgrades |
100 |
100 |
100 |
200 |
200 |
|
|
|
|
|
|
|
|
|
Pipe Improvements/Pressure
Reduction |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
50 |
|
Ridermains |
155 |
75 |
75 |
75 |
155 |
155 |
155 |
55 |
55 |
55 |
55 |
55 |
55 |
|
System Improvements &
Misc Pipes & Fittings |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
50 |
50 |
50 |
50 |
50 |
50 |
|
Water Treatment Plant Upgrades |
|
|
|
|
|
|
|
|
|
150 |
500 |
500 |
500 |
|
Dam Upgrades |
|
0 |
0 |
0 |
0 |
0 |
0 |
100 |
100 |
100 |
100 |
0 |
100 |
|
Total (a) ($,000s) |
2,231 |
4,086 |
2,945 |
1,230 |
975 |
1070 |
925 |
5,165 |
3,115 |
765 |
1,115 |
2,465 |
2,065 |
1.35.8 Sensitivity
on Capital Plan
Most
of the Capital projects are growth related, therefore if growth is slower (or
faster) than predicted then projects may need to be put back (or brought
forward).
1.36 Asset Disposal Plan
Water
mains are generally relaid off line. If
pipes are left in the ground they are usually sealed at the connections and
retained as a possible duct for cables.
Mechanical
equipment that has been replaced is cannibalised for parts or sold as scrap
metal unless it is considered to have genuine resale value. In this case, the piece of surplus equipment
will be sold with income directed to the water supply account.
1.37 Long Term plan
The
Council adopted a 10 year Long Term Plan in 2012 which outlined the major activities
and projects the Council expected to be involved in during the next 10 years,
and the resources needed for these.
These have been reviewed, as above, and this Plan proposes changes which
will be carried into the Long Term Plan 2015-25.
1.38 Funding
1.38.1 Contributions
The
Resource Management Plan has set a financial contribution so that subdividers,
developers and new industry pay their share of the capital expenditure for
reserves purposes each year as part of the costs of growth.
From
1 July 2006 Development Contributions have been collected under the Local
Government Act 2002 as detailed in the Long Term Plan.
The
remaining costs of collecting, treating and delivering water are funded from
user charges.
1.38.2 Water by Meter User Charges
From
1 July 1999 universal metering has been in operation and there is no charge in
the general rates for the supply of water.
The
Water Pricing Structure Working Party was convened in 2003 and made its
recommendation to the Infrastructure Committee which in turn recommended the
pricing structure to the full Council meeting on 18 December 2003.
The
objective of the pricing structure is to:
· Encourage
water conservation
· Be
fair to residential and commercial water users
· Be
simple to administer and readily understood by the public
· Recognise
the opportunity value and fire fighting value of the water supply system and
the benefits this provides to empty sections and houses
· Provide
regular cash flow while avoiding excessive reading and invoicing costs
The
key points in the pricing structure are:
· A
house or section without a water connection not be charged a fee
· All
properties on water by meter (including empty sections) should pay a minimum
annual charge.
· The
fixed costs are approximately 90% and variable costs approximately 10% of the
total costs of operating the water supply.
If the minimum annual charge was set to recover 90% of costs there would
be little incentive to conserve water.
Therefore the minimum annual charge was set to recover only 30% of the
total costs. This encourages water
conservation, but still means that low (or no) volume users do pay a share of
the opportunity and fire fighting value of the supply.
· There
being no “entitlement to free water for low usage” associated with the minimum
annual charge.
· The
minimum annual charge (collected as a daily charge) be set to recover 30% of
the estimated water by meter revenue requirement, and that the remaining 70% be
recovered as user charges
· The
revenue required from Major Water Users with Even Demand (including financial
and operating costs) be calculated based on the value of water supply assets
used by those users and allocated as a percentage of peak summer demand for
assets sized for peak demand (part of the treatment plant), and as a percentage
of water used for assets sized for water volume
· The
charges for Bulk Water Users over 10,000m3 per year, where there is
predominantly summer irrigation, be at the average of the 0-10,000m3 and the
10,000-100,000m3 rates. This
recognises that these Users contribute to the summer peak, but do not use a
large part of the reticulation
· The
charges for usage in the 10,000-100,000m3 band and 100,000+m3
band be set to recover the revenue calculated above and in the same ratios as
used in previous years.
· A
revenue issue may arise in the future, if the water reuse project involving
treated water from Bells Island is developed. This project would supply
irrigation water to the Tahunanui / Stoke area and impact on water sales
currently made for this purpose.
1.39 Asset Management
Council
adopted an Asset / Activity Management Plan Policy in 2010. This policy
confirms that the Water Asset Management Plan should be developed to a “Core
Plus “ level as best reflects the needs for a city of Nelson’s size.
A gap
analysis between “Core” and “Advanced” Asset Management has been undertaken for
each asset group. The analysis is shown
in Appendix D.
1.40 Information Systems
All
asset information is stored on Arcinfo, a computer based Geographical
Information System and Hansen Asset Management System. The accounting system used is integrated
computer software supplied by Napier Computer Systems. The various systems are linked.
1.41 Accounting/Financial
Systems
1.41.1 Background
Accounting
is carried out to International Financial Reporting Standards (IFRS) to comply
with the Local Government Act. The Nelson City Council uses integrated computer
software supplied by Napier Computer Systems.
The
General Ledger is linked to packages that run Debtors, Creditors, Banking,
Rates, Fixed Assets, Invoicing, Water Billing, Job Costing, and Payroll.
Internal
monthly financial reports are generated by activity and sub-activity.
External
financial reports by significant activity are published in the annual
report. Monthly summaries are presented
to the Finance Committee of Council.
1.41.2 Definition of Expenditure Categories
Expenditure
can be divided into two broad categories;
i) Ongoing
day to day operations and maintenance works;
ii) Programmed
works that upgrade or renew the asset to provide the required level of service.
All
expenditure on infrastructure assets will therefore fall into one of three
categories:
iii) Maintenance
Expenditure
iv) Capital
Expenditure – renewals/replacements
v) Capital
Expenditure – creation/enhancement
1.41.3 Maintenance Expenditure
Maintenance
may be planned or unplanned, and is the regular ongoing day to day work
necessary to keep assets operating, including instances where portions of the
asset fail and need immediate repair to make the asset operational again. This includes:
· Regular
and ongoing annual expenditure necessary to operate and keep the assets at
their required service potential;
· Day to
day and/or general upkeep works designed to keep the assets operating at
required levels of service;
· Works
which provide for the normal care and attention of the asset including
programmed repairs and minor replacements;
· Unplanned
(reactive) maintenance i.e. isolated failures requiring immediate repair to
make the asset operational again.
1.41.4 Capital Renewal/Replacement Expenditure
Renewal
expenditure is major work which does not increase the asset’s design capacity
but restores, rehabilitates, replaces or renews an existing asset to its
original capacity. This includes:
· Works
which do not increase the capacity of the asset, but restores them to their
original size, condition capacity, etc.
· The
replacement component of augmentation works which restores the assets to their
original size, condition, capacity, etc.
· Reconstruction
or rehabilitation works involving improvements, realignment and regrading;
· Renewal
and/or renovation of existing assets, restoring the assets to a new or fresh
condition consistent with the original asset.
1.41.5 Capital Creation/Enhancement Expenditure
Capital
works create a new asset that did not previously exist, or upgrade or improve
an existing capacity. They may result
from growth, social or environmental needs.
This includes:
· Construction
works which create a new asset that did not previously exist in any shape or
form;
· Expenditure
which purchases or creates a new asset (not a replacement) or in any way
improves an asset beyond its original design capacity;
· Upgrading
works which increase the capacity of the asset;
· Construction
works designed to produce an improvement in the standard and operation of the
asset beyond its present capacity.
1.41.6 Depreciation and Loss of Service
Potential
· Depreciation
and Loss of Service are calculated in Hansen.
1.42 Geographical
Information System
1.42.1 Background
When
the decision was made to implement the Geographical Information System in 1993
it was recognised that the existing asset information was not of a suitable
standard to be entered directly into the system. A contract was let for the capture and
delivery of data in digital format suitable for entry into the Geographical
Information System system.
The
data capture included contours, building outlines, road markings, kerb and
channel, manholes, sumps, valves, hydrants etc.
To ensure that underground services were captured as accurately as
possible, students were employed to identify and mark every surface access
point (e.g. manholes, valves).
The data
was captured, using photogrammetry, from March 1994 and progressively delivered
over the following three years. Nelson
City Council staff carried out accuracy checks on the co-ordinate data
supplied, searched all the engineering plans and field books for information on
pipe alignment, material and age and entered this information into the
Geographical Information System.
1.42.2 Accuracy Limitations
There
is a high degree of confidence in the accuracy of the data.
· Spatial
Data
Data captured
by photogrammetry is required to be accurate to within a tolerance of ± 0.3m. In streets where surface
openings could not be seen from the air (e.g. under verandas or trees) the
points were picked up by the contractor’s field survey team. In other less
accessible areas, it was not considered economic to search for buried
fittings. Instead the best estimated
position was entered and the accuracy limitation flagged.
· New
assets are recorded from the surveyed coordinates and levels shown on the “as
built” plans supplied by the subdivider (for vested assts) or Council’s project
section (for new capital work).
· Pipe
Size, Material, and Age Data
There
is high confidence in the accuracy of pipe age, material and size data in
Hansen.
Before
historic data was entered into the Geographical Information System system
considerable research through existing “as built” and “field book” records was
carried out.
For
early pipes where an exact date of construction was not known, the best
estimate was used based on the type of pipe, the age of surrounding pipes and
the period the area was developed.
Cross
reference was also made to Council’s schematic water supply operational plans -
“the water plans”. These plans have existed in transparency and latterly in
electronic format for over 40 years and are used daily by the maintenance
contractor. Whenever the contractor excavates onto a pipe and discovers an
error in size or material in the plans, this is reported and the master plan
updated.
· New
assets are recorded from the “as built” plans supplied by the subdivider (for
vested assets) or Council’s engineering project section (for new capital work).
· Toby
Location
· As
outlined in Section 5.2.7, each property has been provided with a meter
manifold in a plastic meter box. This
manifold also serves as the toby for the property.
· As
part of the project, a description of the meter box location has been entered
into the Napier Computer Systems Water Billing System. The location of each meter box and toby is
recorded by dimensions from boundaries.
· The
meter box location is only recorded on Geographical Information System for new
subdivisions.
1.42.3 Maintenance of Geographical Information
System Data
New
data is updated into the Geographical Information System system on a monthly
basis.
1.43 Information Flow
Requirements and Processes
1.43.1 Existing Information Flow and Business
Processes
In
June 2000, Opus International Consultants Ltd completed a report entitled “The
Development of Business Process Mapping for Asset Management Systems”
preparatory to Nelson City Council purchasing and implementing a computer based
Asset Management System.
The
report details the existing business processes used by the Nelson City Council
in its Asset Management planning.
The report
identified a preferred process for the management of Council assets and
identified gaps in the current process for each asset group and recommended
actions required to correct the gaps and implement the transition to the
preferred management process.
The
report concluded that the majority of data required for Asset Management is
already collected and stored. However
the data is stored in a myriad of systems and files and is therefore not
extensively used to support the Asset Management planning decision making
processes.
1.44 Asset Management
System
1.44.1 Background
In
2000 the Hansen Asset Management System was selected as best suited to meet the
future Asset Management planning requirements of Council. In 2014 a decision
was made to continue with the Hansen Asset Management System version 8 (INFOR).
1.44.2 Implementation
The
water asset group was chosen to pilot the implementation of the new system.
The
data collection and management for water was improved as noted above, and once
the new procedure was approved, was developed over other asset groups within
the Nelson City Council.
1.44.3 Accuracy Limitations
Pipe
data in Hansen is populated from the Geographical Information System system and
the comments above regarding accuracy limitations applies also.
Non
pipe data is entered into Hansen manually from “as-built” drawings therefore is
considered to be accurate.
1.45 Network Model
1.45.1 Background
In
2001 the Infoworks water network modelling package was purchased and installed.
The Network Model is used to calculate fire hydrant flows, verify design pipe
sizes for new works and check the capacity of the system to cope with future
development.
1.45.2 Accuracy Limitations
In
2002 extensive monitoring of flow and pressure was carried out to enable the
model to be more accurately calibrated.
Further extensive flow and pressure monitoring was carried out in
February 2006 and was used to further refine the model. Model calibration is
carried out regularly with re-calibration undertaken in 2014/15.
Infoworks
is populated from the Geographical Information System system and the comments
above regarding accuracy limitations apply also.
1.46 Condition Model
Condition
models will be developed for the various Water Supply Assets. This has commenced with condition models for
steel and cast iron pipe. The utility
services maintenance contractor is collecting ratings on corrosion, pitting,
coating and tuberculation when pipe is exposed for maintenance. These ratings are combined within the Hansen
system to give an overall pipe condition.
When sufficient data has been collected the condition and hence expected
useful life left, of lengths of pipe of similar age and laid under similar
conditions will be able to be predicted.
The
system needs to be extended to Asbestos Cement pipe condition prediction using
data collected by the Utility Services Maintenance contractor and information
from the “New Zealand Asbestos Cement Watermain Manual” produced by the New
Zealand Water and Waste Association.
1.47 SCADA Telemetry
Council
has a “Kingfisher” SCADA (Supervisory Control and Data Acquisition) system and
an “Intouch” system at the base station. The system is used to monitor and
control critical aspects of the network such as the dams, treatment plant,
reservoirs, pumps and control valves.
The
need for constant monitoring of the water network by the SCADA system has grown
to the point that without it, maintaining the current Levels of Service would
be difficult. SCADA has given Council the ability to ascertain faults and instigate
remedial actions by remote control without affecting the service to consumers.
PLAN IMPROVEMENT AND MONITORING
1.48 Previous Action
Plans
The
2001, 2004, 2006, 2009 and 2012 Water Supply Asset Management Plans contained action
plans for Monitoring and Improvement.
Table 8.1 Reviews these plans and reports on progress.
Table 8.1 Previous Action Plans Report Needs to
be updated.
|
·
Action |
·
WAMP Ref |
·
Year Due |
·
Completed Y/N |
·
Comments |
|
·
Health and Safety Practices
Internal Audit |
·
8.3.6 |
·
Six monthly |
·
Yes |
·
Done every six months |
|
·
Maintain Backflow Register |
·
2.2.4 |
·
Annually |
·
Yes |
·
|
|
·
Compare average peak two
day demand with projected demand |
·
2.3.4 |
·
Annually |
·
Yes |
·
|
|
·
Target pressure correction
work |
·
2.4.4 |
·
Annually |
·
Yes |
·
|
|
·
Target flow correction
work |
·
2.5.6 |
·
Annually |
·
Yes |
·
|
|
·
Review risk analysis |
·
4.7 |
·
Annually |
·
Yes |
·
|
|
·
Review and update costs by
30 August each year |
·
8.4.5 |
·
Annually |
·
Yes |
·
|
|
·
Maitai Dam Annual
Engineering Inspection |
·
5.2.3 |
·
Annually |
·
Yes |
·
|
|
·
Revise water supply demand
growth |
·
3.7 |
·
2006 |
·
Yes |
·
This document updates peak
annual use compared to supply capacity. |
|
·
Establish a backflow prevention
policy |
·
2.2.4 |
·
2006 |
·
No |
·
Policy now superseded by
programme. Council approved funding 2013/14. |
|
·
Develop Contamination
Response Plan |
·
4.4.6 |
·
2006 |
·
No |
·
Deferred pending
completion of PHRMP. |
|
·
Establish Condition Model for
asbestos cement pipe |
·
7.8 |
·
2006 |
·
No |
·
Longer term project
resource dependent. |
|
·
Achieve “Ab” water grading
from Ministry of Health |
·
2.2 |
·
2007 |
·
Yes |
·
Achieved May 2011. |
|
·
Investigate options for
mitigating risk to Maitai pipeline |
·
4.4.1 and 5.2.2 |
·
2007 |
·
Yes |
·
Council decision to
duplicate pipeline made in 2007. |
|
·
Fit seismic shutoffs to
major water reservoirs |
·
4.3.2 |
·
2008 |
·
Yes |
·
Completed October 2007 |
|
·
Commence duplication of
Maitai pipeline |
·
4.3.2 |
·
Dam to WTP ·
2011/14 |
·
Yes |
·
Construction due to
complete 2013/14. |
|
·
Maitai Dam comprehensive
Safety Review |
·
4.2.3 |
·
2014 |
·
No |
·
Due 2014 |
|
·
Revise Asset Management
Plan |
·
8.4.4 |
·
2014 |
·
Yes |
·
This document |
|
·
Routinely calibrate the
accuracy of the Network Analysis |
·
2.4.4 |
·
2014/15 |
·
No |
·
Due 2014/15 |
|
·
Pump Stations 5 year
engineering inspections |
·
5.2.5 |
·
2009/14 |
·
No |
·
Carried out on a rolling
basis as resources allow |
|
·
Reservoirs 5 year engineering
inspections |
·
5.2.4 ·
|
·
2009/14 |
·
No |
·
Carried out on a rolling
basis. Panorama Drive done 2009,
Observatory Hill done 2010. |
|
·
Have backflow preventors
on all commercial /residential premises |
·
4.3.2 |
·
2024 |
·
No |
·
Not due |
|
·
Replace double check
valves on residential properties |
·
4.3.2 |
·
2015 |
·
No |
·
Not due |
1.49 Performance
Monitoring and Management
The
effectiveness of the Water Asset Management Plan will be monitored in various
ways and the results used in the updating and revision of the Plan as described
in Section 8.4.
1.49.1 Current Level of Service Objectives
This
Water Asset Management Plan contains levels of service in Section 2.0. Compliance with the current level of service objectives
will be monitored by internal audit.
1.49.2 Capital and Renewal Works Programme
The
carrying out of the annual capital and renewal works programme will be
monitored to ensure that the works are completed on time and within budget.
1.49.3 Maintenance Works Programme
The
carrying out of the maintenance works will be monitored to ensure that the
works are carried out within the required response times, to the required
standard, and at the least cost.
1.50 Improvement
Programme
1.50.1 Improving Accuracy and Confidence in
Asset Management Plan
Asset
management improvements and associated objectives are noted throughout the
Asset Management Plan.
These
improvements will improve the accuracy of, and confidence in, the Water Asset
Management Plan. These improvements are
shown in Table 8.2.
A
risk assessment is an essential element of any Asset Management Plan. This involves identification of critical
assets, risk analysis and development of risk reduction and contingency
planning to suit the business situation.
1.50.2 Core to Advanced Gap Analysis
Asset
Management Planning is a constantly evolving process, with underpinning Asset
Management systems constantly providing better information. Previous Water Supply Asset Management Plans
were adopted by Council in 1999, 2001, 2006, 2009 and 2012. These reviews have each created an updated
plan and have been timed to link with Council’s strategic planning cycle, i.e.
the Community Plan and Long Term Plan.
The
Infrastructural Assets Business Unit held an in-house Asset Management workshop
in January 2006 in preparation for the 2009 rewrite of the Unit’s three year
business plan, the Water Supply Asset Management Plan, and Transportation Asset
Management Plan.
At
that workshop a gap analysis between “Core” and “Advanced” Asset Management was
undertaken for each asset group. The
Water Supply Asset Management Plan was considered to be midway between “core”
and “advanced”. The detailed assessment
is included in Appendix D.
Based
on the definitions in the recently published International Asset Management
Manual 2006 the Water Supply Asset Management Plan 2004 is considered between
core and advanced in that the areas in Table 8.2 are not covered.
In
recent years it has been recognised that a new rating level of “Core Plus” is
the most appropriate rating for cities of Nelson’s size. This rating reflects that parts of the asset
can be managed at a Core level and parts at an Advanced level. The resultant provides an effective asset
management tool without becoming un-necessarily expensive. The development of “core plus” asset
management practices will be reviewed prior to the completion of the 2018-28
Asset Management Plan.
1.51 Monitoring And
Review Procedures
The
plan will be reviewed annually and revised every three years to incorporate,
amongst other things, improved decision making techniques, updated asset
information, and Council policy changes which impact on targeted levels of
service.
The
effectiveness of the Asset Management Plan will be monitored in various ways.
1.51.1 Statutory Audit
The
Local Government Act requires that an annual, financial audit of the operations
of the Council be carried out. Audits
may include all significant activities such as Asset Management planning.
Previous
Water Asset Management Plans were examined by Audit New Zealand in the course
of audits of the Nelson City Council.
1.51.2 Internal Audit
An
internal audit will be taken to assess the effectiveness with which the plan
meets its objectives prior to the development of the 2018-28 Asset Management
Plan.
1.51.3 Benchmarking
Benchmarking
of service quality and cost efficiency against similar organisations will be
carried out at some future date, most likely once an Asset Management System is
operational, and a history has been established.
Local
Government NZ embarked on a benchmarking exercise for Council utilities in
2014. Nelson City Council was a contributor to that exercise.
1.51.4 Review and Updates
The
Water Asset Management Plan programmes and costs will be reviewed and updated
annually by 30 August each year for incorporation into the Annual Plan.
1.52 Explanation
Throughout
this Water Asset Management Plan, Objectives, Targets, Capital Works, Major
maintenance and Plan improvements are referred to. Table 9.1 brings all these items together in
chronological order to show the work required and the targeted time for the
actions for each section of the Water Asset Management Plan.
Table 9.1 Action Plan To be updated
|
|
WAMP Ref |
Year |
|
Water Quality |
·
|
·
|
|
·
Over the next three years
the following are considered important to complete: |
·
|
·
|
|
· Progress Backflow Prevention Programme |
·
|
·
2015/18 |
|
· Renewal of WTP membranes |
·
|
·
2015-2018 |
|
·
Review of FACE,
Microbiological compliance and Chemical compliance with the aim of
identifying ways of reducing demerit points accumulated through the Drinking
Water Grading process. |
·
|
·
2015-18 |
|
·
Develop Contamination
Response Plan. |
·
|
·
2015-18 |
|
·
Pressure |
·
|
·
|
|
·
Routinely calibrate the
accuracy of the Network Analysis model so that reliable predictions are
provided. |
·
2.4.6 |
·
3 year cycle |
|
·
Target pressure correction
work so that areas of the network with most consumers and greatest pressure
problems are corrected first. |
·
|
·
|
|
·
Flow |
·
|
·
|
|
·
Target flow correction
work so that areas with most consumers and greatest flow problems are
corrected first. |
·
2.5.6 |
·
Annually |
|
·
Environmental |
·
|
·
|
|
·
Ongoing monitoring or
Resource Consent conditions. |
·
2.7.4 |
·
Annually |
|
·
Future demand |
·
|
·
|
|
· When future growth projections are available, the water supply demand for
the city will be revised for inclusion in the next Water Supply Asset
Management Plan. |
·
3.7 |
·
Annually |
|
· Continue the water loss identification and reduction programme |
·
|
·
|
|
·
Emergency and Risk
Management |
·
|
·
|
|
·
Refer Table 4.5 for Risk Treatment
Schedule and Plan. Review the lifelines
risk assessment and response |
·
4.6 |
·
Annually 2015-2018 |
|
·
Growth |
·
|
·
|
|
·
When the final results of
the revised Nelson Resource Management Plan are available, the water supply demand
for the City will be revised for inclusion in the next Water Supply Asset
Management Plan. |
·
3.7 |
·
2015-18 |
|
·
|
·
|
·
|
|
·
Risk |
·
|
·
|
|
·
Develop Contamination
Response Plan. |
·
4.4.6 |
·
2006 |
|
·
Condition Model |
·
|
·
|
|
·
Establish Condition Model for
Asbestos Cement Pipe. |
·
7.8 |
·
2015 |
|
·
Water Supply Grading |
·
|
·
|
|
·
Maintain “Ab” water
grading from Ministry of Health. |
·
2.2 |
·
Annually |
|
·
Risk |
·
|
·
|
|
·
Commence duplication of
Maitai Pipeline. |
·
4.3.2 |
·
Construction started
2011/12 |
|
·
Maitai Dam |
·
|
·
|
|
·
Comprehensive safety
Review (Last completed 2014) |
·
4.2.3 |
·
Due 2018 |
|
·
Asset Management Plan |
·
|
·
|
|
·
Revise by 30 November. |
·
8.4.4 |
·
2015 |
|
·
Network Model |
·
|
·
|
|
·
Routinely calibrate the accuracy
of the Network Analysis model so that reliable predictions are provided. |
·
2.4.4 |
·
2016 |
|
·
Pump Stations |
·
|
·
|
|
·
Rolling programme of
inspections and upgrade where required. |
·
5.2.6 |
·
Following programme |
|
·
Reservoirs |
·
|
·
|
|
·
Rolling programme of
inspections and upgrade where required. |
·
5.2.5 |
·
Following programme |
|
·
Risk |
·
|
·
|
|
·
Have backflow preventors
on all commercial premises. |
·
4.4.6 |
·
Completion deferred in
this document until 2024 |
|
·
Risk |
·
|
·
|
|
·
Replace double check
valves on residential properties (in conjunction with water meter renewals). |
·
4.4.6 |
underway |
1.53 Annual Performance
Monitoring
Throughout
this Water Supply Asset Management Plan annual performance and monitoring
measures are noted. Table 9.2 brings all
these items together.
Table 9.2 Annual Performance Monitoring and
Reporting
|
|
WAMP Reference |
|
·
Water Quality (i) Measure quality in accordance with the current
Drinking Water Standards for New Zealand as set out in the Health Act 1956. (ii) Record compliance with Ministry of
Health grading. (iii) Record compliance with backflow
prevention requirements. |
·
2.2.4 |
|
·
Reliability (i) Record daily headworks supply and
treatment plant supply. (ii) Record the actual time the water supply
is interrupted and restored, and number of properties affected. (iii) Record all complaints regarding “out of
water”. (iv) Record time and type of notice shutdown
given to consumers. (v) Project peak daily demands for a 30 year
planning period every 5 years. |
·
2.3.4 |
|
·
Pressure ·
Identify the number of
properties with unacceptable: (i) Pressure fluctuations; (ii) Minimum pressure; (iii) Maximum pressure. |
·
2.4.4 |
|
·
Flow (i) Record flows (ii) Determine theoretical flows by use of a
computer model. |
·
2.5.5 |
|
·
Environment Sustainability (i) Record natural river flows, abstraction
flows, mitigation flows, river temperatures, and water quality and biotic
diversity and density. |
·
2.7.3 |
i)
APPENDIX A: GLOSSARY OF TERMS
·
·
GLOSSARY OF TERMS
The following terms
and acronyms (in brackets) are used in this Plan.
|
·
Advanced Asset Management |
·
Asset management which
employs predictive modelling, risk management and optimised decision-making
techniques to establish asset lifecycle treatment options and related long term
cash flow predictions. (See Basic Asset Management). |
|
·
Annual Plan |
·
An Annual Plan is
published in years two and three, alternating with the three-yearly Long Term
Plan, that sets out Council’s updated financial situation, intended activities
and work programme for the following three financial years. |
|
·
Asset |
·
A physical component of a
facility which has value, enables services to be provided and has an economic
life of greater than 12 months.
Dynamic assets have some moving parts, while passive assets have none. |
|
·
Asset Management |
·
The combination of
management, financial, economic, engineering and other practices applied to
physical assets with the objective of providing the required level of service
in the most cost-effective manner. |
|
·
Asset Management System |
·
An Asset Management system
is a combination of processes, data and software applied to provide the
essential outputs for effective Asset Management planning such as reduced
risk and optimum infrastructure investment. |
|
·
Asset Management Plan |
·
A plan developed for the
management of an infrastructure asset that combines multi-disciplinary
management techniques (including technical and financial) over the lifecycle
of the asset in the most cost effective manner to provide a specified level
of service. A significant component of
the plan is a long-term cash flow projection for the activities. |
|
·
Asset Register |
·
A record of asset
information considered worthy of separate identification including inventory,
historical, financial, condition, construction, technical and financial
information about each. |
|
·
Backflow Prevention Device |
·
A mechanical device
required by the Drinking Water Protection Regulations to prevent water from private
plumbing flowing back into the water supply system and possibly contaminating
the public supply. May be a column
10.7m high, a double check valve system or a reduced pressure principle
device. |
|
·
Benefit-Cost Ratio (B/C) |
·
The sum of the present values
of all benefits (including residual value, if any) over a specified period,
or the lifecycle, of the asset or facility, divided by the sum of the present
value of all costs. |
|
·
Business Plan |
·
A plan produced by an
organisation (or business units within it) which translates the objectives
contained in an Annual Plan into detailed work plans for a particular, or
range of, business activities.
Activities may include marketing, development, operations, management,
personnel, technology and financial planning. |
|
·
Capital Expenditure |
·
Expenditure used to create
new assets or to increase the capacity of existing assets beyond their
original design capacity or service potential. Capital expenditure increases the value of
asset stock. |
|
·
Cash Flow |
·
The stream of costs and/or
benefits over time resulting from a project investment or ownership of an
asset. |
|
·
City Datum |
·
The baseline from which
heights in the City are measured. It
is approximately 12m below mean sea level (so that all numbers are positive). |
|
·
Closed Circuit Television |
·
A method of inspecting
pipes by sending a mobile camera along the length of the pipe to visually
record the interior. |
|
·
Community Plan |
·
See Long Term Council
Community Plan. |
|
·
Components |
·
Specific parts of an asset
having independent physical or functional identity and having specific
attributes such as different life expectancy, maintenance regimes, risk or
criticality. |
|
·
Condition-Based Preventive
Maintenance |
·
Preventive maintenance initiated
as a result of knowledge of an items condition from routine or continuous
monitoring. |
|
·
Condition Monitoring |
·
Continuous or periodic
inspection, assessment, measurement and interpretation of the resultant data,
to indicate the condition of a specific component so as to determine the need
for some preventive or remedial action. |
|
·
Core Asset Management |
·
Asset management which
relies primarily on the use of an asset register, maintenance management systems,
job/resource management, inventory control, condition assessment and defined
levels of service, in order to establish alternative treatment options and
long-term cash flow predictions.
Priorities are usually established on the basis of financial return
gained by carrying out the work (rather than risk analysis and optimised
decision-making). |
·
Corrective Maintenance |
·
The remedial actions
performed as a result of failure, to restore an item to a specified
condition. Corrective maintenance may
or may not be programmed. |
|
·
Critical Assets |
·
Assets for which the
financial, business or service level consequences of failure are sufficiently
severe to justify proactive inspection and rehabilitation. Critical assets have a lower threshold for
action than non-critical assets. |
|
·
Current Replacement Cost |
·
The cost of replacing the
service potential of an existing asset, by reference to some measure of
capacity, with an appropriate modern equivalent asset. |
|
·
Data Warehouse |
·
A system that is used to
centralise a group of disparate databases in an organisation to facilitate
access into each of those databases. |
|
·
Deferred Maintenance |
·
The shortfall in
rehabilitation work required to maintain the service potential of an asset. |
|
·
Demand Management |
·
The active intervention in
the market to influence demand for services and assets with forecast
consequences, usually to avoid or defer capital expenditure. Demand
management is based on the notion that as needs are satisfied expectations
rise automatically and almost every action taken to satisfy demand will
stimulate further demand. |
|
·
Depreciated Replacement
Cost |
·
The replacement cost of an
existing asset less an allowance for wear or consumption having regard for
the remaining economic life of the existing asset. |
|
·
Depreciation |
·
The wearing out,
consumption or other loss of value of an asset whether arising from use,
passing of time or obsolescence through technological and market
changes. It is accounted for by the
allocation of the cost (or revalued amount) of the asset less its residual
value over its useful life. |
|
·
Deterioration Rate |
·
The rate at which an asset
approaches failure. |
|
·
Economic Life |
·
The period from the
acquisition of the asset to the time when the asset, while physically able to
provide a service, ceases to be the lowest cost alternative to satisfy a
particular level of service. The
economic life is at the maximum when equal to the physical life; however
obsolescence will often ensure that the economic life is less than the
physical life. |
|
·
Failure Modes, Effects and
Criticality Analysis |
·
A technique for analysing
and evaluating a design to ensure that the application has the desired
reliability characteristics by obviating those critical failure modes through
employment of redundancy, providing alternate modes of operation, derating,
or any other means. |
|
·
Gap Analysis |
·
A method of assessing the
gap between a business’s current Asset Management practices and targeted
future objectives/practices. Also
called needs analysis or improvement planning. |
|
·
Geographic Information
System |
·
Software which provides a
means or spatially viewing, searching, manipulating, and analysing an
electronic database. |
|
·
Infrastructure Assets |
·
Stationary systems forming
a network and serving whole communities, where the system as a whole is
intended to be maintained indefinitely at a particular level of service
potential by the continuing replacement and refurbishment of its
components. The network may include
normally recognised ordinary assets as components. |
|
·
l/sec |
·
Litres per second. A measure of flow. |
|
·
Level of Service |
·
The defined service
quality for a particular activity (i.e. water) or service area (i.e. water
quality) against which service performance may be measured. Service levels usually relate to quality,
quantity, reliability, responsiveness, environmental, acceptability and cost. |
|
·
Life |
·
A measure of the
anticipated life of an asset or component;
such as time, number of cycles, distance intervals etc. |
|
·
Lifecycle |
·
The cycle of activities
that an asset (or facility) goes through while it retains an identity as a
particular asset i.e. from planning and design to decommissioning or
disposal. |
|
·
Lifecycle Cost |
·
The total cost of an asset
throughout its life including planning, design, construction, acquisition,
operation, maintenance, rehabilitation and disposal costs. |
|
·
Likelihood |
·
Used as a qualitative
description of probability or frequency. |
|
·
Long Term Council
Community Plan |
·
Prepared as a requirement
of the Local Government Act 2002, with the purpose of describing Council’s
activities, describing the ‘community outcomes’ (goals) of the Council area,
providing integrated decision-making and coordinating the resources of
Council. It provides a long-term focus
for the decisions and activities of the Nelson City Council, and is an
important basis for the accountability of the Council to the Nelson
community. It provides an opportunity
for the public to participate in decisions on activities to be carried out by
Council. It covers ten years planned
financial expenditure in detail. |
|
·
m3/day |
·
Cubic metres per day. A measure of flow. |
|
·
Main |
·
The pipework system that
conveys water from the intakes to each street. ·
Trunk mains bring water
from the intakes to the City secondary mains water to suburbs. ·
Reticulation mains (or
distribution) mains supply water into each street and are fitted with fire
hydrants. ·
Rider mains are smaller
pipes supplying one side of a street. |
|
·
Maintenance |
·
All actions necessary for
retaining an asset as near as practicable to its original condition, but
excluding rehabilitation or renewal.
Fixed interval maintenance is used to express the maximum interval
between maintenance tasks.
On-condition maintenance is where the maintenance action depends upon
the item reaching some predetermined condition. |
|
·
Maintenance Standards |
·
The standards set for the
maintenance service, usually contained in preventive maintenance schedules,
operation and maintenance manuals, codes of practices, estimating criteria,
statutory regulations and mandatory requirements, in accordance with maintenance
of quality objectives. |
|
·
Monitor |
·
To check, supervise,
observe critically, or record the progress of an activity, action or system
on a regular basis in order to identify change. |
|
·
Non-asset Solution |
·
A non-asset solution is
one where demand for an asset’s service is dealt with in a way other than by
additional investment in new resources and infrastructure. This might be by regulation (restricting
time of use and type of use), economic incentives (such as pricing structures
and subsidies), educational campaigns and provision of alternative ways of
meeting customers’ needs. Non-asset
solutions are usually included in a demand management strategy. |
|
·
Non-return Valve (NRV) |
·
A mechanical device that
allows water to flow in one direction only. |
|
·
NZ IFRS |
·
International Financial
Reporting Standard |
|
·
Optimised Decision Making
(ODM) |
·
An optimisation process
for considering and prioritising all options to rectify existing or potential
performance failures of assets. The process
encompasses NPV analysis and risk assessment. |
|
·
Optimised Depreciated
Replacement Cost (ODRC) |
·
The optimised replacement
cost after deducting an allowance for wear or consumption to reflect the
remaining economic or service life of an existing asset. ODRC is the surrogate for valuing assets in
use where there are no competitive markets for assets, or for their services
or outputs. |
|
·
Optimised Replacement Cost
(ORC) |
·
The minimum cost of
replacing an existing asset with modern equivalent assets offering the same
level of service. The optimisation
process adjusts the value for technical and functional obsolescence, surplus
assets or over- design. |
|
·
Payback Period |
·
The time it takes for the
cumulative benefits or savings of an investment to pay back the original
investment and other accrued costs. |
|
·
Performance Measure (PM) |
·
A qualitative or
quantitative measure of a service or activity used to compare actual
performance against a standard or other target. Performance measures commonly relate to
statutory limits, safety, responsiveness, cost, comfort, asset performance,
reliability, efficiency, environmental protection and customer satisfaction. |
|
·
Performance Monitoring |
·
Continuous or periodic
quantitative and qualitative assessments of the actual performance compared
with specific objectives, targets or standards. |
|
·
Planned Maintenance |
·
Planned maintenance
activities fall into three categories: ·
Periodic – necessary to
ensure the reliability or to sustain the design life of an asset. ·
Predictive – condition
monitoring activities used to predict failure. ·
Preventive – maintenance
that can be initiated without routine or continuous checking (e.g. using information
contained in maintenance manuals or manufacturers’ recommendations) and is
not condition- based. |
|
·
Pressure Reducing Valve
(PRV) |
·
A mechanical device that
modulates to maintain a constant lower pressure downstream irrespective of
flow. |
|
·
Rehabilitation |
·
Works to rebuild or
replace parts or components of an asset, to restore it to a required
functional condition and extend its life, which may incorporate some
modification. Generally involves
repairing the asset to deliver its original level of service (i.e. heavy
patching of roads, sliplining of sewer mains, etc) without resorting to
significant upgrading or renewal, using available techniques and standards. |
|
·
Renewal |
·
Works to upgrade,
refurbish or replace existing facilities with facilities of equivalent
capacity or performance capability. |
|
·
Remaining Economic Life |
·
The time remaining until
an asset ceases to provide the required service level or economic usefulness. |
|
·
Renewal/Replacement |
·
The complete replacement
of an asset that has reached the end of its life, so as to provide a similar
or agreed alternative, level of service. |
|
·
Repair |
·
Action to restore an item
to its previous condition after failure or damage. |
|
·
Replacement Cost |
·
The cost of replacing an
existing asset with a substantially identical new asset. |
|
·
Reservoir |
·
A large storage area for
water. May be uncovered, e.g. Maitai
Lake or covered, e.g. stressed concrete reservoirs at Thompson Terrace. |
|
·
Residual Value |
·
The net market or
recoverable value which would be realised from disposal of an asset or
facility at the end of its life. |
|
·
Rider Main |
·
A small diameter watermain
on the opposite side of the road from the principal watermain. |
|
·
Risk Management |
·
The application of a
formal process to the range of possible values relating to key factors
associated with a risk in order to determine the resultant ranges of outcomes
and their probability of occurrence. |
|
·
Risk Management Process |
·
The systematic application
of management policies, procedures and practices to the tasks of establishing
the context, identifying, analysing, evaluating, treating, monitoring and
communicating risk. |
|
·
Routine Corrective
Maintenance |
·
Corrective maintenance,
excluding emergency corrective and programmed corrective maintenance. |
|
·
Routine Maintenance |
·
Day to day operational
activities to keep the asset operating (replacement of light bulbs, cleaning
of drains, repairing of leaks, etc) and which form part of the annual operating
budget, including preventive maintenance. |
|
·
Sensitivity Analysis |
·
Testing of the variations
in the outcome of an evaluation by altering the values of key factors about
which there might be uncertainty. |
|
·
Service |
·
A service refers to the provisioning
of or the actual system of supplying a public need, ·
A water service (pipe) is
that section of the reticulation between the main in the street and the
property boundary. |
|
·
Stakeholders |
·
Those people and
organisations who may affect, be affected by, or perceive themselves to be
affected by, a decision or activity. |
|
·
Strategic Plan |
·
A plan containing the
long-term goals and strategies of the Council. Strategic plans have a strong external
focus, cover major portions of the Council’s operations and identify major
targets, actions and resource allocations relating to the long-term survival,
value and growth of the Council. |
|
·
Tank |
·
A small covered storage
area for water. Usually made of
concrete and of 23m3 capacity. |
|
·
Universal Metering |
·
Having water meters fitted
to all properties, i.e. ordinary (residential) and extraordinary (commercial,
industrial and other non-residential) users. |
|
·
Unplanned Maintenance |
·
Corrective work required
in the short-term to restore an asset to working conditions so it can
continue to deliver the required service or to maintain its level of security
and integrity. |
|
·
Useful Life |
·
May be expressed as
either: ·
The period over which a
depreciable asset is expected to be used, or ·
The number of production or
similar units (i.e. intervals, cycles) that is expected to be obtained from
the asset. |
|
·
Valuation |
·
Assessed asset value which
may depend on the purpose for which the valuation is required i.e.
replacement value for determining maintenance levels, market value for
lifecycle costing and optimised deprival value for tariff setting. |
ii)
iii)
APPENDIX B: WATER SUPPLY
CONSERVATION STRATEGY
·
MAITAI
(i)
Refer to Figure A. Please note that the letters below correspond
with the same letters in circles in the Figure.
A. Publicity will be run with the theme “Use
Water Wisely” between 1 January and 30 April each year.
B. When the water level is in this range water
will be released from the reservoir into the Maitai River as required by the
‘Surplus Water’ requirement of Resource Consent 960567.
The arrangement that
was established with the Nelson Catchment Board in 1987 is that surplus water
is released at a steady rate from the reservoir whenever the flow at the forks
drop below 300 litres per second and the lake level is above the acceptable
draw down line. The rate of release is
reviewed weekly.
C. When the water level is in this range
sprinkler restrictions will be put in place.
As a minimum restriction odd numbered properties would be able to water
on odd-numbered days and even numbered properties on even numbered days. Advertising will be run to remind the public
of these restrictions. Flushing of mains
will be reduced.
D. When the water level is in this range a
sprinkler ban will be put in place. The
only exception will be high value areas such as bowling greens, golf course
greens, cricket pitches and high profile public gardens. Advertising will be run to remind the public
of this ban.
E. When the water level is in this range
hosing restrictions will be introduced.
Depending on the severity of the situation these measures could include:
· A complete ban on residential hosing
· Restrictions on industrial and commercial use of water e.g. close down
automatic car washes, stop washing of cars in Sale Yards
· Approaches to major industries to explain the severity of the situation
and request co-operation through minimal water use.
· Increased advertising
· Establishment of a ‘Hot Line’ for residents to report non-compliance
with Water Restrictions.
· Water mains only flushed in response to water quality complaints.
F. If during the period 1 May to 30 October
the minimum river flow is reduced in accordance with Resource Consent 960567
the response shall be the same as for Item E.
NOTE:
i) This strategy outlines
the minimum response to falling water levels in the Maitai Reservoir. Response may be more severe depending on long
range weather forecasts.
ii) Water restrictions may
be put in place for other reasons such as fluctuating water pressures in the
reticulation caused by excessive demand.
i) When the natural flow
of the Roding River above the weir is 196 litres per second or less for two consecutive
days (5 year return period low flow), restrictions as in Section C will be put
in place.
ii) When the natural flow
of the Roding River above the weir is 160 litres per second or less (10 year
return period low flow), restrictions as in Section D will be put in place.
iii) When the natural flow
of the Roding River above the weir is 140 litres per second or less for two
consecutive days (20 year return period low flow), restrictions as in Section E
will be put in place.
Note: These measures are in accordance with the
requirements of Resource Consent No. 975374
(ii)
Extract from Civil Defence
Emergency Management Act 2002
·
s60. Duties of Lifeline
Utilities
Every lifeline utility must:
a) Ensure that it is able to function to the fullest possible
extent, even though this may be at a reduced level, during and after an
emergency;
b) Make available to the Director in writing, on request, its plan
for functioning during and after an emergency;
c) Participate in the development of the national civil defence
emergency management plans;
d) Provide, free of charge, any technical advise to any Civil
Defence Emergency Management Group or the Director that may be reasonably
required by that Group or the Director;
e) Ensure that any information that is disclosed to the lifeline
utility is used by the lifeline utility, or disclosed to another person, only
for the purposes of this Act.
·
s64. Duties of Local
Authorities
1. A local authority must plan and provide for Civil Defence
Emergency Management within its district.
2. A local authority must ensure that it is able to function to the
fullest possible extent, even though this may be at a reduced level, during and
after an emergency.
Extract from Nelson Tasman
Engineering Lifelines Project Report 2004
Civil Water Supply
Nelson City water supply is sourced from Maitai and Roding river
catchments. The water supply network includes dams, intake structures, water
treatment plant, tunnels, approximately 320km of pipework, 4 pump stations and
reservoir storage of approximately 13,300m3.
The Maitai Water supply scheme, including the Maitai earthfill Dam, was
commissioned in 1987 and is considered to be in good condition except for the
trunk main between the dam and Upper Brook Street. The Roding Weir was
commissioned in 1940 and is still in good operating condition. Gravel tends to
build up behind the weir and requires regular removal.
The Brook Dam, constructed in 1904 as Nelson’s original water supply
scheme, was decommissioned in 2000. The
Maitai trunk pipeline, constructed in 1963, is largely exposed and is
vulnerable to landslip with some sections positioned on benched platforms on
steep geologically unstable slopes and some sections passing through a tunnel.
The pipe is identified as at extreme risk from movement failure caused by
earthquake, landslide or settlement. This segment of the network is marked as
highest priority for mitigation measures to ensure ongoing water supply is
secure. The main is nominated for future replacement in the next five years.
The 65 year old Roding pipeline, which is rated at high risk due to
flooding potential, passes through a 2.7km tunnel under the Barnicoat range,
and the pipe is programmed to be replaced in 20 years. The Central City and Port Hills Cast Iron
mains are all at the end of their life and are all predominantly due to be
replaced by 2006/07. Atawhai and Stoke suburbs have more recent pipe systems
constructed of AC or PVC and are in good condition.
Reservoirs in Thompson Terrace have been seismically strengthened in
1992/93 and re-roofed in 2001/02. Stoke, Atawhai, and Observatory Hill
reservoirs are recent and all are in good condition. Pump stations in Princes Drive, Austen Ward
Heights, Van Diemen Street and Panorama Drive have been constructed since 1990
and are considered to be in good condition.
The recently constructed water treatment plant at the Tantragee Saddle
is situated close to slopes potentially prone to landslip, however the facility
is rated to be at low risk and risks to its operation are assessed in detail in
site specific geotechnical reports associated with construction design.
Walters Bluff (Atawhai) reservoir although sited on a splinter fault has
been specifically designed and constructed to mitigate risks from fault rupture
and earthquake shaking and is rated at low risk to these hazards.
Other mitigation measures identified for Nelson’s water network include
installation of seismic control valves on reservoirs to secure water reserves
in existing storage facilities and prevent loss through failed service lines.
Since this report was
completed the Stoke High Level Reservoir has been completed in 2010/11. The reservoir is located on the York/Brook
saddle above the land fill site and has a storage volume of 2500 cubic
metres. An additional 440m3
reinforced concrete reservoir has been constructed at Observatory Hill in 2014.
This takes Nelson’s storage to 22,340m3.
The Christchurch
Earthquakes of 2010 /2011 lead to significant damage to that city’s
infrastructure including water storage reservoirs and pipe network from direct
shaking and liquifaction. Recognising this, and the results of other natural
hazard investigation post the Nelson storm events of December 2011 and April
2013, Nelson City Council is reassessing the risk to the network from
earthquakes (including liquefaction, tsunami and direct shaking), flooding,
storms and sea level rise.
v)
APPENDIX D: NELSON CITY COUNCIL ADVANCED
ASSET MANAGEMENT GAP ANALYSIS - WATER
Table A: Gap
Analysis - Water
A – Advanced asset
management criteria met
C – Core asset
management criteria only met
|
Asset Management Attribute |
‘Core’ Asset Management
Planning Criteria |
‘Advanced’ Asset Management
Planning Criteria |
Current |
Desired |
Comment |
Time |
|
1.
Description of Assets |
An
adequate description of the asset, both physically and in financial terms,
with the ability to aggregate and disaggregate information. State
the remaining useful lives of assets. A
financial description of the assets that is linked to the physical
description and meets the requirements of: · Financial Reporting · Valuation Standards, augmented by the NZ Depreciation
and Valuation Guidelines |
As
for ‘Core’ plus · A reliable physical inventory of assets at both an
individual asset level and at a network level. This would include: Physical attributes such
as location, material, age etc. |